Dynamics of construction as of 03.03.20

  • 03/03/2020

Dear buyers, We bring to your attention the dynamics of construction of all our metropolitan complexes. The status of the works is fixed as of 03.03.20

Residential complex Akadem-Kvartal

House 1
Installation of windows - 98%
Water supply and sewerage - 97%
Heating - 91%
Electricity - 93%
Fire protection systems - 65%
Wall plaster - 92%
Coupler Setting - 80%
IWC Finish - 15%
Facade arrangement - 55%
Elevator installation - 25%
Doors - 48%
Roof arrangement - 92%
Entrance group - 97%

House 2
Installation of windows - 99%
Water and sewerage - 93%
Heating - 67%
Power supply - 83%
Fire protection systems - 42%
Wall plaster - 78%
Coupler Setting - 50%
Installation of metal doors in apartments and MZCs started - 12%
Clean staircase finishing - 30%
Elevator installation - 22%
Facade arrangement - 80%
Roof arrangement - 70%
Entrance group - 87%

Residential complex Nyvky-Park

House 5
Finishing works are carried out in sections A, E, B - 99%
MFC Finish - 99%
Work is underway to adjust the elevators.
Work is underway to improve the surrounding area.
Work is underway to renovate the apartments.

House 6
Work is underway to arrange windowsills.
Finishing works are carried out on sections D, E and E - 90%
Work on installation of doors of apartments and MZK is in progress: 95%
There are facade works on sections D, E, E - 95%
Laying tiles on walls - 1 floor (facade).
Work is underway to adjust the elevators.
Roof arrangement of entrance groups - 90%.
Work is underway to improve the surrounding area.
Work is underway to renovate the apartments.

House 7
Concreting of underground part of entrance groups on sections E2 and E1.
Laying of walls: Section E2: 12, 14, 17 floor. Section B: 6, 11, 14-15 floor. Section E1: 11-12, 14-17 floor.
Work is underway on the installation of window structures on sections E2 on 16 floors, on sections E1 on 4-5 floors, on sections B on 2 floors.
Backfill of the sinuses of the pit.

House 8
Laying of walls and partitions on sections B: 14, 16, 17 floor; on section B: 5, 11, 15, 16, 17 floor; on section D - 12, 17 floor.
Work is underway on the installation of window structures on section D on the 16th floor; Section B on the 10th floor; on section B on the 10th floor. Work is underway on the installation of distribution boards. Plaster works are underway.
Work is underway to arrange the roof.
Work began on the arrangement of the facade.
Backfill of the sinuses of the pit.

House 11
Section G: development of a foundation pit.
Section I: foundation planning.

House 12
Section D: reinforcement and concreting of vertical elements of 8 floors.
Section I: Concreting of floor slab 7 floors.
Section E: Installation of 6-storey vertical formwork.
Section B: Concreting of floor slab of 2 floors.

Kindergarten
Waterproofing the basement walls. Backfill of the sinuses of the pit. Setting up external networks.

Residential complex Ozernyi Hai Hatne

House 6
Facade works - 99%
Adjacent area - 75%
Finishing works:
Renovated apartments - 50%
IAC - 99%
Elevators -99%
External networks - 95%

House 7
Monolithic works - 98%
Laying of external and internal walls - 65%
External networks - 15%

House 8
Installation of window blocks - 95%
Roof arrangement - 70%
External networks - 20%
Internal networks - 10%

House 9
Facade works - 80%
Finishing works:
Wall plaster - 85%
Floor screed: - 40%
Water supply and sewerage - 85%
Heating - 85%
Electricity supply - 85%
Installation of elevators - 90%

House 42
Monolithic works - 99%
Laying of external and internal walls - 95%
Roof arrangement - 60%
Installation of window blocks - 60%

House 43
Monolithic works - 99%
Laying of external and internal walls - 95%
Roof arrangement - 70%
Installation of window blocks - 60%

Residential complex Prychal 8

Section 1
Monolithic frame arrangement - entrance groups.
Roof - Machine Room - 98%
Arrangement of walls and partitions - entrance groups.
Installation of windows, doors - 35%

Section 2
Monolithic frame arrangement - entrance groups.
Roof - machine room - 90%
Arrangement of walls and partitions - entrance groups.
Installation of windows, doors - 6%

Section 3
Horizontal element 13 floor.
Arrangement of walls and partitions - 9th floor.

Section 4
Vertical element 14 floor.
Arrangement of walls and partitions - 10th floor.

Residential complex Syretski Sady

House 1
Landscaping - 95%

House 2
Facade insulation - 99%
Lifts - 85%
Renovated apartments - 90%
Installation of window structures - 97%

House 3
Masonry - 95%
Roof arrangement - 70%
Windows - 85%
Facades - 75%
Apartments without repair - 70%

House 4
Windows - 90%
Facade insulation - 70%
Roof arrangement - 95%
Masonry - 95%
Plaster, screeds - 90%

House 5
Windows - 75%
Roofing - 10%
Facade - 1%
Finishing - 1%

House 7
Test bushes of piles.

House 8
Frame 3 floors.

RC Sky Avenue 

1 section - monolith, installation of formwork vertical elements 16 floors, masonry - 13 floor.
Section 2 - 13 floors of the monolith, masonry - 11 floors.
3 section - monolith, installation of vertical elements of 1 floor,
4, 5 section - installation of formwork of floor slab of 1 floor.
Glazing - 1 section - 3 floor, 2 section - 2 floor.
Plastering of apartments - 2 section 2 floor.

RC Teremky

2 turns, 2 sections
Improved territory - 90%
2 turns, 3 sections
Improved territory - 90%
3 turns, 4 sections
Installation of elevators is in progress - 98%
The territory is being improved - 85%
Coloring of ceilings in apartments with repairs - 95%
Laying of tiles in apartments with repair - 95%
3 turns, 5 sections
Installation of elevators is in progress - 98%
The territory is being improved - 85%
Coloring of ceilings in apartments with repairs - 95%
Laying of tiles in apartments with repair - 95%
3 turns, 6 sections
Facade works - 98%
The territory is being improved - 85%
Coloring of ceilings in apartments with repairs - 95%
Laying of tiles in apartments with repair - 95%
4 turns, 7 section
Overlapping of vertical elements of 4 floors is performed.
4 turns, 8 sections
The vertical elements of the 9th floor are overlapped.
Laying - 1-4 floor.
4 turns, 9 sections
Overlapping vertical elements 13 floor.
Laying - 1-9 floor.
4 turns, 10 sections
Overlapping vertical elements 15 floors.
Laying - 1-10 floor.

RC Intergal City

On tower "A" - slab floor 5 floors.
On tower "D" - floor slab of 9 floors. Works on wall laying and communication niches are in progress.
On tower "B" - floor slab 7 floors.
Sport Complex: monolithic designs of a pool for babies are at work.