Dynamics of construction as of 05.12.19

  • 05/12/2019

Dear buyers, We bring to your attention the dynamics of construction of all our metropolitan complexes. The status of the works is fixed as of 05.12.19.

Residential complex Akadem-Kvartal

House 1
Wall and partition arrangement, masonry - 99%
Installation of windows - 98%
Water supply and sewerage - 82%
Heating - 55%
Electricity - 80%
Fire protection systems - 33%
Wall plaster - 60%
Coupler Setting - 47%
IQF Finish - 10%
Facade arrangement - 25%
Elevator installation - 25%
Doors - 20%
Roof arrangement - 92%
Entrance group - 75%

House 2
Installation of windows - 99%
Water supply and sewerage - 65%
Heating - 34%
Electricity - 65%
Fire protection systems - 16%
Plastering of walls - 33%
Coupler Setting - 25%
Installation of metal doors in apartments and MZCs started - 6%
Clean stairwell trim - 15%
Elevator installation - 22%
Facade arrangement - 62%
Roof arrangement - 50%
Entrance group - 70%

Residential Complex Vladimirskyi

Facade (installation of granite 1-3 floor) - 55%
Wall plaster - 95%
Thermal insulation of walls with mineral wool - 95%
Ventilation and smoke removal - 80%
Roof arrangement - 95%
Installation and commissioning of lifts - 80%
Land improvement - 60%

Residential complex Malakhit

Masonry - kindergarten.
Installation of window structures - kindergarten.
Finishing works - 5-20 floor.
Facade works - 15%

Residential Complex Nivki-Park

House 5
Work on installation of windowsills and low tides on windows and balconies - 90%
Finishing works are carried out on sections A, E, B - 97%
Fine processing of MZC - 95%
Roofing works on sections A, B and E are underway - 97%
Work is underway on the arrangement of the facade - 97%
Laying tiles on walls of 1 floor.
Work is underway to connect the engineering networks - 99%
Work is underway to arrange the doors in TP5.
Entrance roof unit - 95%
Work is underway to adjust the elevators.
Work is underway to improve the surrounding area.

House 6
Work is underway to install metal doors on the first floors. Work is underway to arrange windowsills.
Finishing works are carried out on sections D, E and E - 80%
Work is underway on the installation of apartment doors and MZK: section D - 14th floor, section E - 14th floor.
section D - 16 floor.
Roofing works are underway on sections D, E and D - 95%
The front works on sections D, E, D are carried out - 95% (balconies of cold transitions). Laying tiles on walls of 1 floor (facade).
Work on the installation of elevators.
Entrance roof unit - 65%
Work is underway to improve the surrounding area.

House 7
Concreting of underground part of entrance groups on section E2.
Laying of walls: Section E2: 6, 9-13 floor. Section B: 3, 5-6, 11-13 floor. Section E1: 9-13 floor.

House 8
Laying of walls and partitions in sections B: 11, 12, 15 floor and roof; on sections B: 5, 12, 14 floor and roof; on sections D - 6, 10, 11, 12 floor and roof.
Installation works are underway for window structures on the 6th floor of Section D, on the 4-6th floor of Section B and B. Work is ongoing on the installation of electrical cables. Plaster works are underway.

House 12
Work is in progress on the arrangement of vertical elements in sections "G" and "I".
Work is underway to arrange the tower crane # 2.

Kindergarten
Concrete works are underway on the floor slab of 4 floors.

Residential Complex Ozernyi Gai Gatne

House 6
Facade works - 99%
Adjacent area - 70%
Finishing works:
Renovated apartments - 20%
IAC - 95%
Elevators - 99%

House 7
Monolithic works - 97%
Laying of external and internal walls - 10%

House 8
Monolithic works - 99%
Laying of external and internal walls - 85%
Installation of window blocks - 10%
Roof arrangement - 50%
External networks - 10%

House 9
Laying of external and internal walls - 99%
Installation of window blocks - 95%
Front work: - 70%
Finishing works:
Wall plaster - 25%
Water supply and sewerage - 20%
Heating - 10%
Electricity supply - 10%
Installation of elevators - 20%

House 42
Monolithic works: - 80%
Laying of external and internal walls: - 30%
Waterproofing cap - 70%

House 43
Monolithic works: - 99%
Laying of external and internal walls: - 33%
Waterproofing cap - 60%

Residential complex Prychal 8

Section 1
Roof - Machine Room - 98%
Arrangement of walls and partitions - 19-20 floor.

Section 2
Roof - machine room - 90%
Arrangement of walls and partitions - 20-22 floor.

Section 3
Vertical element 5 floors.

Section 4
Vertical element 5 floors.

Residential Complexes Syretsky Sady

House 1
Improvement - 95%

House 2
Plaster, screeds - section 3, 2, 1 - 95%
Facade insulation - 99%
Elevators - 80%
Apartment renovation - 90%

House 3
Masonry - 95%
Roof arrangement - 40%
Windows - 85%
Facades - 70%
Apartments without repair - 50%

House 4
Windows - 87%
Facade insulation - 70%
Roof arrangement - 45%
Masonry - 95%
Plaster, screeds - 87%

House 5
Windows - 65%
Roofing started - 5%

House 8
Your own field is done.

RC Sky Avenue 

House 1
Foundations: Section 5 - Installation of the grid.
Monolithic works:
1 and 2 sections: work is underway to arrange the vertical elements of the 11th floor.
3 and 4 sections: arrangement of vertical elements of the plinth.
Laying: on the 7th floor of 2 sections and on the 6th floor of 1 section.

RC Teremky

2 turns, 2 sections
Installation of baskets under air conditioning - 98%
Laying laminate in apartments with renovated - 90%
Installation of interior doors in apartments with repairs - 70%
Improved territory - 85%
2 turns, 3 sections
Installation of baskets under air conditioning - 98%
Laying laminate in apartments with renovated - 90%
Installation of interior doors in apartments with repairs - 60%
Improved territory - 85%
3 turns, 4 sections
Installation of elevators - 95%
Installation of radiators inside the apartments - 60%
Laying of floor tiles in MZC - 95%
Installation of baskets under air conditioning - 85%
Territory improvement - 80%
3 turns, 5 sections
Installation of elevators - 95%
Installation of radiators inside the apartments - 60%
Laying of floor tiles in MZC - 95%
Installation of baskets under air conditioning - 85%
Territory improvement - 80%
3 turns, 6 sections
Facade works - 98%
Installation of elevators - 95%
Installation of radiators inside the apartments - 60%
Laying of floor tiles in MZC - 95%
Installation of baskets under air conditioning - 85%
Territory improvement - 80%
4 turns, 8 sections
The vertical elements of the first floor are overlapped.
4 turns, 9 sections
The vertical elements of the 9th floor are overlapping.
4 turns, 10 sections
The vertical elements of the 9th floor are overlapping.

RC Traditsiya

House 4
External networks - 80%
Electricity - basement.
Painter - 23 floor.
Screed - 1, 26 floor.
Facades - 85%
Roof - 90%
Finishing works in apartments (tile) - 6-14 floor.

Intergal City

The "A" tower is complete with reservoir drainage. The work is the foundation.
On the tower "G" - work is underway to arrange the floor slab 5 floors.
Work has begun on the arrangement of the monolithic frame of the tower "B".