Dynamics of construction as of 07.05.2019

  • 05/07/2019

Dear buyers, we bring to your attention construction dynamics of all our capital complexes. The status of the works is recorded as of 05.07.19

RC Akadem-Kvartal

Building No. 1

Masonry - 17th floor.
Glazing works on floors 10-11 are underway.

Building No. 2

Masonry - 14-15 floors.
Glazing works on floors 9-10 are underway.

RC Volodymyrsky

The installation of the “smart home” system has begun - today the volume is estimated at 8%.
Installation of individual heat points is about to be completed - 85%.
Finishing works (walls plastering (Individual Heating Plants) and screeding (15th floor and basement) are underway.
Hydro and thermal insulation in the passage area - 38%.
Masonry – the 3rd  floor and the basement.
Electrical works - 24% (5-21 floors).
Low-voltage systems - 23% (the works started on the 5th-19th, 2nd-3rd floors).
Ventilation and smoke removal - 13% (1st -11th floors; 4 smoke exhausters have been installed on the roof).
Plumbing works - 54% (installation of water risers 1-24 floors, heating and water supply systems on the 22nd floor).
Ceiling plastering in common facilities - 6-10, 12-14 floors.
Door assembly - 4-24 floors.
Installation of cargo and office elevator cars - 80%
Roofing works - 60% underway.
Installation of window structures is underway - 5-22 floors.
Installation of facades - 69% (the balcony blocks and vapor barrier are underway).

RC Malakhit

Building No. 5

Monolithic works are underway (vertical element of the 24th floor).
Masonry - 1-16 floors.
Active works on the utilities laying are underway.
Installation of window constructions started - 1-5 floors.

RC Nyvky-Park

Building No. 5

Works on basements waterproofing are underway.
Works on window and balcony sills installation are underway.
Screeding: Section E - 6, 7 floors; Section A - 8, 9 floors.
Finishing works: basement, 5-12, 17 floors.
Works on the roof, facade construction and tile laying are underway.
Engineering networks tie-in.
Works on setting up a monolithic framework for the heat transfer station are underway.
Waterproofing of the heat transfer station basement.
Monolithic works on the installation of entrance spaces are underway.
Installation of elevators (section B).
Installation of doors is in progress: section A - 5, 6–9 floors, section B - 6–9 floors and the basement, section E - 6–8, 10 floors.
The ventilation system installation is underway.

Building No. 6

Walls masonry: 17th floor in section G; 16.17 floors in section E; 15-17 floors and the roof in section D.
Windows installation: 16-17 floors.
Finishing works are underway on 8-13 floors.
Screeding: section D - 12-14 floors, section E-10 floor, section G - 9 floor.
Engineering networks tie-in continues.
Roofing works are underway.
Facade works are underway.

Building No. 7

Monolithic works are underway - 11th floor.
Waterproofing of the basements.
Walls masonry: section E2: 1, 3, 4th floors. Section B: 1st and 2nd floors.

Building No. 8

Monolithic works are underway - 15-16 floors.
Waterproofing of the basements.
Walls masonry: section B: 1, 5, 4, 3 floors and the basement; Section B: 2-4 floors and the basement; Section G - basement, 1-6 floors.

Kindergarten

The pit development is underway.

RC Ozerny Gai Gatne

Building No. 5

The facade and interior decoration works are being completed.
Entrance spaces are at the final stage.
Adjacent territory - 70%

Building No. 6

Exterior and interior walls masonry - 1-8 floors.
Installation of window constructions is underway (1-3 sections: 7-9 floors)
Finishing works are being completed (plaster, screed) - 90%
Facade works are at the final stage - 93%
Water supply - 50%
Drainage - 90%
Installation of elevators is being completed - 99%

Building No. 7

Monolithic works started: 1st floor, 1 section - 5%
Basement - 20%

Building No. 8

Monolithic works are underway (6-7 floors)
Masonry - 10%

Building No. 9

Monolithic works are underway (8th floor: 1, 2 sections  - 50%)
Exterior and interior walls masonry - 1-6 floors.

Building No. 42

Granular base - 75%
Concrete preparation - 75%
Base slab - 60%
1 section – ditch
2 section - base slab - 20%

Building No. 43

Granular base - 50%
Concrete preparation - 50%
Base slab - 50%
3,4 section - ditch
1,2 section – 3rd floor - 30%

RC Prychal 8

Section 1

Monolithic frame installation (vertical element of the 17th floor) - 50%
Walls and partitions installation - 1-6 floor.

Section 2

Monolithic frame installation (floor slab over the 17th floor) - 80%
Walls and partitions installation - 1-5 floor.

RC Syretski Sady

Building No. 1

Interior decoration - 89%
Installation of window constructions is being completed - 99%
Improvement work started - 15%

Building No. 2

Installation of window constructions is being completed - 93%
Finishing works are underway (plaster, screed) - section 3, 2, 1 - 65%
Facade insulation - 65%
Elevators are being actively mounted - 75%

Building No. 3

Masonry - 95%
Roofing - 20%
Installation of window constructions - 7%

Building No.  4

Installation of window constructions is being completed - 85%
Facade insulation - 60%
Roofing - 25%
Masonry - 95%
Finishing works are underway (plaster, screed) - 50%

Building No.  5

Monolithic works are underway (floor slab over the 21st floors).
Masonry - 13th floor.

RC Teremky

1st phase

Repair works (98%) and communications tie-in (90%) are being completed.

2nd phase, 2nd section

Insulation works - 95%, roofing and facade works - 90%.
Installation of air conditioner baskets - 60%

2nd phase, 3rd section

Insulation works - 95%, roofing and facade works - 90%.
Installation of air conditioner baskets - 52%

3rd phase, 4th section

Insulation works are being completed, walls plastering in apartments without redecoration is being completed - 90%
Underway:
- floor screed - 70%
- electricity wiring in apartments with redecoration - 75%
Plastering of common facilities walls - 35%

3rd phase, 5th section

Insulation works (95%), walls plastering in apartments without redecoration (80%).
Underway:
- floor screed - 65%
- electricity wiring in apartments with redecoration - 70%
Plastering of common facilities walls - 35%

3rd phase, 6th section
Installation of windows - 85%
Insulation - 95%
Walls plastering in apartments without redecoration - 80%
Floor screed - 60%
Electricity wiring in apartments with redecoration ents - 70%
Plastering of common facilities walls - 35%.

RC Tradition

Building No. 4
Masonry on the 19th, 20th, 23-26th floors.
Underway:
- external networks - 60%
- plaster - 14-18 floors.
- electricity - 14-18 floors.
- sewage (risers) - 80%
- painting work - 9-10 floors.
- screed - 11th floor and the basement.