Dynamics of construction as of 07.06.19

  • 07/06/2019

Dear buyers, we bring to your attention the dynamics of construction as of 07.06.19

Housing Complex Akadem-Kvartal

Building 1

Parapet

Masonry – 17th floor.

Glazing – 9th floor.

 

Building 2

Parapet

Masonry – 14th-15th floor.

Glazing – 6th, 7th, 8th floor.

 

Housing Complex Volodymyrskyi

 

Installation of the “smart home” system - 4% (layout of pipes on 7-21 floors.

Installation of individual heat plants - 60% (equipment installation is under way).

Wall plastering - 7% (individual heat plants)

Screeding - 29% (sole plate, 12th floor)

Hydro and thermal insulation in the passage area - 30%

Masonry - 3 floor and plinth.

Electrical works - 15% (5-21 floors).

Low-voltage systems - 11% (works started on 5-19, 2-3 floors).

Ventilation and smoke removal - 12% (1-11 floors; 4 smoke removals on the roof).

Plumbing works - 43% (works on installation of risers of water supply, sewerage, drainage sewerage on 1-24 floors are being performed, floor distribution of heating and water supply on the 20 and 21 floors is being performed).

Finishing works in common facilities - 52% (plastering of ceilings 6-10, 12-14, 23-24 floors).

Installation of door structures - 45% (4-24 floors).

Installation of elevator equipment - 75% (installation of cargo and office elevators).

Roofing - 55% (steam and hydro-barriers, extruder, keramzite concrete screed, screed made of fine-grained concrete, slag wool along the perimeter).

Installation of window structures - 5-16 floors.

Installation of facades - 44% (metal-plastic balcony blocks, vapor barrier).

 

Housing Complex Malachite

 

Building No. 4

Finishing works - 99%

Facade works - 99%

Landscaping - promenade area - 80% (waterproofing of parking lots).

 

Building No. 5

Vertical element of the 20 floors.

Masonry - 1-12 floors.

Active works on the utilities laying are underway.

 

Housing Complex Nyvky Park

 

Building No.  5

Waterproofing of A, B and E sections basements is underway.

Works on the backfill of the pit.

Works on windows installation: 1st floor

Works on laying the floor screed are underway.

Finishing works are carried out in sections A, E, B-basement, 5-12, 17 floors.

Roofing works in sections A, B and E are underway.

Facade works are underway.

Engineering networks tie-in.

Works on setting up a monolithic framework for the heat transfer station are underway.

Monolithic works on the installation of entrance spaces are underway.

Installation of elevators.

Installation of doors is in progress: section A - 2-5 floors, section B - 2-5, 7 floors and basement, section E - 2, 4-6 floors.

The ventilation system installation is underway.

Installation of doors on the 1st floor of sections A.

 

Building No. 6

Walls masonry 7, 11, 14, 17 floors of section G; 10, 12, 15, 16, 17 floors of section E; 11, 15, 16, 17 floors and roof of section D.

Waterproofing of basements is underway.

Works on backfill of the pit.

Installation of windows: 10-17 floors of sections G, E, D.

Finishing works on the 6-11 floors of section G, D, E.

Screeding: section D - 10-11 floors, section E - 9,10 floors, section G - 3, 4, 6 floors.

Engineering networks tie-in continues.

Roofing works on sections G and E are underway.

Facade works on section G are underway.

 

Building No. 7

Work is underway to arrange the floor slab 9 floor section E2.

Work is underway to arrange the vertical elements of the 9th floor in section E1.

Work is underway to arrange the floor slab 8 floors in section V.

Basement waterproofing on sections V, E1, E2.

Backfill of the sinuses of the pit.

Laying of walls: section E2: 1 floor. Section B: 1st and 2nd floor.

 

Building No.  8

Work is underway to lay the 13-floor floor slab in section G.

Work is underway to arrange the vertical elements of the 13th floor in section B.

Work is underway to arrange the vertical elements of the 13th floor in section V.

Basement waterproofing on sections G, B, V.

Backfill of the pit.

Walls and partitions masonry on sections V: 1, 3, 4, 5 floors; on section B: 2-4 floors and basement; on section G - basement, 1-5 floors.


Housing Complex Ozernyi Hai Hatne

Building No.  5

Interior decoration - 98%

Entrance groups - 98.5%

Facade - 99.90%

Adjacent territory - 70%

 

Building No. 6

Exterior and interior walls masonry:

1st floor - interior - 99%

2nd floor - interior 99%

3rd floor - interior 99%

4th floor - interior 99%

5th floor - interior 99%

6th floor - interior 99%

7th floor - interior 99%

8th floor - interior 99%

Installation of window blocks:

Section 1- 7th floor 90%

Section 2 - 7th floor 90%

Section 3 - 9th floor 90%

Finishing works:

Plastering of walls:

Section 1 - 60%

Section 2 - 60%

Section 3 - 60%

Floor screed:

Section 1- 60%

Section 2 - 60%

Section 3 - 60%

Facade works:

Section 1- 80%

Section 2 - 70%

Section 3 - 60%

 

Building No.  7

Foundation: 35%

Baseplate 10%

 

Building No.  8

4th floor - 25%

 

Building No. 9

5th floor: 1, 2 sections - 40%

Exterior and interior walls masonry:

1, 2 section: 1 floor 80% exterior - interior - 80%

2nd floor -80% exterior - interior - 80%

3rd floor -10% exterior - interior - 10%

3,4 section: 1 floor -80% exterior - interior - 80%

2nd floor -90% exterior - interior - 90%

3rd floor -90% exterior - interior - 50%

5,6 section: 1 floor -90% exterior - interior - 90%

2nd floor - 90% exterior - interior - 90%

 

3rd floor - 80% exterior - interior - 80%

4th floor - 60% exterior - interior - 60%

 

Building No.  42

Granular base - 70%

Concrete preparation - 70%

Base slab - 50%

Basement - 50%

1st floor - 50%

 

Building No. 43

Granular base - 50%

Concrete preparation - 50%

Base slab - 50%

Basement - 50%

1st floor - 50%

2nd floor - 25%

 

Housing Complex Prychal 8       

 

Section 1

Monolithic frame installation (vertical element 11 floors) - 52%

Walls and partitions installation - 1-4 floor.

 

Section 2

Monolithic frame installation (floor slab over 12 floors) - 53%

Walls and partitions installation - 1-4 floors.

 

Housing Complex Syretski Sady

 

Building 1

Interior decoration - painting - 89%

Windows - 95%

 

Building 2

Windows - 90%

Plastering, screeds - section 3, 2, 1 - 50%

Facade insulation - 40%

 

Building 3

Masonry - 95%

Roofing - 10%

 

Building 4

Windows - 75%

Facade insulation - 45%

Roofing - 15%

Masonry - 95%

 

Building 5

Floor slab over the 18th floors.

Masonry - 10th floor.

Housing Complex Teremky

 

1 phase

Building communications tie-in - 90%

Repair works - 94%

2 phase, 2 sections

Facade works - 90%

Insulation - 95%

Roofing - 90%

Installation of air conditioning baskets - 52%

Painting of common facilities ceilings - 80%

Installation of elevators - 90%

2 phase, 3 section

Facade works - 90%

Insulation - 95%

Roofing - 90%

Installation of air conditioning baskets - 52%

Painting of common facilities ceilings - 80%

Installation of elevators - 90%

3 phase, 4 section

Installation of windows - 85%

Insulation - 70%

Plastering of walls in apartments without repair - 60%

Floor screed - 40%

Electricity wiring in apartments with redecoration - 15%

3 phase, 5 section

Installation of windows - 85%

Insulation - 70%

Plastering of walls in apartments without repair - 60%

Floor screed - 40%

Electricity wiring in apartments with redecoration - 15%

3 phase, 6 sections

Installation of windows - 85%

Insulation - 55%

Plastering of walls in apartments without repair - 60%

Floor screed - 40%

Electricity wiring in apartments with redecoration - 15%

 

Housing Complex Tradytsia

 

Building No. 4

Vertical element of the 27th floors, floor slab of the 27th floors.

Masonry - 15, 16, 18, 19, 21, 22 floors and the basement.

External networks - 60%

Plaster - 13-15 floors.

Electricity - 10-15 floors.

Sewer (risers) - 50%

Painting work - 5-6 floors.

Screed - 9th floor and the basement.

 

Housing Complex Yaskravyi 

 

Building No. 6

Installation of window structures - 98%

Plumbing - 96%

Electrical works - 85%

Ventilation and smoke removal - 80%

Low-voltage systems - 60%

Screed - 99%

Common facilities finishing - 99%

Elevator installation and commissioning - 90%

Facade - 99%

Roofing - 99%

Entrance group - 95%

Landscaping - 66,7%