Dynamics of construction as of 02.09.19

  • 02/09/2019

Dear buyers, we bring to your attention construction dynamics of all our capital complexes. The status of the works is recorded as of 02.09.19.

RC Academ-Kvartal

Building No. 1

Masonry – 24th floor.

Glazing works - 16th floor.

 

Building No. 2

Masonry – 24th floor.

Glazing works on the 18th floor are underway.

 

HC Volodymyrskyi

 

The installation of the “smart home” - 38%

(laying of pipes on the 7-22 floors).

Installation of individual heat points - 85% (the frames are mounted).

Walls plastering – 33% (individual heat points, commercial staircase, plinth, 3rd floor, entrance hall, lobby)

Screeding – 68% (plinth, 23-26 floors).

Hydro and thermal insulation in the passage area​​ - 60%.

Masonry – the 4th floor and the plinth.

Electrical works - 46% (5-24 floors).

Low-voltage systems - 41% (5-24, 2-3 floors).

Ventilation and smoke removal - 16% (1-3 floors).

Plumbing works - 72% (commenced: horizontal plumbing for risers, installation of distribution manifolds).

Finishing works in common facilities - 70% (plastering of the ceilings 6-18, tiling 14-16 floor).

Door structures - 69% (5-20 floors).

Installation of lift equipment - 80% (installation of cabins for cargo and office lifts).

Roofing works - 60% (steam and hydro-barriers, extruder, clay-concrete screeding, fine-grained screeding, slag wool on the perimeter).Installation of window structures - 5-22 floors.

Installation of facades - 75% (the balcony blocks and vapor barrier are underway).

 

RC Malachite

 

Building No. 5

Masonry – 16-24th floor.

Active works on the utilities laying are underway.

Installation of window constructions - 1-11 floors.

Installation of window structures - 1-11 floors.

Finishing works - 5-6 floors.

 

RC Nyvky Park

 

Building No. 5

Works on basements waterproofing in Sections A, B, E are underway.

Works on window and balcony sills installation - 80%.

Screeding: Section A - 16, 17 floors.

Finishing works: sections А, Е, B - 80%.

Finishing works in the common facilities - 45%

Roofing works in sections A, B and E are underway - 94%

Facade works - 95%

Tiling of the walls of the 1st floor.

Engineering networks tie-in - 85%

Masonry of the heat transfer station.

Monolithic work on the arrangement of the entrance groups.

Facade works on the entrance groups.

Roofing works on the entrance groups.

Installation of doors is in progress: section A – 12-13 floors, section B - 17 floor and the basement, section E - 10, 11 floors.

The ventilation system installation.

 

Building No. 6

Windows installation: 16-17 floors in sections G, E, D.

Finishing works are underway on 12-14 floors in sections G, E, D.

Screeding: section D - 13-14 floors, section E-10th floor.

Engineering networks tie-in – 75%.

Roofing works are underway in sections G, E, D – 60%.

Facade works are underway in sections G, E, D – 85%.

 

Building No. 7

Work is underway to arrange the floor slab of the 15 floor in section E2.

Work is underway to arrange the floor slab of the 15 floor in section E1.

Work is underway to arrange the floor slab of the 15 floor in section B.

Waterproofing of the basements in sections B, E1, E2.

Backfill of the pit.

Walls masonry: section E: 1-6th floors. Section B: 1-6 floors.

 

Building No. 8

Waterproofing of the basements in sections G, B, C.

Backfill of the pit.

Walls and partitions masonry: section B: 1-9 floors and the basement; Section B: 1-8 floors and the basement; Section G - basement, 1-8 floors.

 

Kindergarten:

Work is underway to reinforce the basement slab.

RC Ozernyi Hai Hatne              

 

Building No. 6

Exterior and interior walls masonry - 1-8 floors – interior – 99%

Installation of window constructions: 7-9 floors – 99%

Finishing works are being completed (plastering and facade works)

Electrical work: 97%

Elevators: 99%

Finishing of common facilities:

1 section - 80%

2 section - 60%

3 section - 50%

Adjacent area: 10%

 

Building No. 7

Monolithic works: 4th floor: 1-2 section – 40%.

External and internal walls masonry:

1st floor - 20%

2nd floor - 30%

 

Building No. 8

Monolithic works completed – 1-10th floors

External and internal walls masonry:

1st floor - 50%

2nd floor - 30%

Installation of staircases - 50%

 

Building No. 9

Monolithic works - 99%

Exterior and interior walls masonry:

1, 2 section:

1-5 floor: internal - 95%

3, 4 section:

1-8 floor: 98% external; 95% internal.

5.6 section:

1-6 floor: 98% internal.

Waterproofing of the plinth - 5%

Installation of window blocks - 1%

 

Building No. 42

Granular base - 75%

Concrete preparation - 75%

Base slab - 75%

1 section - the pit

2nd section: 6th floor - 50%

 

Building No. 43

1, 2 section

Finished basement, 1-6 floors.

RC Prychal 8

Section 1

Monolithic frame installation - roofing, engine room.

Walls and partitions installation – 11-13 floors.

 

Section 2

Monolithic frame installation - horizontal structures of the 22 floor

Walls and partitions installation – 10-13 floors.

HC Syretski Sady

 

Building No. 1

Interior decoration, painting - 95%

Landscaping - 95%

 

Building No. 2

Installation of window constructions - 93%

Plastering, screeding - section 3, 2, 1 - 70%

Facade insulation - 75%

Elevators - 75%

Finishing of the apartments with redecoration – 40%

 

Building No. 3

Masonry - 95%

Roofing - 40%

Installation of window constructions - 30%

Facade – 10%

 

Building No.  4

Installation of window constructions - 85%

Facade insulation - 65%

Roofing - 40%

Masonry - 95%

Plastering, screeding - 60%

 

Building No.  5

Masonry - 20th floor.

Windows – 2%

 

RC Sky Avenue

 

Building 1

Preparatory works are underway for digging the pit of sections 3, 4, 5.

Work is underway to arrange the floor slab of the 5th floor in sections 1 and 2.

Masonry on the 2n floor of 1 section.

 

RC Teremky

2nd phase, 2nd section

Installation of air conditioner baskets - 98%

Elevator installation - 98%

Tiling in apartments with repair - 60%

Pasting of wallpaper in apartments with repairs - 20%

 

2nd phase, 3rd section

Installation of air conditioner baskets - 98%

Elevator installation - 98%

Tiling in apartments with repair - 60%

Pasting of wallpaper in apartments with repairs - 20%

 

3rd phase, 4th section

Facade works - 97%

Floor screeding - 87%

 

3rd phase, 5th section

House insulation - 97%

Facade works - 95%

Floor screeding - 87%

 

3rd phase, 6th section

Installation of windows - 97%

House insulation - 94%

Facade works - 92%

Floor screeding - 87%

 

4th phase, 8th section

Testing of piles - 60%

 

4th phase, 9th section

Testing of piles and concrete pad - finished.

                                         

4th phase, 10th section

Testing of piles and concrete pad - finished.

The basement floor has been completed.           

 

RC Tradition

 

Building No. 4

Masonry on the 27th floor, roof.

External networks - 60%

Plaster - 19, 23-24 floors.

Electricity - 19, 23-24 floors.

Painting work – 16th floor.

Screed – 18th floor

Facades – 60%

Roofing – 60%