PROGRESS OF CONSTRUCTION AS OF 30.11.18

  • 30/11/2018

RC "Volodymyrskyi"

Pouring of slab on the technical floor is completed, parapet is partially poured too. Installation of reinforcing frame and formwork of the vertical structures of the technical floor is in progress.
Brickworks on the basement,1,
4, 14, 15, 16 and 17 floors. Works on concealed wiring on typical residential floors inside monolith structures of the slab over the 24th floor are in progress. Installation of lighting protection system is carried out solely in monolith structures.

Installation of still fencing of staircases – 6th floor.


RC “Syretski Sady” 

Building No. 1
Completion of installation of windows and balconies – 99%.
Façade – heat insulation of walls – 80%.

Entrance groups – basements are completed

Building No. 2 
Brickworks – 1st to 16th floor.

Roofing works are completed in 3 sections - 1st layer.

Windows – 2-4floors (section 3)

Building No. 3 
Brickworks – 1st to 6th floor


Building No.4
Brickworks – 1st to 16th floor.

Windows – 2nd to 8th floor.

Building No.5
Testing of pile field is completed. Foundation is completed.

 

RC “Yaskravyi”
Building No.6 
Works on installation of walls, partitions, brickworks (external -92.5%, internal – 97.4%) are in progress. 
Installation of window structures-76%
Plumbing works –44.8 %

Electric wiring works – 19.5%

Ventilation and smoke exhaust system – 5.6%

Low-current systems – 10.4 %
Wall plastering – 27.5%
Installation of screed – 38.4%

Decoration of GUPs – 15.3%
Installation and adjustment of elevators– 70%
Façade works – 75.3%

Roofing – 88.3%
Entrance group – 48.3%

 

Building No. 7 
Plumbing works – 98%
Electric wiring works – 92%
Ventilation and smoke exhaust system – 93%
Low-current systems – 95%
Finishing of GUPs – 99%
Installation and adjustment of elevators – 91%
Development of adjoining territory – 90%

 

RC “Parkovi Ozera” 

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96%

Plumbing works – 56%
Electric wiring works – 46%
Ventilation and smoke exhaust system – 26%
Low-current systems – 33%
Wall plastering –84% 
Installation of screed -75%

Finishing works at GUPs – 37%

Installation and adjustment of elevators – 90%
Façade works – 96%
Façade heat insulation - 97%
Façade finishing – 96%
Roofing – 94%.
Entrance group – 77%

 

RC “Ozernyi Hai Gatne” 
 

Building No.2
Internal decoration -99%
Development of adjoining territory -99%

Building No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration - 99%.

Building No. 5
Internal decoration – 92%.
Glazing – 99.9%
Façade – 99.85%

Building No.6
Monolith works : 

Section 1: 7th floor – 60%

Section 2: 77th floor - 80%

Section 3: 8th floor – 10%

Building No.9
Gravel bedding – 80%

Concrete bedding - 30%

 

RC “Traditsiya” 

Building No.2
Active finishing works inside apartments are ongoing.


Building No.4
Vertical element of the 12th floor, slab over the 12th floor are in progress.

Brickworks – 6th floor and basement.
 

RC “Malakhit”

Building No.4
Section 401 – Brickworks on 20-25 floors.
Sections 402- 403 – facade works – 99%

Section 403 - finishing works - 2-8 floors

405-406 – finishing works are ongoing: 99%

Façade works - 98%

Works on waterproofing of parking areas are ongoing. Development of promenade zone – 40%.

Works on development of the territory of building No.4 – 40%

Building No.
5
Pouring of the slab over the basement is in progress.

 

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases in all sections is in progress.
Finishing works at GUP: section
Ж – 1st floor.

Façade works are about to be completed. Works on development of adjoining territory are ongoing. Works on arrangement of heat supply system are in progress.

Building No.4
Plastering works at GUPs: B – on the 17th floor.
Works on adjustment of elevators are ongoing.

Finishing works and tiling at GUPs: section Б – on the 17th floor, section В – on the 17th floor.

Works on installation of doors - section В – 17th floor.
Installation of drywalls and paint works in the halls of the first floors at section Е, Б, В are in progress.

Building No.5
Brickworks on the floors 8
9, 11, 12  of section A; section Е - on the 9, 10, 11, 12 floors and basement. Section  Б - on the 7, 8, 10, 11 floors and basement.

Brickworks for ventilation shafts on the roof at sections A and E are in progress.

Water proofing of basements at sections А, Б and Е is in progress.

Back filling of the pit is in progress.

Installation of windows: 3nd to 6th floor at sections A, Б and E.   

 

Building No.6
Installation of vertical elements of the 15th floor at section Г
Installation of vertical elements of the 1
5th floor at section E.
Installation of slab over the 1
4th floor at section Д*
Brickworks on the4, 5, 6, 7 floors in section Г; on
5, 7, 8 floors at section Е and on 7th and 8th floors of section Д *.

Works on water proofing of basements are in progress.

Works on backfilling of the pit are ongoing.

Building No.7
Excavating works for the pit are ongoing.

Works on reinforcement of the basement slab at section E1is ongoing.

Installation of vertical elements of the basement at section B is in progress.


Building No.8
Works on installation of vertical elements of the 1st floor  at section Г*.

Works on installation of vertical elements of the 1st floor  at section Б*.

Works on installation of the slab over the basement at section B is in progress.

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments  (1,
9, 12, 13 floors).

Building No.3 

Roofing works are ongoing.

Installation of metal and plastic windows - 98%.
Façades works are in progress  – 98% (works are carried out on the basement).

Wall plastering on 9, 14 floors (apartments) is ongoing.

Works on installation of suspended ceiling made of plasterboards on 1st and 16th floors are in progress.
Works on electric wiring and plumbing are in progress.
Works on laying ceramic tiles at the staircases are ongoing.

Territory development works are in progress.

Painting works at GUPs and staircases (1-10 floors).
Installation of decorative plaster on 4, 5, 10, 12 floors are in progress.

Roofing works are ongoing.
 

 

Building No.4 
Installation of metal and plastic windows – 98%
Façades works are in progress – 95%

Works on electric wiring and plumbing are in progress.

Installation of cement and sand screed on 9, 14, 15 floors.

Roofing is in progress.

Wall plastering on 5, 8, 13 floors (turn-key apartments), as well as at GUPs, 10th and 11th floors.

Painting works at GUPs on the 3d to 16th floors are in progress.

Ceramic tiling works on the 17th (GUP, IHU, pumping station) are in progress.

Installation of entrance doors at apartments and technical premises is in progress.

Development of the territory is ongoing.

 

 

Building No.5 
Works on installation of metal and plastic windows are ongoing – 92%.

 

RC “Teremky” 

1st stage – Works on heat insulation of the building are in progress. Painting façade works are ongoing. Works on installation of internal mains and plumbing works are in progress. Installation of basket holders for air conditioner units. Connection of communication networks to the building.

Stage 2, section 2 – Water-proofing of the basement is ongoing. Roofing works are in progress. Plastering works inside the apartments on the 13th floor is in progress. Electric wiring works on the 14th floor are in progress.

Pouring of screed on the 2nd floor. Works on heat insulation of the building are in progress.

Stage 2, section 3 – Installation of windows on 24 to 25th floor is in progress. Heat insulation of the roof of the building is ongoing. Wall plastering works inside apartments on the 13th floor. Electric wiring works on the 14th floor are in progress. Pouring of screed on the 2nd floor.

Stage 3, section 4 – slab over the vertical elements of the 23th floor is installed.

Stage 3, section 5 – slab over the vertical elements of the 22nd floor is in progress. Brickworks on 33,11 and 12 floors inclusive are in progress.
Stage 3, section 6  - slabs over the vertical elements of the 2nd to 10th floor inclusive are installed.