Dynamics of construction as of 03.02.20

  • 03/02/2020

Dear buyers, We bring to your attention the dynamics of construction of all our metropolitan complexes. The status of the works is fixed as of 03.02.20

Residential complex Akadem-Kvartal

House 1
Installation of windows - 98%
Water supply and sewerage - 95%
Heating - 85%
Electricity supply - 90%
Fire protection systems - 60%
Wall plaster - 85%
Coupler Setting - 73%
IWC Finish - 15%
Facade arrangement - 55%
Elevator installation - 25%
Doors - 40%
Roof arrangement - 92%
Entrance group - 95%

House 2
Installation of windows - 99%
Water supply and sewerage - 87%
Heating - 55%
Electricity - 77%
Fire protection systems - 30%
Wall plaster - 60%
Coupler Setting - 40%
Installation of metal doors in apartments and MZCs started - 10%
Clean staircase finishing - 25%
Elevator installation - 22%
Facade arrangement - 80%
Roof arrangement - 70%
Entrance group - 85%

Residential Complex Volodymyrskyi

Facade (porcelain stoneware) - 70%
Wall plaster - 95%
Thermal insulation of walls with mineral wool - 95%
Numbering of apartments - 25%
Roof arrangement - 95%
Installation and commissioning of lifts - 80%
Land improvement - 90%

Residential complex Malakhit

Laying - kindergarten - 1-2 floor.
Installation of window structures - kindergarten.
Finishing works - 16-24 floor.
Facade works - 40%

Residential complex Nyvky-Park

House 5
Finishing works are carried out on sections A, E, B - 99%
Finishing of MSC - 99%
Work is underway to adjust the elevators.
Work is underway to improve the surrounding area.

House 6
Work is underway to arrange windowsills.
Finishing works are carried out on sections D, E and E - 85%
Work on installation of apartment doors and MZC is underway - 85%
There are facade works on sections D, E, E - 95%
Laying tiles on walls of 1 floor (facade).
Work is underway to adjust the elevators.
Entrance roof unit - 90%
Work is underway to improve the surrounding area.

House 7
Concreting of underground part of entrance groups on sections E2 and E1.
Laying of walls: Section E2: 12, 14, 17 floor. Section B: 6, 11, 14-15 floor. Section E1: 11-12, 14-17 floor.
Work is underway on the installation of window structures on sections E2 on 5 floors, on sections E1 on 4-5 floors.

House 8
Laying of walls and partitions on sections B: 14, 16, 17 floor; on section B: 5, 11, 15, 16, 17 floor; on section D - 12, 17 floor.
Work is underway on the installation of window structures: on section D on the 10th floor. On section B on the 7th floor; on section B on the 6-7 floor. Work is underway on the installation of distribution boards. Plaster works are underway.
Work is underway to arrange the roof.

House 12
Section D: Reinforcement of floor slab 4 floors.
Section I: Concreting of vertical elements of 4 floors.
Section E: Installation of the floor slab formwork 2 floors.
Section B: Concrete of vertical cellar elements.

Kindergarten
Concrete railing works are underway. Waterproofing the basement walls.

Residential complex Ozernyi Hai Hatne

House 6
Facade works - 99%
Adjacent area - 75%
Finishing works:
Renovated apartments - 45%
MLC - 95%
Elevators -99%
External networks - 95%

House 7
Monolithic works: - 97%
Laying of exterior and interior walls: 30%
Waterproofing cap - 30%
External networks - 15%

House 8
Laying of external and internal walls - 95%
Installation of window units: 65%
Roof arrangement - 50%
External networks - 20%

House 9
Laying of external and internal walls - 99%
Installation of window units: - 99%
Front work: - 70%
Finishing works:
Wall plaster - 50%
Floor screed: - 5%
Water and sewerage - 70%
Heating - 70%
Electricity - 70%
Installation of elevators - 60%

House 42
Monolithic works: - 99%
Laying of exterior and interior walls: 80%
Waterproofing cap - 85%
Roof arrangement - 45%

House 43
Monolithic works: - 99%
Laying of external and internal walls: - 75%
Roof arrangement - 7%

Residential complex Prychal 8

Section 1
Monolithic frame arrangement - entrance groups.
Roof - Machine Room - 98%
Arrangement of walls and partitions - entrance groups.

Section 2
Monolithic frame arrangement - entrance groups.
Roof - machine room - 90%
Arrangement of walls and partitions - entrance groups

Section 3
Horizontal element 9 floor.
Arrangement of walls and partitions - 6th floor.

Section 4
Vertical element 10 floor.
Arrangement of walls and partitions - 6th floor.

Residential complex Syretski Sady

House 1
Improvement - 95%

House 2
Facade insulation - 99%
Elevators - 80%
Renovated apartments - 90%
Installation of window structures - 95%

House 3
Masonry - 95%
Roof arrangement - 70%
Windows - 85%
Facades - 75%
Apartments without repair - 70%

House 4
Windows - 87%
Facade insulation - 70%
Roof arrangement - 95%
Masonry - 95%
Plaster, screeds - 87%

House 5
Windows - 75%
Roofing - 10%

House 7
Test bushes of piles.

House 8
Frame 1 floor.

RC Sky Avenue 

House 1
1 section: mounting of formwork of vertical elements of 14 floors, masonry - 10 floors.
Section 2: 13 floors of the monolith, masonry - 9 floors.
Section 3: Installation of vertical elements of 1 floor.
4, 5 section: installation of formwork covering 1 floor

RC Teremky

2 turns, 2 sections
Installation of baskets under air conditioning - 98%
Improved territory - 90%
2 turns, 3 sections
Installation of baskets under air conditioning - 98%
Improved territory - 90%
3 turns, 4 sections
Installation of elevators - 95%
Installation of radiators inside the apartments - 80%
Installation of baskets under air conditioning - 90%
The territory is being improved - 85%
Coloring of ceilings in apartments with repairs - 80%
Laying of tiles in apartments with repair - 50%
3 turns, 5 sections
Installation of elevators - 95%
Installation of radiators inside the apartments - 80%
Installation of baskets under air conditioning - 90%
The territory is being improved - 85%
Coloring of ceilings in apartments with repairs - 80%
Laying of tiles in apartments with repair - 50%
3 turns, 6 sections
Facade works - 98%
Installation of elevators - 95%
Installation of radiators inside the apartments - 60%
Laying of floor tiles in MZC - 95%
Installation of baskets under air conditioning - 85%
Territory improvement - 80%
Coloring of ceilings in apartments with repairs - 80%
Laying of tiles in apartments with repair - 50%
4 turns, 7 section
The vertical elements of the 1 floor are overlapped.
4 turns, 8 sections
Overlapping of vertical elements of 5 floors is performed.
4 turns, 9 sections
Overlapping vertical elements 12 floors.
Laying - 2-8 floor.
4 turns, 10 sections
Overlapping vertical elements 12 floors.
Laying - 2-8 floor.

RC Tradytsiia

House 4
External networks - 85%
Electricity - TP, basement.
Painter - 80%
Facades - 95%
Finishing works in apartments (tile) - 60%
Improvement - 15%

Intergal City

On tower "A" - slab floor 3 floors.
The tower "G" - floor slab 8 floors. Works on wall laying and communication niches are in progress.
On tower "B" - vertical element 5 floors.
Sport Complex: monolithic pool designs for teenagers, monolithic large pool designs.