Construction Progress of Intergal-Bud Projects in September 2026

Intergal-Bud continues active construction across all of its residential developments. In September, a wide range of works was underway at the construction sites — from foundations and reinforced concrete frames to engineering systems installation and finishing works.

CITY HUB has entered the final stage of construction. At Polar Park, interior finishing and engineering systems installation are already underway in Building No. 1, while the reinforced concrete frame of Building No. 2 has been completed. At Kaskad Residence, the structural frames of the first two sections are being constructed, while the monolithic works on the shelter are almost complete. At INTERGAL CITY, landscaping, engineering and finishing works are ongoing. At Sky Avenue, façade insulation works are underway on Building No. 3, while at Novi Syretski Sady, foundations are being prepared for the new buildings.

Read more about the construction progress in our monthly report.

CITY HUB Residential Complex, 8–10 Mokra Street

A residential complex that harmoniously combines the convenience of urban living with the comfort of private space. Residents will enjoy spacious apartments, underground parking, children’s and sports areas, as well as well-developed on-site infrastructure. Planned construction completion — Q3 2026.

Building 2

  • Entrance areas — 88.5%
  • Internal brick walls and partitions — 98%
  • Roofing — 96%
  • Façade works — 93.5%
  • Boiler room and gas supply — 48%
  • Electrical switchboard installation — 99%
  • Individual heating substation installation — 47.5%
  • Pumping station installation — 96%
  • Plumbing works in the basement, apartments and common areas (water supply, sewerage, heating) — 99%
  • Electrical installation works in apartments, common areas and basement — 99%
  • Ventilation and smoke extraction — 90%
  • Fire protection system — 90%
  • Engineering equipment automation — 90%
  • Screed in common areas and apartments — 100%
  • Wall plastering in apartments — 99%
  • Elevator installation and commissioning — 97%
  • Installation of small metal structures — 96%
  • Outdoor lighting — 70%
  • Landscaping and greenery — 52.5%

Building 2 parking:

  • Entrance areas — 90%
  • Electrical installation works — 94%
  • Electrical switchboard installation — 99%
  • Plumbing works — 96%
  • Ventilation and smoke extraction — 96%
  • Fire protection system — 92%
  • Metal-plastic window installation — 100%
  • Parking markings — 85%
  • Landscaping and greenery — 65%

Kaskad Residence, 5A Prychalna Street

A comfort-class residential complex located just 200 metres from the Dnipro River. It combines cascading architecture, a gated territory, developed infrastructure, full autonomy and energy independence. All apartments are delivered with White Box finishing.

Section 1:

  • Tower crane installation — 100%
  • Monolithic reinforced concrete frame — 30%

Section 2:

  • Tower crane installation — 100%
  • Monolithic reinforced concrete frame — 7%

Section 3:

  • Excavation pit — 100%

Shelter No. 1:

  • Excavation pit — 100%
  • Base preparation and concrete blinding — 100%
  • Foundation slab — 100%
  • Monolithic protective walls and floor slab — 98%
  • External waterproofing and backfilling — 55%

Polar Park Residential Complex, 2 Petra Kalnyshevskoho Street, Kyiv

Building No. 1:

  • Walls and partitions — 98%
  • Metal-plastic structures installation — 99%
  • Internal water supply and sewerage systems — 77%
  • Internal heating system — 78%
  • Internal power supply system — 77%
  • Fire protection systems — 68%
  • Wall plastering — 67%
  • Floor screed — 52%
  • Common-area finishing — 36%
  • Elevator installation and commissioning — 29%
  • Façade works — 26%
  • Roofing — 62%

Building No. 2:

  • Monolithic frame — 100%
  • Walls and partitions — 75%
  • Ventilation ducts and precast staircases — 100%
  • Metal-plastic structures installation — 41%
  • Internal water supply and sewerage systems — 18%
  • Internal heating system — 18%
  • Internal power supply system — 22%

Building No. 3:

  • Monolithic frame — 94%
  • Walls and partitions — 52%
  • Ventilation ducts and precast staircases — 90%
  • Metal-plastic structures installation — 18%

Parking:

  • Monolithic parking structure — 98%
  • Walls and partitions — 35%

Sky Avenue Residential Complex, 3 Sviatoslava Khorobroho Street

A comfort+ residential complex located near Sevastopolska Square. The project comprises six residential buildings with commercial premises on the ground floors and cosy inner courtyards featuring children’s and sports areas and recreation zones.

Building No. 3:

  • Waterproofing of the underground basement section — 62%
  • Entrance areas — 85%
  • External ceramic block walls — 97%
  • Internal ceramic block walls and partitions — 94%
  • Metal-plastic windows and doors installation — 89%
  • Electrical works in apartments, common areas and basement — 42%
  • Roofing — 53%
  • Elevator equipment installation — 27%
  • Plumbing works in the basement, apartments and common areas (water supply, sewerage, heating) — 42%
  • Engineering systems in fully finished apartments — 23%
  • Ventilation and smoke extraction — 15%
  • Fire protection system — 46%
  • Screed in common areas and apartments — 37%
  • Wall plastering in common areas and apartments — 47%

Parking No. 2 (under Building No. 3):

  • Parking waterproofing — 41%
  • Backfilling — 50%

Children’s educational facility:

  • Brickwork — 99%
  • External wall waterproofing — 95%
  • Backfilling — 90%
  • Roofing — 36%

Parking of Syretski Sady Residential Complex, 10D Ivana Vyhovskoho Street

  • Monolithic frame — 28%

Novi Syretski Sady Residential Complex, 10D Ivana Vyhovskoho Street

A comfort-class residential development based on the “city within a city” concept. It is an extension of the large-scale Syretski Sady project, featuring updated architectural and façade solutions, modern infrastructure, and a new vision for recreation areas, children’s playgrounds and sports facilities.

Building 11:

  • Excavation pit completed
  • Works on the foundation pile field are underway

Building 12:

  • Pile testing is underway

INTERGAL CITY Multifunctional Complex, 16B Staronavodnytska Street

A premium multifunctional complex combining elegance, futuristic architecture, advanced technology and a unique location in Pechersk — the centre of the capital’s business, cultural and investment life.

Tower A:

  • Ventilated façade systems — 99%, glazed façade systems — 98%
  • Internal plumbing systems: K1 — 99%, K2 — 99%, T1/T2 — 99%, V1 — 99%
  • Main heating pipelines with distribution manifolds — 99%
  • Ventilation systems installation — 96%
  • Air-conditioning systems installation completed — 100%; equipment units installation — 15%
  • Fire suppression system installation — 98%
  • Access control and structured cabling systems — 96%
  • Electrical installation works — 98%
  • Boiler room installation — 97%
  • Terrace surfacing — 93%
  • Individual heating substation and heating module installation — 97%
  • Apartment door installation — 20%
  • Finishing works on technical floors (floors 23–25) — 90%
  • Engineering rooms: electrical switchboard room — 97%, pumping station — 97%
  • Common-area finishing (floor tiles, wall panels, access hatches) — 50%
  • Firestop penetrations — 90%
  • Terrace railing installation — 20%
  • Internal gas pipeline — 99%
  • Installation of heating appliances in apartments — 50%
  • Technical door installation — 95%
  • Landscaping works have started

Tower B:

  • Masonry — 95%
  • Internal plumbing works — 80%
  • Heating — 75%
  • Ventilation — 80%
  • Air-conditioning systems — 60%
  • Plastering — 90%
  • Common-area finishing — 95%

Tower V:

  • Masonry — 100%
  • Internal plumbing works — 96%
  • Electrical installation works — 90%
  • Heating — 75%
  • Ventilation — 30%
  • Air-conditioning systems — 60%
  • Structured cabling and access control systems — 90%
  • Plastering — 80%

Tower H:

  • Masonry — 95%
  • Ventilation block installation — 98%
  • Ventilated façade systems — 65%, glazed façade systems — 70%
  • Metal structures installation — 100%
  • Roofing — 95%
  • Screed — 47%
  • Plastering — 65%
  • Roof metal structures — 32%
  • Ventilation systems installation — 55%
  • Heating systems — 71%
  • Internal plumbing works — 75%
  • Air-conditioning systems — 30%

Tower D:

  • Monolithic works — 99%
  • Ventilated façade systems — 74%, glazed façade systems — 94%
  • Structured cabling and access control systems — 85%
  • Plastering — 70%
  • Common-area screed — 45%
  • Terrace waterproofing — 80%
  • Technical floor waterproofing — 90%
  • Elevator installation has started
  • Water supply and sewerage systems — 60%
  • Heating systems — 50%
  • Air-conditioning systems — 10%
  • Ventilation — 10%
  • Electrical installation works — 15%

Building 6:

  • Monolithic works — 50%

Stylobate:

  • Surface installation — 60%

Office slope:

  • Monolithic works — 95%

Parking:

  • Finishing works (sandblasting) — 95%
  • Dismantling works — 85%
  • Stormwater drainage system — 15%
  • Fire suppression system — 30%

Retaining walls:

  • PS-2 — 80%

External utility networks:

  • Gas pipeline — 40%