Dynamics of construction as of 02.08.19

  • 02/08/2019

Dear buyers, we bring to your attention construction dynamics of all our capital complexes. The status of the works is recorded as of 02.08.19.

Residential complex Akadem-Kvartal

Building No. 1

Masonry – 18-19th floors.
Glazing works on 14th floor.

Building No. 2

Masonry - 17-19 floors.
Glazing works on 16-17 floors are underway.

Residential Complex Volodimirskyi

The installation of the “smart home” system has begun - today the volume is estimated at 14%.
Installation of individual heat points is about to be completed - 85%.
Finishing works (walls plastering (Individual Heating Plants, commercial staircase, plinth) and screeding (19, 25, 26th floors and basement) are underway.
Hydro and thermal insulation in the passage area - 38%.
Masonry – the 4th floor and the basement.
Electrical works - 32% (5-24 floors).
Low-voltage systems - 27% (5-24, 2-3 floors).
Ventilation and smoke removal - 16% (1-3 floors).
Plumbing works - 64% (commenced: installation of distribution manifolds; heating radiators in common facilities; horizontal plumbing for risers in the plinth).
Ceiling plastering in common facilities - 6-10, 12-18 floors.
Door assembly - 4-24 floors.
Installation of cargo and office elevator cars - 80%
Roofing works - 60%.
Installation of window structures - 5-22 floors.
Installation of facades - 69% (the balcony blocks and vapor barrier are underway).

Residential complex Malakhit

Building No. 5

Monolithic works; parapet, roof.
Masonry - 11-21 floors.
Active works on the utilities laying are underway.
Installation of window constructions - 1-10 floors.

Residential Complex Nyvky-Park

Building No. 5

Works on basements waterproofing are underway.
Works on window and balcony sills installation are underway.
Screeding: Section E - 10, 11 floors; Section A - 12, 13 floors.
Finishing works: sections А, Е, B - 75%.
Works on the roof, facade construction – 90%
Tile laying on the walls if the 1st floor.
Engineering networks tie-in – 80%.
Works on setting up a monolithic framework for the heat transfer station are underway.
Waterproofing of the heat transfer station basement.
Monolithic works on the installation of entrance spaces are underway.
Installation of elevators (section B).
Installation of doors is in progress: section A – 10-11 floors, section B - 16–17 floors and the basement, section E - 8, 10 floors.
The ventilation system installation is underway.

Building No. 6

Windows installation: 16-17 floors in sections G, E, D.
Finishing works are underway on 10-13 floors in sections G, E, D.
Screeding: section D - 12-14 floors, section E-10 floor, section G - 17 floor.
Engineering networks tie-in continues.
Roofing works are underway in sections G, E, D.
Facade works are underway in sections G, E, D.

Building No. 7

Work to install the vertical elements of the 14th floor in section E2 is underway.
Work to install the vertical elements of the 14th floor in section E1 is underway.
Work to install the floor slab of the 13th floor in section C is underway.
Waterproofing of the basements in sections B, E1, E2.
Backfill of the pit.
Walls masonry: section E2: 1-5th floors. Section C: 1-6th floors, section E1: 1-6th floors.

Building No. 8

Work to install the floor slab of the 17th floor in section C is underway.
Work to install the floor slab of the 17th floor in section B is underway.
Work to install the vertical elements of the 17th floor in section G is underway.
Waterproofing of the basements in sections G, B, C.
Backfill of the pit.
Walls and partitions masonry: section C: 2-8 floors and the basement; Section B: 2-64 floors and the basement; Section G - basement, 1-8 floors.

Residential Complex Ozernyi Hai Hatne

Building No. 6

Exterior and interior walls masonry - 1-8 floors
Installation of window constructions is underway (1-3 sections: 7-9 floors)
Finishing works are being completed (plaster, screed) - 99%
Facade works are at the final stage - 97%
Electrical work: 97%
Elevators: 99%
Finishing of common facilities: 40%
Adjacent area: 10%

Building No. 7

Monolithic works: 1st floor.

Building No. 8

Monolithic works - 8 floors
External walls masonry – 1 st floor - 50%

Building No. 9

Monolithic works - 97%
Exterior and interior walls masonry - 1-8 floors.

Building No. 42

Granular base - 75%
Concrete preparation - 75%
Base slab - 60%

Building No. 43

Granular base - 75%
Concrete preparation - 50%
Base slab - 50%

Residential complex Prychal 8

Section 1

Monolithic frame installation (floor slab of the 19th floor)
Walls and partitions installation – 8 floor, 80%.

Section 2

Monolithic frame installation (floor slab over the 20th floor).
Walls and partitions installation - 7 floor, 80%.

Residential Complex Syretski Sady

Building No. 1

Interior decoration, painting - 89%
Landscaping - 60%

Building No. 2

Installation of window constructions is being completed - 93%
Finishing works are underway (plaster, screed) - section 3, 2, 1 - 65%
Facade insulation - 70%
Elevators - 75%
Finishing of the apartments with redecoration – 40%

Building No. 3

Masonry - 95%
Roofing - 40%
Installation of window constructions - 25%
Facade – 7%

Building No.  4

Installation of window constructions is being completed - 85%
Facade insulation - 65%
Roofing - 35%
Masonry - 95%
Plastering, screeding - 50%

Building No.  5

Floor slab over the 22nd floor).
Masonry - 14th floor.

RC Teremky

1st phase
Repair works (98%) and communications tie-in (90%) are being completed.

2nd phase, 2nd section
Facade works – 98%
Insulation works - 98%
Installation of air conditioner baskets - 80%
Elevator installation - 96%
Tiling in apartments with repair - 20%

2nd phase, 3rd section
Facade works – 98%
Insulation works - 98%
Installation of air conditioner baskets - 80%
Elevator installation - 96%
Tiling in apartments with repair - 20%

3rd phase, 4th section
Installation of windows - 95%
House insulation - 95%
Facade works - 90%
Plastering of walls in apartments without repair - 85%
Floor screeding - 80%

3rd phase, 5th section
Installation of windows - 95%
House insulation - 95%
Facade works - 90%
Plastering of walls in apartments without repair - 85%
Floor screeding - 80%

3rd phase, 6th section
Installation of windows - 95%
House insulation - 65%
Facade works - 50%
Plastering of walls in apartments without repair - 85%
Floor screeding - 80%

RC Tradytsija

Building No. 4
Masonry on the th, 20th, 26-27th floors.
Underway:
- external networks - 60%
- plaster - 15-16, 19 floors.
- electricity - 15-16, 19 floors.
- sewage (risers) - 90%
- painting work - 11-12 floors.
- screed – 13, 15 floor
- facades – 10%.