Dynamics of construction as of 05.11.19

  • 05/11/2019

Dear buyers, We bring to your attention the dynamics of construction of all our metropolitan complexes. The status of the works is fixed as of 05.11.19.

Residential complex Akadem-Kvartal

House 1
Wall and partition arrangement, masonry - 98%
Installation of windows - 96%
Water and sewerage - 78%
Heating - 50%
Electricity supply - 66%
Fire protection systems - 21%
Wall plaster - 50%
Coupler Setting - 40%
IQC Finish - 4%
Facade arrangement - 10%
Elevator installation - 21%
Doors - 10%
Roof arrangement - 80%
Entrance group - 60%

House 2
Wall and partition arrangement, masonry - 97%
Installation of windows - 95%
Water supply and sewerage - 60%
Heating - 34%
Electricity - 60%
Fire protection systems - 16%
Plastering of walls - 22%
Coupler Setting - 18%
Installation of metal doors in apartments and MZCs started - 4%
Clean staircase finishing - 5%
Installation of elevators - 20%
Facade arrangement - 45%
Roof arrangement - 10%
Entrance group - 65%

Residential Complex Volodymyrskyi

Facade (installation of granite 1-3 floor) - 30%
Wall plaster - 85%
Electrical work - 95%
Plumbing - 95%
Coupler arrangement - 90%
Arrangement of door structures - 80% (apartment and in MZK).
Insulation of walls by a minvat - 70%
Finishing works in MZK - 80% (puttying of ceilings, tiles).
Ventilation and smoke removal - 70%
Roof arrangement - 70% (work on terraces).
Installation and commissioning of lifts - 80%

Residential complex Malakhyt

Masonry - kindergarten.
Installation of window structures - kindergarten.
Finishing works - 5-15 floor.
Facade work - 7%

Residential Complex Nyvky-Park

House 5
Work on installation of windowsills and low tides on windows and balconies - 80%
Finishing works are carried out in sections A, E, B - 97%
MFC net finishing - 95%
Roofing works on sections A, B and E are underway - 97%
Work is underway on the arrangement of the facade - 97%
Laying tiles on walls of 1 floor.
Work is underway to connect the engineering networks - 99%
Work is underway to arrange the doors in TP5
Entrance Roof Arrangement - 95%
Work is underway to adjust the elevators.
Door handles are being installed.
Work is underway to improve the surrounding area.

House 6
Work is underway to install metal doors on the first floors.
Work is underway to arrange windowsills.
Finishing works are underway on sections D, E and E - 70%
Work is underway on the installation of apartment doors and in the MZK: section D - 9th floor, section E - 14th floor, section D - 8th floor.
Floor coupler arrangement: section D - 16 floor.
Roofing works are underway on sections D, E and E - 80%
There are facade works on sections D, E, D - 95% (balconies of cold transitions). Laying tiles on walls of 1 floor (facade).
Work on the installation of elevators.

House 7
Concreting of underground part of entrance groups on section E2.
Laying of walls: Section E2: 6, 8-13 floor. Section B: 3, 5-6, 9-13 floor. Section E1: 5, 8-13 floor.

House 8
Laying of walls and partitions on sections B: 6, 11-15 floor; on sections B: 5, 7, 8, 11-14 floor and roof; on sections D - 6, 10-15 and the roof.
Work is underway on the installation of window structures on the 5th floor of Section D, on the 3-4 floor of Section B.

House 12
Work is underway to arrange a sand cushion under section E.
Work is ongoing on the arrangement of the tower crane.

Kindergarten
Work is underway to concretize the vertical elements of the 3 floors.

Residential Complex Ozernyi Hai Hatne

House 6
Front work - 98%
Adjacent area - 40%

House 7
Monolithic works
1.2 section - 97%
3,4,5 section - 85%
6.7 section - 97%
Laying of external and internal walls:
1st floor - 5%

House 8
Monolithic works - 99%
Laying of external and internal walls - 65%

House 9
Laying of external and internal walls:
1.2 section - 95%
3.4 section - 98%
5.6 section - 98%
Installation of window blocks
1, 2 section - 5%
3, 4 section - 90%
5, 6 section - 99%
Facade works
3, 4 section - 70%
5, 6 section - 98%

House 42
Crushed stone cushion - 80%
Concrete preparation - 75%
Baseplate - 75%
Basement 75%
Monolithic works:
Sections: 2, 3, 4 - 99%
Laying of external and internal walls:
Section 2:
2nd floor - 80%
3rd floor -10%
Section 3:
1st floor - 15%
Section 4:
1st floor - 98%
2nd floor - 95%
3rd floor - 80%

House 43
Monolithic works:
1 section - 99%
Section 2 - 99%
3.4 section -90%
Laying of external and internal walls:
1 section - 15%

Residential complex Prychal 8

Section 1
The roof is a machine room.
Arrangement of walls and partitions - 19-20 floor.

Section 2
The roof is a machine room.
Arrangement of walls and partitions - 20-22 floor.

Residential Complex Syretsky Sady

House 1
In the work interior decoration - painting - 99%
Improvement - 95%

House 2
Plaster, screeds - section 3, 2, 1 - 90%
Facade insulation - 99%
Elevators - 80%
Apartment renovation - 90%

House 3
Masonry - 95%
Roof arrangement - 40%
Windows - 85%
Facades - 70%
Apartments without repair - 50%

House 4
Windows - 85%
Facade insulation - 70%
Roof arrangement - 45%
Masonry - 95%
Plaster, ties - 85%

House 5
Windows - 18%
Start of work on the roof - 2%

RC Sky Avenue

House 1
Basis: Arrangement of pile fields for 4 and 5 sections; Section 3 - set the clearance.
Monolithic works: works on the arrangement of the floor slab 10 floors: 1 and 2 sections
Laying of walls and partitions: laying of walls on the 4th floor of 2 sections and on the 5th floor of 1 section.

RC Teremky

2 turns, 2 sections
Installation of baskets under air conditioning - 98%
Pasting of wallpaper in apartments with repairs - 90%
Installation of laminate in apartments with repairs - 40%
Installation of interior doors in apartments with repairs - 30%
The territory is being improved - 70%

2 turns, 3 sections
Pasting of wallpaper in apartments with repairs - 90%
Installation of laminate in apartments with repairs - 40%
Installation of interior doors in apartments with repairs - 30%
The territory is being improved - 70%

3 turns, 4 sections
Facade works - 98%
Installation of elevators - 85%
Installation of baskets under air conditioning - 70%
Improvement of the territory - 40%

3 turns, 5 sections
Facade works - 98%
Installation of elevators - 85%
Installation of entrance doors in apartments - 85%
Improvement of the territory - 40%

3 turns, 6 sections
Installation of windows is in progress - 98%
Home insulation is in progress - 97%
95% of facade works are in progress
Installation of elevators - 85%
Installation of entrance doors in apartments - 85%
Improvement of the territory - 40%

4 turns, 8 sections
Tested piles.

4 turns, 9 sections
Vertical element 6 floor.

4 turns, 10 sections
Vertical element 6 floors.

RC Tradytsiia

House 4
External networks - 70%
Plaster - 26th floor.
Electricity - basement.
Painter - 19, 20 floor.
Screed - 25, 23, 20 floor.
Facades - 80%
Roof - 85%
Finishing works in apartments (tile) - 4-11 floor.

RC Intergal City

Tower A
The piling is complete. In the work of installing reservoir drainage under the foundation.

Tower G
Work is underway to arrange the floor slab 7 floors.