Dynamics of construction as of 01/03/19

  • 01/03/2019

LCD "Academ-Quarter"

House number 1

Floor slab 20 floor.

Masonry - 8th floor.

House 2

Floor slab of the 20th floor, vertical element of the 21st floor.

Masonry - 5th floor.

LCD "Vladimirsky"

Waterproofing device - 5-10 floor, basement.

Masonry - TE, 19, 21, 23 floor.

The device of internal power supply networks - 5-9 floor.

The device of internal networks of heating and ventilation - 1-10 floor.

The device of internal water supply and sewerage networks - 1-10 floor.

Device finishing works MOP - 14.75%

The device door structures and hatches - 4-24 floor.

Installation of elevator equipment - 35% (1-24 floor).

Roof installation - 16%

The device window designs - 5-16 floor.

The installation of metal fencing staircases - 6 floors.

Device external engineering networks - 35%

LCD "Malachite"

House number 4
Finishing works - 1-22 floor (finishing).
Facade work - 30%
Improvement - promenade area - 40%

House number 5
Floor slab 6 floors.
Masonry - 1-3 floor.

LCD "Nyvky Park"

House number 3
Work is underway on commissioning of heat supply.
There is a transfer of apartments to investors.

House number 4
Elevators are being adjusted.
Work is underway on the finishing of apartments with repairs.
Finishing work on the arrangement of the facade.
Work is underway on the installation of window sills and baskets for air conditioning.

House number 5
The laying in the basement, on 13, 14, 15, 16, 17 floors of section A is carried out; on 9, 11, 14, 15 floors of section E; on the 8th floor of section B.
Work is underway on laying the vent. mines on the roof of sections B and E.
Works on waterproofing the basements of sections A, B and E.
Work is underway on backfilling the excavation.
Works on installation of windows are in progress: floor 8-11 in sections A, B and E.
Work is underway on laying the cable of the fire safety system: section A - floor 9-13, section E - floor 5-10.
Finishing work is underway on section A - basement.

House number 6
The device parapets on section E.
Device parapets section D *.
The laying is carried out: 4, 5, 7, 8 floor and a cellar on section G; 5, 7, 8 floor on section E; 1, 7, 8 floor and basement of section D *.
Work is underway on waterproofing basements.
Work is underway on backfilling the excavation.
Work is underway on the installation of windows: 5-7 floor sections G, E, D *

House number 7
Work is underway to arrange the vertical elements of the 1st floor of section E2.
Work is underway to arrange the vertical elements of the 1st floor of the E1 section.
Work is underway to arrange the vertical elements of the 1st floor in section B.

House number 8
Work is underway to arrange the vertical elements of the 6th floor in section G *.
Work is underway to arrange the vertical elements of the 6th floor in section B **.
Work is underway to arrange the vertical elements of the 5th floor in section B.

LCD "Lake Guy Hatne"

House number 5
Interior finish - 96%
Entrance groups - 92
Facade - 99.9%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 95%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%
6th floor - external - 90%; internal - 90%
7th floor - external - 95%; internal - 90%
8th floor - external - 90%; internal - 90%
9th floor - 30%

House number 9
Monolithic works:
5, 6 section - 95%
basement:
1, 2 section - 5%
2nd floor:
3, 4 section - 60%

LCD "Otradny"

House number 3
Installation of plastic windows - 98%
Facade works - 98%
Work is underway on electrical installation and plumbing (installation of automatic machines in the apartments, installation of meters for heating).
Finishing works are in progress - 4, 5, 8, 9, 13, 14 floors (renovated apartments).

House number 4
Installation of plastic windows - 98%
Facade works - 95%
Work is underway on the device of electrical installation and plumbing works (lamps on the floors of the MZK, installation of household appliances in apartments with repairs).
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 5
Installation of metal windows - 95%
Work is underway on the device plaster on the 9th floor.
Installation of equipment for passenger and freight elevators.
Work is underway on the installation of ventilation to the ground floor.
Work is underway to arrange facades from the 2nd to the 16th floor.
The device is a cement-sand screed on the 12th floor.

LCD "Park Lakes"

House number 13

Plumbing works - 90%

Electrical work - 78%

Ventilation and smoke removal - 70%

Low-voltage systems - 56%

Installation of elevators and commissioning - 90%

Residential complex "Syretsky Gardens"

House number 1
In the work of interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.

The House 3
Masonry - 13-16 floor.

House 4
Windows - 2-22 floor.

House 5
Vertical element of the 6th floor.

Residential complex "Teremki"

1st turn
Work on the painting of the facade.
Internal engineering and plumbing works are being carried out.
Connection of communications to the house is carried out.
Repair work is underway (tile layout): 13,14, 18, 19th floor.
2nd stage, 2nd section
Roofing work is underway.
Plastering of walls in the apartments on the 23rd and 24th floor is performed.
Work on the insulation of the house.
Installation of elevators.
2 stage, 3 section
Roofing work is underway.
Plastering of walls in the apartments on the 23rd and 24th floor is performed.
Installation of elevators.
Plastering of walls in the MOS - 6, 7th floor.
3rd stage, 4th section
The laying is carried out from 1 to 21 floor.
3 stage, 5 section
The laying is carried out from 1 to 21 floor.
3rd stage, 6th section
Overlapping roof of the house.
The laying is carried out from the 19th to the 21st floor.

Residential complex "Tradition"

House number 2
Active finishing is carried out apartments.

House number 4
Vertical element of the 19th floor, slab of the 19th floor.
Masonry - 10-14 floor and basement.
External networks - 40%
Plaster - 2-3 floor.
Electricity - 2-4 floor
Sewerage - 15%

LCD "Yaskravy"

House number 6
Works on the construction of walls and partitions, masonry (external contour - 99%)
Installation of window designs - 87%
Plumbing works - 78.6%
Electrical work - 29.7%
Ventilation and smoke removal - 24.7%
Low-voltage systems - 26.3%
Plaster walls - 64.9%
Screed device - 84.3%
Finishing MOS - 48%
Installation of elevators and commissioning - 75%
Facade arrangement - 95%
Roof installation - 92.3%
Entrance group - 85%
Improvement - 0,7%