Company "Intergal-Bud": the dynamics of construction on 06.10.17

  • 06/10/2017

Residential complex "Vladimirsky"

Foundation device - 100%.

Basement walls waterproofing - 100%.

Completed the overlap of the 3rd floor.

The construction of vertical walls - the 4th floor.

 

Residential complex "Syretsky Gardens"

House number 1

Section 1: The construction of the 2nd floor has begun. Laying concrete bricks.

Section 2: The construction of the 1st floor has begun.

 

House number 2

Work is underway on the gravel base under the base pla1e.

 

House number 3

Cleared the area.

 

House number 4

Dug a pit.

Completed soil testing piles.

 

Residential complex "Yaskravy"

 

House number 4:

Finished installing a fire alarm.

Completed installation of low-voltage systems.

Installation of the ventilation system is completed.

Internal power supply system - 100%.

Water supply and sewage system - 100%.

Device on-site networks - 100%

Arrangement of the entrance to the house - 99%.

Landscaping completed.

 

House number 5:

The monolithic frame device is 100% complete.

Brickwork completed.

Installation of window structures is completed.

Plumbing work - 99%.

Electrical work - 95%.

Ventilation and smoke removal - 81%.

Low-voltage systems - 87%.

Plaster walls - 100%.

Floor screed - 100%.

Roof installation - 99% (waterproofing continues).

Installation and commissioning of elevators - 75%.

 

House number 6:

In section number 1:

Completed the construction of the 7th floor.

The readiness of the 8th floor vertical is 40%.

Basement waterproofing - 85%.

Basement insulation - 80%.

 

In section number 2:

Completed construction of the 8th floor.

The construction of the vertical of the 9th floor has begun.

Basement waterproofing - 85%.

Basement insulation - 80%.

 

In section number 3:

The construction of the 9th floor has been completed.

Basement waterproofing - 85%.

Basement insulation - 80%.

 

House number 7:

The device of the monolithic frame section number 1 - 90%. In the work of the 24th floor.

The device of the monolithic frame section number 2 - 90%. In the work of the 24th floor.

Brickwork is being carried out: section No. 1 - 57% (13th – 20th floors in work), section 2 –28% (in work 7, 8, 9th floors).

The device of the ventilation ducts is being carried out: in section 1, the works were performed at 86% (in the 22nd -24th floors); in section number 2 the work was performed on 94% (in the 23rd and 24th floors).

Plumbing works have been started: on section 2 works are being carried out on the 1st and 2nd floors.

Work has begun on ventilation and smoke removal - 10%.

Started plastering of walls and screed equipment.

Installation of window constructions: in sections 1 - 20% (4-8 floors), in section 2 - 6% (2-4 floors).

 

Residential complex "Lake Guy Gatne"

 

House number 2:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 100% (masonry attic floor).

The device of monolithic floor slabs - 100%.

The device partitions - 100%.

Roof -30%.

Facade -35%.

Interior decoration - 20%.

Improvement of the local area - 5%.

External networks - 10%.

 

House number 3:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 100%.

The device of monolithic floor slabs - 100%.

The device partitions - 100%.

Roof - 20%.

Facade -35%.

Interior decoration - 20%.

Landscaping of the local area - 5.

External networks - 10%.

 

House number 4:

The foundation is completed - 100%.

The basement is 100% waterproofed.

The device walls - up to the 5th floor.

Finishing - 10%.

Screed - 10%.

Heating networks - 20%.

Electricity - 20%.

 

House number 5:

Foundation device - 100%.

The basement is 100% waterproofed.

The device walls - up to the 4th floor.

Partitions - up to the 2nd floor.

 

Residential complex "Demiivka"

 

House number 2:

The slab of the 20th floor is being built.

Mounted ventilation units and staircases on the 15th floor, inclusive.

Brick masonry on floors 1-5, 7-10 and 13 floors is completed.

Work continues on the brickwork on the 6th, 11th, 12th floors.

Installation of water risers is in progress.

Finished waterproofing basement.

Readiness of monolithic structures of input groups - 90%.

Installation of windows 2-6-th floors.

 

Residential complex "Park Lakes"

 

House number 11:

The construction of external walls and partitions is completed.

The construction of internal walls and partitions is completed.

Roof installation is completed.

Installation of window structures is completed.

Facade installation is complete.

Plaster walls finished.

Plumbing works - installation of meters, pressure testing of the system, commissioning of individual heat points.

Floor screed is finished.

Installation of the internal power supply system - work is underway on the installation of the switchboard and connecting the house to a permanent circuit.

Low-voltage systems - 96%. The commissioning and installation of sensors are completed.

Ventilation and smoke removal - 97%. Before the end, only the commissioning work remains.

Installation of elevators - 93%. Commissioning is underway.

 

House number 12:

The monolithic frame device is performed on the 26th floor (96%).

The construction of walls and partitions is performed on floors 17-21 (56%).

The device ventilation channels - is performed on the 19th floor (68%).

Installation of window structures - is carried out on the 9-11th floors (37%).

Plumbing works - vertical up to 13 floors (33%).

Electrical work - wiring done up to the 8th floor (26%).

Ventilation and smoke removal - performed on floors 3-8 (11%).

Low-voltage systems are performed on the 2nd floor (8%).

Plaster walls - performed on 4-6 floors (19%).

Equipping common areas with wallpaper and tiles - finished 2nd floor.

 

House number 13:

The monolithic frame device is made on the 16-18th floors (63%).

Started equipping walls and partitions.

The device ventilation channels - is performed on the 14th to 16th floors (51%).

Entrance group - partly made iron-concrete frame (11%).

 

Residential complex "Traditsia"

 

House number 2:

The device is a monolithic slab 22nd floor.

Bricklaying is carried out on the 17th floor, inclusive.

 

House number 3:

Brickwork completed.

Facade work completed.

Finishing work on the 15th floor.

Screed to the 20th floor.

Plastering works - 25th floor.

Plumbing works are underway on all floors.

 

 

Residential complex "Nyvky Park"

 

House number 1:

The monolithic frame device is complete.

The device walls and partitions completed.

Installation of window designs is completed.

The installation of internal engineering continues.

Work continues on interior decoration:

Section A - floor screed and plaster on the 14th floor;

Section B - screed and plastering work completed;

Section B - screed and plastering work completed.

Door installation performed:

Section A - on the 10th floor;

Section B, C - on the 13th floor.

The device facade is made at 70%.

Work is underway on the installation of elevators.

Work is underway on the structure of the metal structures of the entrance groups.

Work is underway on the design of external engineering networks.

 

House number 2:

The monolithic frame device is complete.

The device walls and partitions completed.

Installation of window designs is completed.

Work continues on internal engineering.

Section G - screed and plastering work completed;

Section D - floor screed and plaster on the 11th floor.

Work continues on interior decoration.

Work is underway on the installation of elevators.

Work began on the device facade.

Work is underway on the design of external engineering networks.

 

House number 3:

In sections G, D, W, work is underway to build a monolithic frame on the 14th floor.

The laying of the walls continues: works are being carried out on the 7th and 8th floors of sections G, D, J.

 

House number 4:

In sections E, B, C, a monolithic frame of the 10th floor is maintained.

The laying of the walls continues: sections B, C on the 2nd floor; Section E on the 3rd and 4th floors.

 

Residential complex "Otradny"

House number 1:

The monolithic frame device is 100% complete.

The brickwork of the external walls is 100% complete.

Facade painting is underway - 80%.

Plastering work performed on the 16th floor.

Screed is made on the 16th floor.

Finishing work is underway at the MZK.

 

House number 2:

The monolithic frame device is 100% complete.

Work is underway on the installation of brickwork: on the 16th floor.

The device waterproofing basement completed.

Backfill done.

Work is underway on the arrangement of the roof - 80%.

 

House number 3:

Reinforcement and concreting performed up to the 16th floor.

The construction of the 16th floor flooring has begun.

The waterproofing device of the basement is completed.

Brick wall on the 4th floor.

 

House number 4:

Base plate is made.

The vertical elements of the 7th floor are being built.

Brickwork is used on the 1st floor - 40%.

 

House number 5:

Work is underway to arrange the vertical elements of the basement floor - 70%.

 

Residential complex "Teremki"

 

1st house:

Installation of vertical floors 18 floors;

Facade work at the 14th floor level

 

2nd house:

Installation of vertical floors of the basement.

Work is underway on the arrangement of the pit on the 4th section of the 3rd stage.

 

Residential complex "Malachite"

 

3rd house:

Internal finishing works from the 2nd to the 9th floor are carried out on sections 302-303 - completed by 90%.

Began to landscaping recreation areas on the roof.

Work is done on the installation of external engineering networks:

- domestic sewage K1;

- rainwater drain K2;

- plumbing B1;

- Electricity of the net.

 

4th house:

Monolithic frame, section 404 - 100%.

Work is underway on the brickwork from the first to the sixth floors of section 404.

Work is underway to install vertical reinforced concrete structures on sections 405-406, the mark is 0.100.

 

Parking P1. Work is underway on the installation of reinforced concrete foundations, the mark is 6.300.

Parking P2. Work is underway to install vertical reinforced concrete structures, the mark is 6.300.

Section 401. The foundation is made at 100%, the mark - 3.100.

Section 402-403. Pile field performed at 100%.