Dynamics of construction on May 25

  • 25/05/2017

«Bright» RC

 

House number 4:

 

Installation and commissioning of elevators - 96% (arrangement of technical elements).

The arrangement of the roof - 96,5% (left to lay the upper ruberoid layer).

Facade installation - 99% (work is almost completed).

Pure finishing of public places - 87% (painting, applying decorative plaster, rubbing with ceramic tiles on the 1st floor).

Installation of ventilation system - 99% (prepared for commissioning).
The system of internal power supply - 97,5% (it remains to install powerplants and light bulbs in public places).
The system of internal heating - 99% (left to install the batteries in the basement).
The system of internal water supply and sewerage - 98% (the establishment of comb, in apartments with the finishing left to install washbasins).
Installation of fire alarm - 75% (installation of meters).
Installation of low-current systems - 75% (installation of the control panel).
Interior layout - 90%.
Arrangement of entrance groups - 65% (mounting of metal structures, decoration with ceramic granite).
Improvement of the territory - 70% (arrangement of sidewalks, access roads, asphalting territory continues).
 
House number 5:
 
The arrangement of the monolithic frame is 100%.
Brick masonry is made on 90% (the brick masonry remains under the lockers).
Installation of window constructions - 98% (work is almost completed).
Plumbing works - 70% (expansion of heating pipes on floors).
Electrical work - 65% (decomposition of electric cable on floors).
Weak-current systems - 58% (expansion of the wiring on the floors).
Plastering of walls - 36%.
The tension of the floor is 65% (in the 19th floor).
The laying of the brickwork on the roof is 100%.
Roof installation - 44% (left to install waterproofing).

 

House number 6:
 
In sections №1, №2 and №3 the work on the arrangement of the pile field is made 100%.
Concrete preparation for the foundation plate was completed in Sections No.2 and No.3. The reinforcement of the base plate began on section №3. Mounting of tower cranes continues.
 
House number 7:
 
The arrangement of the monolithic frame of section №1 - 42%. In work 13-14 th floor.
The arrangement of the monolithic frame of section №2 - 40%. The work is 14th floor.
Bricklaying is carried out: section number 1 - 9% (in the 2-5 th, 7 th floors), section number 2 - 4% (in work 2-3rd floor).
Installation of ventilation ducts is carried out: in sections №1 and №2 works are executed on 27% (9-10-th floors).

 

«Ozerny Gai Gatne» RC
 
Building number 1: all construction work completed.
 
House number 2:
Foundation of the foundation - 100%.
Waterproofing the walls of the cap - 100%.
Arrangement of walls - 45% (brickwork on the 3rd floor).
Arrangement of monolithic slabs of overlap - 40% (3rd floor).
Arrangement of partitions - 30% (2nd floor).
 
House number 3:
Foundation of the foundation - 100%.
Waterproofing the walls of the cap - 100%.
Arrangement of walls - 45% (brickwork on the 3rd floor).
Arrangement of monolithic slabs of overlap - 40% (3rd floor).
Arrangement of partitions - 30% (2nd floor).

 

House number 4:
The foundation of the foundation has been completed.
A screed for waterproofing is executed for installation of a base plate.
Arrangement of the walls of the basement - 30% (poured down the walls of the basement).
 
House number 5:
Foundation of the foundation - 100%.
Arrangement of the walls of the basement - 50% (poured down the walls of the basement).
 
«Demiivka» RC
 
Building number 1: all construction work completed.

 

House number 2:
 
The mounting of the ceiling floor of the 7th floor continues.
Ventilated blocks are mounted on 3-4 floors.
Backflow continues.
Completed works on insulation and waterproofing of the ground floor. The installation of monolithic structures of entrance groups, entrances to basements, and so on.
 
“Park Lakes” RC
 
House number 11:
 
Arrangement of walls and partitions (masonry) - executed on the basement - on the 21st, 23-24th floors; work is done on the 22nd floor (85%), on the 25th-26th floor - 55%. The laying on the roof is made by 10%.
Installation of window constructions continues on the 25th floor.
Plastering of walls is executed on the basement-17th floors; on the 19-20th floors completed 95%; works on the 18th floor - 20%, on the 21st and 23rd floors - 50%.
Mounting of the system of internal electric power supply - work is carried out on high-voltage risers.
Mounting of internal heating systems - mounting of pipes on floors 1-25, horizontally diluting on floors 1-12.
Installation of the system of internal water supply and sewerage - mounting of the pipe of the water supply to the 25th floor, the sewerage is completed to the 25th floor.
The tension of the floor is executed on the basement-8th floors. The works are on the 9th-10th floors (90%).
The installation of the facades (insulation of balconies), ventilation ducts and mounting of elevations continues.

 

House number 12:
 
The arrangement of a monolithic frame is carried out on the 14th-15th floors. On sections №1 and №2 - reinforcement and concreting of vertical elements of the 15th floor, on section №3 - reinforcement of slab floor over the 14th floor.
Arrangement of walls and partitions:
in section number 1 on the ground floor (100%), on the first floor (40%); in section №2 - 2nd floor (30%), socle (10%); in section number 3 - 2nd floor (95%).
 
House number 13:
 
The arrangement of the main pile field, including piles of tower cranes, has been completed.
The base plate is made on all 3 sections.
Monolithic frame is in progress:
in sections №1 and №2 reinforcement and concreting of floor slabs over the first floors are carried out;
in section №3 reinforcement and concreting of vertical elements on the 2nd floor are carried out.
 
«Traditsia» RC
 
House number 3:
 
Arrangement of the floor slab of the 26th floor.
Brick masonry on the 18-22th floors.
The installation of window constructions is carried out on the 8th-11th floors.
Electrotechnical works are carried out on 5-9th floors.
Installation of pipe-laying of heating and water supply on 4-6th floors is underway.
Mounting of sanitary risers is ongoing (in works 14-26 floors).
Plastering of walls - in the work of the 5th, 6th and 8th floors.
 
House number 2:
 
The placement of the floor slab is on the 1st floor.

 

«Malakhit» RC
 
The following works are carried out on the construction site of the house №3:
Installation of a monolithic frame:
section 301 - 99% (concreting of slabs of overlappings of elevator shafts and stairs);
sections 302-303 - 100%;
section 304 - 99% (work on the installation of a plate of a staircase march of the technical floor ends).
The seating of the waterproofing of the cap is practically completed:
Section 301 - 98%;
sections 302-303 - 98%;
section 304 - 95%.
Arrangement of walls and partitions:
section 301 - 60% (laying on the 16th floor);
sections 302-303 - 100%;
section 304 - 60% (laying on the 18th floor).
Installation of window constructions:
section 301 - 45% (10th floor);
Sections 302-303 - 99% (works with the glazing of process holes for the submission of materials);
section 304 - 42% (9th floor).
Reverse falling asleep - it was left to perform vertical planning under the finishing of the accomplishment:
Section 301 - 90%;
section 302-303 - 90%;
section 304 - 90%.
 
House number 4:
 
Work is being done on the installation of the foundation pit. Concreteing of vertical elements to the mark "0" is carried out on section 404.
Work is under way on the installation of the pile field of sections 405 and 406: pile drilling continues. The foundation of the parking lot №4 is wound up, the monolithic walls continue to be erected.
 
«Nyvky-Park» RC
 
House number 1:
 
The structure of the monolithic frame is complete.
Arrangement of walls and partitions:
section A - 16th and technical floor in work, sections B - 13-15th floors in work, section B - 12-16th floors.
The mounting of window constructions continues (in the work of the 8th floor).
The installation of internal engineering continues.
Work is ongoing on the interior decoration of the premises: a screed of the floor and plastering on the 5-6th floors.
The installation of the roof in Section A continues, the installation of the roof in Section B has begun.
 
House number 2:
 
Installation of a monolithic frame:
section G - the arrangement of parapets is completed, section D - the installation of floor slabs of the high-rise building.
Arrangement of walls and partitions:
Sections G and D - 5th floor.
The mounting of window constructions continues (in the work of the 1st-2nd floors).

 

House number 3:
 
In the sections "F" and "D" - work is being done on the arrangement of the basement ceiling slab; in section G works on the arrangement of vertical basement structures.
 
House number 4:
 
The foundation plate was started in sections B, B, E.
In Sections B and B, the laying of foundation slabs continues; in section E - the arrangement of vertical elements of the basement.

 

«Otradny» RC
 
House number 1:
 
The structure of the monolithic frame is 80%.
Brickwork: 1st floor - 100%, 2nd floor - 96%, 3rd floor - 96%, 4th floor - 96%, 5th floor - 90%, 6th floor - 96% , 7th floor - 40%, 8th floor - 60%, 9th floor - 80%.
The mounting of window constructions continues: works on the 4th-6th floor.
Backflow is complete.
Plastering of walls - work is carried out on the 2nd floor.
 
House number 2:
 
The installation of the monolithic frame is 75%.
Works on laying brickwork are underway: on the 1 st and 2 nd floors of the work performed 100%, on the third floor - 80%, on the 4th floor - 60%.
Work is ongoing on the installation of waterproofing the basement floor.

 

House number 3:
 
Reinforcement and concreting was performed on 32% (in the work of the 7th floor).
Work is ongoing on the installation of waterproofing the basement floor.
 
House number 4:
 
The foundation slab is executed. Reinforced ground floor. Work is under way on laying a foundation slab.
 
House number 5:
 
The pit is complete. Preparation for piling is under way.
 
«Teremki» RC
 
On the first stage of the construction of the complex there is an installation of the ceiling between the 2nd and 3rd floors.
In the second stage of construction piling tests are ongoing.