Dynamics of construction as of 01.02.19

  • 01/02/2019

LCD "Vladimirsky"
Waterproofing device - 5-10 floor, basement.
Masonry - TE, 17, 25 floor.
The device of internal power supply networks - 5-9 floor.
The device of internal networks of heating and ventilation - 1-4 floor.
Work has begun on the installation of internal water supply and sewerage networks.
The device finishing works MOP - 7%
The device of door designs and hatches - 9%
Roof installation - 16%
The installation of metal fencing staircases - 6 floors.
The device of external engineering networks - 18%

Residential complex "Syretsky Gardens"
House number 1
In the work of interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.

The House 3
Masonry - 13-15 floor.

House 4
Masonry - 1-22 floor, TP.
Windows - 2-17 floor.

House 5
Floor slab 2 floors.

LCD "Yaskravy"
House number 6
Works on the construction of walls and partitions, masonry (external contour - 96%)
Installation of window designs - 76%
Plumbing works - 61.1%
Electrical work - 27.4%
Ventilation and smoke removal - 8.3%
Low-voltage systems - 21%
Wall plaster - 45.5%
Screed device - 68.4%
Finishing MOS - 31.5%
Installation of elevators and commissioning - 71.7%
Facade arrangement - 95%
Roof installation - 92.3%
Entrance group - 82.3%
Improvement - 0,7%

LCD "Park Lakes"
House number 13
The device walls, partitions, masonry (internal) - 99%
Installation of window designs - 98%
Plumbing works - 86%
Electrical work - 74%
Ventilation and smoke removal - 57%
Low-voltage systems - 44%
Finishing MOS - 99%
Installation of elevators and commissioning - 90%
Facade arrangement - 96%
Thermal insulation of facades - 98%
Facade finishing - 96%
Roof installation - 97%
Entrance group - 92%

LCD "Lake Guy Hatne"
House number 5
Interior finish - 95%
Facade - 99.9%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 95%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 95%
5 floor - internal - 95%

House number 9
Foundation reinforcement: 1, 2 section - 50%
Basement walls:
3, 4 section - 50%
 

Residential complex "Tradition"
House number 2
Active finishing is carried out apartments.
 
House number 4
Vertical element of the 17th floor, floor plate of the 16th floor.
Masonry - 5, 6, 7, 8, 9, 10 floor and basement.
External networks - 15%

LCD "Malachite"
House number 4
Section 401 - masonry - on the roof - 95%
Windows - 99%
Finishing works 1-20 floor.
Facade work - 25%
Improvement - promenade area - 40%

House number 5
Vertical element of the 3rd floor.

LCD "Otradny"
House number 3
Installation of plastic windows - 98%
Facade works - 98%
Work is underway on the device of electrical installation and plumbing works - basement, ITE, switchboard and engine room, lighting, installation of automatic machines in the apartments.
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 4
Installation of plastic windows - 98%
Facade works - 95%
Work is underway on the device electrical installation and plumbing works - basement, 5, 8, 9 floor.
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 5
Installation of metal-plastic products - 95%
Plastering works are in progress on the 8th, 9th floors (renovated apartments).
Work is underway on the device electrical installation and plumbing work from 6 to 15 floor.
Installation of equipment for passenger and freight elevators.
Work is underway to warm the basement.

LCD "Academ-Quarter"
House number 1
Vertical element of the 18th floor, slab of the 17th floor.
Masonry - 1, 2, 3, 4, 5, 6th floor.

House number 2
Floor slab 19 floors.

Residential complex "Teremki"
1st turn
Work on the painting of the facade.
Internal engineering and plumbing works are being carried out.
Installation of baskets for air conditioning.
Connection of communications to the house is carried out.
Repair work is being carried out on the 9-11 floor.
2nd stage, 2nd section
Roofing work is underway.
Work on the insulation of the house.
2 stage, 3 section
Roofing work is underway.
Filled floor screed - 7th floor
3rd stage, 4th section
The laying is carried out from the 13th to the 19th floor.
3 stage 5 section
Overlapping roof of the house.
The laying is carried out from the 11th to the 19th floor.
3 phase 6 section
Overlapping vertical elements of the 25th floor is performed.
The laying is carried out from 9 to 19 floor.