Dynamics of construction as of 05/04/19

  • 05/04/2019

Dear customers, we offer you the dynamics of construction as of 05/04/19


LCD "Academ-Quarter"

House number 1
Floor slab 23 floors.
Masonry - 11th floor.
House 2
Floor slab 23 floors, vertical element 24 floors.
Masonry - 6th floor.


LCD "Vladimirsky"


Waterproofing device - 28%
Masonry - 3, 4, 21, 22 floor.
Electrical work - 8% (5-11 floor).
Ventilation and smoke removal - 12% (1-11 floor).
Plumbing works - 29% (1-24 floor).
The device finishing works MOP - 38% (putty ceilings 6th floor).
Door construction device - 45% (floor 4-24)
Installation of elevator equipment - 60% (1-24 floor).
Roof installation - 50%
The device window designs - 5-16 floor.
Facade arrangement - 26%


LCD "Malachite"

House number 4
Finishing works - 1-24 floor (finishing).
Facade work - 80%
Improvement - promenade area - 40% (waterproofing parking lots)

House number 5
Floor slab 11 floor.
Masonry - 5-6 floor.
Work has begun on the laying of utilities.

LCD "Nyvky Park"

House number 5
The laying is carried out on the 14th, 15th, 16th floors of section A; on 9,11,14,16,17 floors of section E; on 8,12-15,17 floors of section B.
Work is underway on waterproofing basements sections A, B and E.
Work is underway on backfilling the excavation.
The installation of windows is in progress: floor 16-17 in section A, floor 13-17 in sections B and E.
Work is underway on laying the cable of the fire safety system: Section E - 4-15 floor, Section B - 3-13 floor, Section A - 8-17 floor.
Finishing work is underway in sections A, E, B– basement, floor 2-10.
Work is underway on the construction of the roof on section A, B and E.
Work is underway on the design of the facade.
Work is underway to connect the engineering networks.
Work is underway on the construction of the pit under the TE.
Conducted monolithic work on the device input groups.

House number 6
The laying is carried out: on 7, 9, 10, 11, 12, 13, 15 floors and a roof on section G; on 1, 7, 9, 10, 11, 12, 14, 15 floors of section E; on 10, 11, 12, 13, 14 floors and basement of section D.
Work is underway on waterproofing basements.
Work is underway on backfilling the excavation.
Work is underway on the installation of windows: 5-9 floor sections G, E, D.
Finishing works are carried out: 3-4 floors of section G, D and E.
Work is underway on the device screed: Section B 5 floor.
Work is underway to connect utilities.

House number 7
Work is underway to arrange the vertical elements of the 4th floor in section E2.
Work is underway to arrange the vertical elements of the 4th floor of the E1 section.
Work is underway on the construction of the floor slab of 3 floors in section B.
The device of a waterproofing of cellars on the sections B, E1, E2.

House number 8
Work is underway to arrange the vertical elements of the 9th floor in section G *.
Work is underway on the construction of the floor slab of the 8th floor in section B **.
Work is underway on the construction of the floor slab of the 8th floor in section B.
The device of waterproofing basements on sections G, B, B.

LCD "Lake Guy Hatne"

House number 5
Interior finish - 97.5%
Entrance groups - 98%
Facade - 99.9%
House territory - 60%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 97%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%
6 floor - internal - 97%
7th floor - internal - 97%
8th floor - internal - 97.5%
9th floor - internal - 97%
Installation of window units:
1 section - 80%
2 section - 60%
Roof - 40%
Water supply - 10%

Building 7
Development of the pit - 5%

House 8
Basement - 3%

House number 9
1st floor:
1, 2 section - 50%
3rd floor:
5, 6 section - 10%

House 42
Development of the pit - 50%

House 43
Crushed cushion - 50%
Concrete preparation - 50%
Base plate - 25%

LCD "Otradny"

House number 3
Installation of plastic windows - 98%
Facade works - 98%
Electrical installation and plumbing works - 95%
Finishing work is underway - 8th, 9th floor (renovated apartments).

House number 4
Installation of plastic windows - 98%
Facade works - 95%
Electrical installation and plumbing works - 95%
Finishing works are being carried out - 5, 13, 14 floor (apartment renovated).

House number 5
Installation of metal windows - 95%
Plaster - 1st and 2nd floor.
Installation of equipment for passenger and freight elevators.
Work on the device ventilation - 85%
Work is underway on the device facades - 2-16 floor.
The device is a cement-sand screed - 2, 13th floor.
The insulation of the staircase with mineral wool is up to the 16th floor.
Work on the facade insulation on the roof - 90%

LCD "Park Lakes"

House number 13
Plumbing works - 98%
Electrical work - 88%
Ventilation and smoke removal - 80%
Low-voltage systems - 65%
Installation of elevators and commissioning - 97%

Residential complex "Syretsky Gardens"

House number 1
In the work of interior decoration - paint brushes.
Windows - 90%

House 2
Windows - 14, 16th floor.
Plaster, screeds - section 3, 2, 1 - 8%
Warming of the facade - 13%

The House 3
Masonry - 95%

House 4
Windows - 2-22 floor.
Facade insulation - 20%
Roof installation - 10%
Masonry - 95%

House 5
Vertical element of the 12th floor.
Masonry - 4th floor.

Residential complex "Teremki"

1st turn
Work on the painting of the facade.
Internal engineering and plumbing works are being carried out.
Connection of communications to the house is made.
Began to landscaping around the first house.
Repair work in progress:
- tile: 24th floor.
- wallpaper: 19, 24th floor.
- laminate floor: 9th floor.
2 turn, 2 section
Roofing work is underway.
The plastering of the walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors is carried out.
Filled floor screed from 2 to 23 floor.
Plaster walls in common areas from 3 to 25 floors.
Work on the insulation of the house.
Painting of MOP ceilings from 4th to 15th floor.
Installation of elevators.
2 stage, 3 section
Roofing work is underway.
The plastering of the walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors.
Filled floor screed from 2 to 23 floor.
The plastering of the walls in the common areas from the 3rd to the 25th floor was completed.

Painting of MOP ceilings from 4th to 15th floor.
Work on the insulation of the house.
Installation of elevators.
3rd stage, 4th section
The laying is carried out - 23-25 ​​floor.
Windows - 5-6 floor.
Plaster walls in the apartments - 2-5 floor.
3 stage, 5 section
The laying is carried out - 23-25 ​​floor.
Windows - 8th floor.
Plaster walls in the apartments - 2-5 floor.
3rd stage, 6th section
Overlapping roof of the house.
The laying is carried out on the 23-25 ​​floor.
Windows - 7-8 floor.
Plaster walls in the apartments - 2-5 floor.

Residential complex "Tradition"

House number 4
Vertical element of the 22nd floor, floor slab of the 21st floor.
Masonry - 13-18 floor and basement.
External networks - 60%
Plaster - 2-4, 6, 8 floor.
Electricity - 7-9 floor
Sewerage (risers) - 50%
Paint brushes - 2-3 floor.
Screed - 2, 5th floor.

LCD "Yaskravy"

House number 6
Installation of window designs - 90%
Plumbing works - 84.7%
Electrical work - 58.2%
Ventilation and smoke removal - 61%
Low-voltage systems - 40%
Plaster walls (apartments) - 62.2%
Screed device - 98%
Finishing MOS - 92%
Installation of elevators and commissioning - 85%
Facade arrangement - 98%
Roof installation - 97%
Entrance group - 92.3%
Improvement - 6%