Dynamics of construction as of 02.10.19

  • 02/10/2019

Dear buyers, We bring to your attention the dynamics of construction of all our metropolitan complexes. The status of the works is fixed as of 02.10.19.

Residential complex Akadem-Kvartal

House 1
Arrangement of walls and partitions, laying - 92%
Installation of windows - 90%
Water and sewerage - 70%
Heating - 48%
Electricity - 46%
Fire protection systems - 15%
Wall plaster - 36%
Coupler Setting - 32%
Start of decoration of MZK, installation of elevators, facade arrangement.
Roof arrangement - 40%
Entrance group - 50%

House 2
Arrangement of walls and partitions, masonry - 90%
Installation of windows - 92%
Water supply and sewerage - 48%
Heating - 32%
Electricity - 52%
Fire protection systems - 15%
Plastering of walls - 18%
Coupler Setting - 11%
Installation of metal doors in apartments and MZK, finishing of staircases, installation of elevators and facade arrangement have been started.
Installation of brickwork on the roof - 85%
Entrance group - 65%

Residential Complex Vladimirskiy

Facade (installation of granite 1-3 floor) - 30%
Wall plaster - 85%
Electrical work - 95%
Plumbing - 95%
Coupler arrangement - 90%
Arrangement of door structures - 80% (apartment and in MZK).
Insulation of walls by a minvat - 70%
Finishing works in MZK - 80% (puttying of ceilings, tiles).
Ventilation and smoke removal - 70%
Roof arrangement - 70% (work on the terraces).
Installation and commissioning of lifts - 80%

Residential complex Malakhit

House 5
Laying - 21-25 floor.
Works on laying of engineering networks are actively underway.
Installation of window structures - 16-18 floor.
Finishing works - 5-10 floor.

Residential Complex Nivki-Park

House  5
Waterproofing of basements of sections A, B and E is underway - 95%
Work is ongoing on the installation of tides on windows and balconies. - 80%
Finishing works are carried out on sections A, E, B - 90%
MFP net finishing - 55%
Roofing works on sections A, B and E are underway - 95%
Work is underway to arrange the facade - 95%.
Laying tiles on walls of 1 floor.
Work is underway to connect engineering networks - 85%
Work is underway to arrange the facade on TP5.
Monolithic work on the arrangement of entrance groups is underway. Facade works on entrance groups are conducted. Entrance roof unit.
Work is underway to adjust the elevators.
Work is underway to install the doors: section A - 12-13 floor, section B - 17 floor and basement, section E - 11, 10 floor. Work is underway to improve the surrounding area.

House  6
Work is underway to install metal doors on the first floors.
Finishing works are underway on sections D, E and E - 70%
Work on the arrangement of the coupler: section D - 15 floor, section E - 10 floor.
Laying tiles on walls of 1 floor.
Roofing works are underway on sections D, E and D * - 70%
Conducting facade works on sections D, E, E - 85%
Work on the installation of elevators is underway.

House  7
Work is underway on the installation of railings in section B.
Basement waterproofing on sections B, E1, E2.
Backfill of the sinuses of the pit.
Laying of walls: section E2: 5-8 floor; section B: 3-9 floor; section E1: 5-8 floor.

House  8
Basement waterproofing on sections D, B, C.
Backfill of the sinuses of the pit.
Laying of walls and partitions on sections B: 6, 7, 9-11 floor; on section B: 5-12 floor; on section D - 6, 7, 8,10 floor.
Work is ongoing on the installation of window structures on the 2nd floor of Section G.

Kindergarten
Work is underway to concretize the vertical elements of the 1st floor.

Residential Complex Ozernyi Hai Gatne

House  6
Wall plaster - 95%
Floor screed - 99%
Facade works - 97%

House  7
Monolithic works - 7th floor

House  8
Monolithic works - 10th floor
Laying of external and internal walls - 1-4 floor

House  9
Laying of external and internal walls - 97%
Installation of window blocks - 98%
Front work - 5, 6 section - 70%

House  42
Crushed stone cushion - 70%
Concrete preparation - 70%
Baseplate - 50%
Basement - 70%
Monolithic works: sections: 2, 3, 4 - 98%
Laying of external and internal walls: 4 section: 1-2 floor.

House  43
Monolithic works - 1 and 2 sections - 95%
3, 4 section - 3 floor - 80%

Residential complex Prychal 8

Section 1
Arrangement of storage area and reinforcement shop.
Arrangement of walls and partitions - 16 floor.

Section 2
Arrangement of monolithic frame - roof.
Arrangement of walls and partitions - 16-17 floor.

Residential Complex Syretsky Sady

House 1
In the work interior decoration - painting - 95%
Improvement - 95%

House 2
Plaster, screeds - section 3, 2, 1 - 90%
Facade insulation - 99%
Elevators - 80%
Apartment renovation - 90%

House 3
Masonry - 95%
Roof arrangement - 40%
Windows - 75%
Facades - 65%

House 4
Windows - 85%
Facade insulation - 65%
Roof arrangement - 40%
Masonry - 95%
Plaster, screeds - 70%

House 5
Laying - 22 floor.
Windows - 15%

RC Sky Avenue 

1 house
Basis: Arranging a field for 3, 4, 5 sections.
Monolithic works: works on the arrangement of the floor slab 7 floors in 1 and 2 sections.
Laying of walls and partitions: laying of walls on the 2nd floor of 2 sections.

RC Teremky

2 turns, 2 sections
Installation of baskets under air conditioning - 98%
Laying of tiles in apartments with repair - 80%
Pasting of wallpaper in apartments with repair - 50%
Improved territory - 30%
2 turns, 3 sections
Installation of baskets under air conditioning - 98%
Laying of tiles in apartments with repair - 80%
Pasting of wallpaper in apartments with repair - 50%
Improved territory - 30%
3 turns, 4 sections
Facade works - 97%
Floor screed fill - 94%
Installation of elevators - 80%
Installation of baskets under air conditioning - 50%
Improved territory - 30%
3 turns, 5 sections
Home insulation is in progress - 97%
95% of facade works are in progress
Floor screed fill - 94%
Installation of elevators - 80%
Installation of entrance doors in apartments - 60%
Improved territory - 30%
3 turns, 6 sections
Installation of windows - 97%
Home insulation is in progress - 97%
95% of facade works are performed
Floor screed fill - 94%
Installation of elevators - 60%
Installation of entrance doors in apartments - 60%
Improved territory - 30%
4 turns, 8 sections
Tested piles.
4 turns, 9 sections
Overlapping vertical elements of 2 floors.
4 turns, 10 sections
Overlapping vertical elements of 2 floors.

RC Tradiciya

House  4
External networks - 70%
Plaster - 19, 20 floor.
Electricity - basement.
Painter - 17-18 floor.
Screed - 19-23 floor.
Facades - 70%
Roof - 80%
Finishing works in apartments (tile) - 3-7 floor.