Dynamics of construction as of 08.02.19

  • 08/02/2019

LCD «Volodymyrsky»


Waterproofing - 5-10 floor, base.
Laying - TP, 17, 19, 24, 25 floor.
The arrangement of internal power supply networks is 5-9 floors.
The arrangement of internal heating and ventilation networks is 1-5 floors.
Work has begun on the arrangement of internal water supply and sewerage networks.
Installation of finishing works MZK - 7%
Installation of door structures and hinges - 9.28%
Roofing - 16%
The arrangement of metal fence staircases - 6 floors.
Arrangement of external engineering networks - 18%


LCD «Syretsky gardens»


House 1
Inside, the interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.

House 3
Laying - 13-15 floor.

House 4
Laying - 1-22 floor, TP.
Windows - 2-22 floors.

House 5
Vertical element of 3rd floor.


LCD «Bright»


House number 6
Works on the arrangement of walls and partitions, masonry (external contour - 96%)
Installation of window constructions - 76%
Sanitary engineering works - 64.9%
Electrical works - 28,9%
Ventilation and smoke removal - 11.1%
Weakness systems - 22,2%
Plaster Wall - 50.5%
Screw arrangement - 72.3%
Interior decoration - 33.5%
Installation of elevators and start-up and adjustment works - 75%
Facade arrangement - 95%
Roof installation - 92.3%
Incoming group - 82.3%
Amenties - 0.7%


LCD Park Lakes

House No. 13

Installation of window constructions - 98%

Sanitary work - 86%

Electrical work - 74%

Ventilation and smoke removal - 57%

Weak-current systems - 44%

Finishing of IGC - 99%

Installation of elevators and start-up and adjustment works - 90%

LCD «Ozerny Gai Gatne»

House No. 5
Interior decoration - 95, 5%
Facade - 99.9%

House number 6
Masonry of external and internal walls:
1st floor - internal - 95%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%

House No. 9
Foundation foundation: 1, 2 sections - 50%


LCD «Tradition»

House number 2

The clean finishing of apartments is being actively pursued.

House number 4

Vertical element of the 17th floor, floor slab 17th floor.

Laying - 5-10 floor and basement.
Extranets - 20%

LCD «Malakhit»

House number 4
Windows - 99%
Finishing works - 1-21 floor.
Facade works - 25%
Improvement - promenade area - 40%

House number 5
Slab floor 3 floors.

LCD «Nyvky-Park»

House number 3
Work is under way to start the heat supply.
Transfer of apartments to investors.

House number 4
Lifts are being adjusted.
Work is ongoing on the finishing of apartments with renovations.
Finished works on the facade arrangement.
Work is underway on installation of window drafts and baskets for air conditioners.

House number 5
Masonry is carried out: in the basement, on 12, 13, 14, 15, 16, 17 floors and roof sections A; on 9, 11 floors and basement section E; on the 8th floor of section B.
Work is being done on the laying of Vent. shafts on roof sections B and E.
Works on waterproofing of basements of sections A, B and E are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are underway: 8-10 floors in sections A, B and E.
The work on laying the fire safety system cable is underway: Section A 2-9 floor.

House number 6
Installation of parapets in section G.
Installing parapets in section E.
Installation of parapets in section D *.
Masonry is carried out: 4, 5, 7, 8 floor and basement on section Г; 5, 7, 8 floor on section E; 1, 7, 8 floor on section D *.
Works on waterproofing basements are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are underway: 4-6 floors in sections G, E, D *.

House number 7
Work is underway on arrangement of vertical elements of the 1st floor in section Е2.
Work is underway on the arrangement of the slab ceiling of the basement in section E1.
Works on the arrangement of vertical elements of the basement under section B.

House number 8
Works on the arrangement of the plate floor 4 floors in section G *.
Work is underway on the arrangement of the ceiling slab of the 4th floor in Section B **.
Work is carried out on the arrangement of vertical elements of the 4th floor in section B.


LCD «Otradny»

House number 3

Installation of metal-plastic windows - 98%

Works on the arrangement of facades - 98%

Work is underway on installation of electrical and plumbing works - a socle, an ITP, an electrical and mechanical department, installation of fixtures, installation of input automata in apartments.

There are finishing works on floors 4, 5, 8, 9, 13, and 14 (apartments with repair).

House number 4

Installation of metal-plastic windows - 98%

Works on the arrangement of facades - 95%

Work is underway on arrangement of electrical and plumbing works - a socle, 5, 8, 9 floor.

There are finishing works on 4, 5, 8, 9, 13, 14 floors (apartments with repair).

House number 5

Works on installation of metal-plastic windows - 95%

Work is underway on plaster laying on the 8th and 9th floor (apartments with renovations).

Works are underway to install electrical and plumbing works from the 6th to the 15th floor.

Installation of equipment for passenger and freight elevators

Work is underway to insulate the ground floor.

Works are being carried out on laying of ventilation shafts from brick on a roof.

Works on installation of doors on the technical floor.

Arrangement of cement-sand link - 9, 10th floor.

LCD «Akadem-Kvartal»

House number 1
Plate of flooring on the 18th floor.
Masonry - 6th floor.


House number 2
Laying - 1st floor.
Vertical element of the 19th floor, floor plate of the 18th floor.


LCD «Teremki»

1 queue
Work is being done on painting the facade, painting ceilings in renovated apartments.
Internal engineering and plumbing work are carried out.
Installing baskets for air conditioners is underway.
Connected to home communication.
Repair works are carried out on floors 4, 13-14.
2nd line, 2nd section
Roofing works are being performed.
Plaster walls - 3, 4, 9, 11, 13, 14, 18 floor.
Filling the floor screed - 2-11 floors.
Work is carried out on insulation of the house.
2nd stage, 3rd section
Roofing works are being performed.
Plaster walls - 3, 4, 9, 11, 13, 14, 18 floor.
Filling the screed of the floor - from 2 to 11 floors.
3rd stage, 4th section
Masonry from 1 to 13 floor is underway.
Laying - 14-20 floors.
3rd stage 5th section
Masonry from 13th to 19th floor is underway.
3rd stage 6th section
Overlapping of vertical elements of the 25th floor is underway.
Masonry from 13th to 19th floor is underway.