Company "Intergal-Bud": the dynamics of construction on 10.25.17

  • 25/10/2017

Company "Intergal-Bud": the dynamics of construction as of 10.25.17

 

Residential complex "Volodimirsky"

Foundation device - 100%.

Basement walls waterproofing - 100%.

Completed the overlap of the 3rd floor.

The construction of vertical walls - the 4th floor.

 

Residential complex "Syretsky Gardens"

House number 1

1st Section: Completed the construction of the 3rd floor. The construction of the 4th floor has begun. Laying concrete bricks.

2nd Section: work is underway on the 2nd floor.

 

House number 2

Concrete preparation for the foundation tile

 

House number 3

Cleared the area.

 

House number 4

Dug a pit.

Completed soil testing piles.

 

Residential complex "Yaskravy"

 

House number 4:

Finished installing a fire alarm.

Completed installation of low-voltage systems.

Installation of the ventilation system is completed.

Internal power supply system - 100%.

Water supply and sewage system - 100%.

Device on-site networks - 100%

Fire Network - 99%

Installation of low-voltage networks - 99%

Landscaping completed.

 

House number 5:

The monolithic frame device is 100% complete.

Brickwork completed.

Installation of window structures is completed.

Plumbing work - 99%.

Electrical work - 98%.

Ventilation and smoke removal - 88%.

Low-voltage systems - 90%.

Plaster walls - 100%.

Floor screed - 100%.

Roof installation - 99% (waterproofing continues).

Installation and commissioning of elevators - 79%.

 

House number 6:

In section number 1:

The construction of the 10th floor is completed.

Readiness of the vertical of the 11th floor - 50%.

Basement waterproofing - 85%.

Basement insulation - 80%.

 

In section number 2:

The construction of the 10th floor is completed.

Vertical of the 11th floor - 80%

Basement waterproofing - 85%.

Basement insulation - 80%.

 

In section number 3:

Completed construction of the 11th floor -75%.

Basement waterproofing - 85%.

Basement insulation - 80%.

 

House number 7:

The device of the monolithic frame section number 1 - 98%. In work technical floor.

The device of the monolithic frame section number 2 - 100%. Completed.

Brickwork is being carried out: section No. 1 - 64% (13-24th floors in work), section No. 2 - 32% (in work 8-12 floors).

Completed installation of ventilation ducts of the 1st and 2nd sections.

Work has begun on ventilation and smoke removal - 10%.

Started plastering of walls and screed equipment.

Installation of window structures: on sections 1 - 30% (4-14 floors), on sections 2 - 22% (2-8 floors).

Plumbing work - 22%.

Electrical work - 17%.

 

Residential complex "Lake Guy Gatne"

 

House number 2:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 100% (masonry attic floor).

The device of monolithic floor slabs - 100%.

The device partitions - 100%.

Roof - 60%.

Facade - 60%.

Interior decoration - 50%.

 

House number 3:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 95% (masonry attic floor).

The device of monolithic floor slabs - 100%.

The device partitions - 100%.

Roof - 50%

Facade - 40%

Interior decoration - 17%.

 

House number 4:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 98% (masonry attic floor).

The device of monolithic floor slabs - 100%.

The device partitions - 100%.

Facade - 20%.

Interior decoration - 5%.

 

House number 5:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 50% (5th floor).

The device of monolithic floor slabs - 50%.

The device partitions - 50%.

 

Residential complex "Demeevka"

 

House number 2:

Concrete floor slab 20th floor.

On the roof, work is underway on arranging parapets and reinforced concrete structures of machine rooms.

Mounted ventilation units on the level of the 19th floor.

Installation of staircases - 100%.

 

Finished brickwork on floors 1-13.

Work continues on the brickwork on floors 14-17.

Installation of risers for water supply, heating and domestic sewage is in progress - 50%.

Readiness of monolithic structures of input groups - 99%.

Completed installation of windows 1-4-th floors.

Installation of windows of 5-7th floors is in progress.

Distribution of horizontal drives for heating and water: floors 2-6.

Electrical installation works: 2-6 floors.

 

Residential complex "Park Lakes"

 

House number 11:

The construction of external walls and partitions is completed.

The construction of internal walls and partitions is completed.

Roof installation is completed.

Installation of window structures is completed.

 

Facade installation is complete.

Plaster walls finished.

Plumbing works - 85% installation of meters, pressure testing of the system, commissioning of individual heat points.

Floor screed is finished.

Installation of the internal power supply system - work is underway on the installation of the switchboard and connecting the house to a permanent circuit.

Electrical installation systems - 95%. Work is underway on the installation of the electrical panel and connecting the house to a permanent circuit.

Low-voltage systems - 96%. The commissioning and installation of sensors are completed.

Ventilation and smoke removal - 97%. Before the end, only the commissioning work remains.

 

Installation of elevators - 93%. Commissioning is underway.

Finishing of common areas - 98%. Correction of comments.

Landscaping - 98%. Correction of comments.

 

House number 12:

The device is a monolithic frame - performed on the technical floor (97%).

The device walls and partitions - performed on the 17-23rd floors (67%).

The device ventilation channels - is performed on the 19th floor (68%).

Installation of window structures - is carried out on the 11-12th floors (41%).

Plumbing works - vertical up to the 19th floor (37%).

 

Electrical work - wiring done up to the 8th floor (33%).

Ventilation and smoke removal - performed on floors 3-8 (11%).

Low-voltage systems are performed on the 2nd floor (8%).

Plaster walls - performed on floors 8-10 (30%).

Equipping common areas with wallpaper and tiles - finished 2nd floor (4%).

 

House number 13:

The monolithic frame is made on the 18th to 19th floors (67%).

Started equipping of walls and partitions (2-3rd floors).

 

The device ventilation channels - is performed on the 14th to 16th floors (51%).

Entrance group - partly made iron-concrete frame (11%).

 

Residential complex "Traditsia"

 

House number 2:

The device is a monolithic slab of 25th floor.

The brickwork is on the 13th, 14th, 15th, 17th floor inclusive.

 

House number 3:

Facade work - 70%.

Plumbing works - from the 1st to the 25th floors.

Installation of heat meters of the 1st zone is completed.

Wiring availability - 80%.

Improvement of the local area - 40%.

External networks - 80%.

Roof - 80%.

Interior decoration of apartments - 60%.

 

Residential complex "Nyvky Park"

 

House number 1:

The monolithic frame device is complete.

The device walls and partitions completed.

Installation of window designs is completed.

The installation of internal engineering continues.

Section A - floor screed and plaster on the 16th floor

Section B - screed and plaster completed;

Section B - screed and plaster completed.

Work continues on interior decoration:

Door installation performed: sec. A - 14 fl. B, In section - 13 fl.

The device facade performed by 75%.

Work is underway on the installation of elevators.

Work is underway on the structure of the metal structures of the entrance groups.

Work is underway on the design of external engineering networks.

Inside the yard work is carried out on the device improvement.

 

House number 2:

The monolithic frame device is complete.

The device walls and partitions completed.

Installation of window designs is completed.

Work continues on internal engineering.

Section G - screed and plaster completed;

Section D - floor screed on the 16th floor; plaster on the 12th floor;

Door installation per second. G - completed. on sec.D on 9 fl

Work continues on interior decoration:

Work is underway on the installation of elevators.

Work is underway on the device facade.

Work is underway on the design of external engineering networks.

 

House number 3:

In sections G, D, W, work is underway to build a monolithic frame on the 15th floor.

The laying of the walls continues: works are being carried out on the 8.9th floors of sections G, D, J.

 

House number 4:

In sections E, B, C, a monolithic frame of the 12th floor is maintained.

The laying of the walls continues: sections B, C on the 3,4,5th floor. Section E on floors 3,4,5.

 

Residential complex "Otradny"

 

House number 1:

The monolithic frame device is 100% complete.

The brickwork of the external walls is 100% complete.

Work is underway on painting the facade - 90%.

Plastering work performed at 95%.

The tie is made to 95%.

Finishing work is underway at the MZK.

Work is underway on the arrangement of the roof - 30%.

Improvement works are underway - 5%.

 

House number 2:

The monolithic frame device is 100% complete.

Work is underway on the installation of brickwork: on the 16th floor and roof.

Work is underway on the arrangement of the roof - 70%.

Plastering works are underway on the 4th floor.

Electrical and plumbing works are underway on the 6th floor.

 

House number 3:

Reinforcement and concreting performed up to the 17th floor.

Brick laying on the 10th floor.

 

House number 4:

Work is underway on the reinforcement of the 8th floor slab.

Brickwork is used on the 2nd floor - 80%.

 

House number 5:

Work is underway to reinforce the slab of the basement floor.

 

Residential complex "Teremki"

 

House 1 (1st phase of construction).

The device is a monolithic frame - the overlap of the 20th floor, installed vertical elements of the 21st floor.

Brick masonry completed on floors 1-14.

 

House 2 (2nd stage of construction).

Section 2. The device is a monolithic frame - completed the overlap of the basement.

Section 3. Monolithic frame device - installation of vertical elements of the basement is completed.

 

House 2A (3rd construction stage).

The pit is prepared for testing the piles.

 

Residential complex "Malachite"

 

3rd house:

In the sections 302-303, internal finishing works from the 2nd to the 9th floor were carried out - 100% completed.

Began to landscaping recreation areas on the roof.

Work is done on the installation of external engineering networks:

- domestic sewage K1 - 90%.

- Rainwater drain K2 - 90%.

- plumbing B1;

- electricity grid

 

4th house:

Monolithic frame, section 404 - 100%.

Work is underway on the brickwork from the first to the sixth floors of section 404.

Work is underway to install vertical reinforced concrete structures on sections 405-406, the mark is 0.100.

Parking P1. Overlap monolithic slabs.

Parking P2. Overlap monolithic slabs.

Section 401. The foundation is made at 100%, the mark - 3.100.

Section 402-403. Work is underway on the foundation.