Dynamics of construction as of 07/06/19

  • 07/06/2019

Dear buyers, we offer to your attention the dynamics of construction as of 07.06.19

RC «Akadem-Kvartal»

House 1
Parapet
Laying - 17th floor.
The glass is 9th floor.

House 2
Parapet
Laying - 14-15 floor.
Glass - 6, 7, 8th floor.

RC «Volodymyrsky»

The arrangement of the "smart house" system - 4% (layout of pipes on 7-21 floors.
Installation of ITP (individual thermal points) - 60% (installation of equipment is carried out).
Plaster walls - 7% (ITP)
Stacking - 29% (socle, 12th floor)
Arrangement of hydro-thermal insulation in the zone of passage - 30%
Laying - 3rd floor and a socle.
Electrical works - 15% (5-21 floor).
Weakness systems - 11% (Works started on 5-19, 2-3 floors).
Ventilation and smoke removal - 12% (1-11th floor, 4 smoke exhausters installed on the roof).
Sanitary engineering works - 43% (works are being carried out on installation of water supply, drainage, drainage drains on floors 1-24, and a superficial heat and water supply on the 20th and 21st floors).
Arrangement of finishing works MZK - 52% (shuttering ceilings 6-10, 12-14, 23-24 floor).
Installation of door structures - 45% (4-24 floor).
Installation of lift equipment - 75% (installation of cargo and office elevators).
The installation of the roof is 55% (steam and hydro barriers are arranged, an extruder, a claydite slab, a fine-grained concrete mix, a minewat along the perimeter, is installed, water absorbing funnels are installed, vents are laid out, mines are pulled over the perimeter of the minewat with a glue mixture)
The arrangement of window constructions is 5-16 floors.
Facade installation - 44% (in the work of the metal-plastic balcony blocks, steam-insulation is carried out).

RC «Malakhit»

House number 4
Finishing works - 99%
Facade works - 99%
Improvement - area promenades - 80% (waterproofing of parking lots).

House number 5
Vertical element of the 20th floor.
Laying - 1-12 floor.
The work on laying engineering networks is actively under way.

RC «Nyvky-Park»

House number 5
Works on waterproofing of basements of sections A, B and E are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are under way: 1 floor
Work is done on laying a floor screed.
There are finishing works in the sections A, E, B-basement, 5-12, 17 floor.
Work is underway to install the roof on Sections A, B and E.
Work is underway on the facade arrangement.
Work is ongoing on connecting engineering networks.
Work is underway to install a monolithic frame under the TP.
Conducted monolithic works on the arrangement of incoming groups.
Lifts are being erected.
Doors are under construction: section A - 2-5 floor, section B - 2-5, 7 floor and basement, section E - 2, 4-6 floor.
Works on installation of doors on the 1st floor of section A.

House number 6
Masonry of walls 7, 11, 14, 17 above section Г; 10, 12, 15, 16, 17 above section E; 11, 15, 16, 17 floor and roof section D.
Works on waterproofing basements are underway.
Work is underway on the backfill of the foundation pit.
Works are underway on the installation of windows: 10-17 floors of sections G, E, D.
Decoration works on the 6th-11th floor of sections D, D and E are underway.
Work is carried out on the installation of the screed: section D - 10-11 floor, section E - 9,10 floor, section G - 3, 4, 6 floor.
Work is ongoing on connecting engineering networks.
Work is underway to install the roof on sections G and E.
Facade works on section G.

House number 7
Works are underway on the installation of the floor slab floor 9 on the section E2.
Work is underway on the arrangement of vertical elements of the 9th floor in section E1.
Work is underway on the arrangement of the floor slab floor 8 on the section B.
Installation of waterproofing basements in sections B, E1, E2.
Reverse fall-down of the sinuses of the pit.
Wall laying: section E2: 1st floor. Section B: 1st and 2nd floor.

House number 8
Work is underway to install the floor slab of the 13th floor in section G.
Work is underway on the arrangement of vertical elements of the 13th floor in section B.
Work is underway on the arrangement of vertical elements of the 13th floor in section B.
Arrangement of waterproofing basements in sections G, B, V
Reverse fall-down of the sinuses of the pit.
Laying of walls and partitions on section B: 1, 3, 4, 5 floor; on section B: 2-4 floor and basement; on section G - a basement, 1-5 floor.

RC «Ozerny Gai Gatne»

House No. 5
Interior decoration - 98%
Ingroups - 98.5%
Facade - 99.90%
Precinct territory - 70%

House number 6
Masonry of external and internal walls:
1st floor - internal - 99%
2nd floor - internal 99%
3rd floor - internal 99%
4th floor - internal 99%
5th floor - internal 99%
6th floor - internal 99%
7th floor - internal 99%
8th floor - internal 99%
Installation of window blocks:
1 section - 7 floor 90%
2nd section - 7th floor 90%
Section 3 - 9th floor 90%
Finishing work:
Plaster walls:
1 section - 60%
Section 2 - 60%
Section 3 - 60%
Floor tension:
1 section - 60%
Section 2 - 60%
Section 3 - 60%
Facade works:
1 section - 80%
Section 2 - 70%
Section 3 - 60%

House number 7
Foundation: 35%
Foundation slab 10%
House number 8
4th floor - 25%
House No. 9
5th floor:
1, 2 sections - 40%
Masonry of external and internal walls:

1, 2 sections: 1 floor 80% external - internal - 80%
2nd floor -80% external - internal - 80%
3rd floor -10% external - internal - 10%
3.4 sections: 1st floor -80% external - internal - 80%
2 floors -90% external - internal - 90%
3rd floor -90% external - internal - 50%

5.6 sections: 1st floor -90% external - internal - 90%
2nd floor - 90% external - internal - 90%
3rd floor - 80% external - internal - 80%
4th floor - 60% external - internal - 60%

House No. 42
Rubbing pillow - 70%
Concrete preparation - 70%
Foundation slab - 50%
Basement - 50%
1st floor - 50%

House No. 43
Rubbing Pillow - 50%
Concrete preparation - 50%
Foundation slab - 50%
Basement - 50%
1st floor - 50%
2nd floor - 25%

RC «Berth 8»

Section 1
Arrangement of a monolithic frame (vertical element of the 11th floor) - 52%
Arrangement of walls and partitions - 1-4 floor.

Section 2
Arrangement of a monolithic frame (plate overlap 12 floors) - 53%
Arrangement of walls and partitions - 1-4 floor.

RC «Syretsky gardens»

House 1
Inside the interior decoration - painter - 89%
Windows 95%

House 2
Windows - 90%
Plaster, screws - section 3, 2, 1 - 50%
Insulation of the facade - 40%

House 3
Laying - 95%
Roofing - 10%

House 4
Windows - 75%
Insulation of the facade - 45%
Roofing - 15%
Laying - 95%

House 5
Plate overlapping over the 18th floor.
Laying is 10th floor.

RC «Teremki»

1 queue
Connected to home communication - 90%
Performed repairs - 94%

2nd line, 2nd section
Performed facade works - 90%
Warming up of the house is carried out - 95%
Roofing works are carried out - 90%
Installation of baskets for air conditioners is carried out - 52%
Painting of IZK ceilings - 80%
Mounting of elevators is carried out - 90%

2nd stage, 3rd section
Performed facade works - 90%
Warming up of the house is carried out - 95%
Roofing works are carried out - 90%
Installation of baskets for air conditioners is carried out - 52%
Painting of IZC ceilings is carried out - 80%
Mounting of elevators is carried out - 90%

3rd stage, 4th section
Installing windows is up to 85%
Warming up of the house is carried out - 70%
Execution of plaster walls in apartments without repair - 60%
Filling the floor screed - 40%
Breeding of electricity in renovated flats is carried out - 15%

3rd turn, 5th section
Installing windows is up to 85%
Warming up of the house is carried out - 70%
Execution of plaster walls in apartments without repair - 60%
Filling the floor screed - 40%
Breeding of electricity in renovated flats is carried out - 15%

3rd turn, 6th section
Installing windows is up to 85%
House insulation is carried out - 55%
Execution of plaster walls in apartments without repair - 60%
Filling the floor screed - 40%
Breeding of electricity in renovated flats is carried out - 15%

RC «Tradition»

House number 4
Vertical element of the 27th floor, floor slab 27th floor.
Laying - 15, 16, 18, 19, 21, 22 floor and basement.
External networks - 60%
Plaster - 13-15 floors.
Electricity - 10-15 floors.
Sewerage (risers) - 50%
Painters - 5-6 floors.
Tightening - 9th floor and basement.

RC «Yaskraviy»

House number 6
Installation of window constructions - 98%
Sanitary engineering works - 96%
Electrical work - 85%
Ventilation and smoke removal - 80%
Low-power systems - 60%
Screw arrangement - 99%
Finishing of IGC - 99%
Installation of elevators and start-up and adjustment works - 90%
Facade arrangement - 99%
Roofing - 99%
Incoming group - 95%
Amenties - 66.7%