Progress of construction as of 08.11.18

  • 08/11/2018

RC "Volodymyrskyi"

Pouring of vertical structures over the 24th floor is completed.
Works on installation of horizontal encasement for the slab over the 24th floor.
Works on concealed wiring on typical residential floors inside monolith structures are in progress. 
Installation of internal heating network and ventilation, internal water supply network and sewage, low-current networks, smart-home system, screed, wall plaster, decoration of GUPs – 5th floor.


RC “Syretski Sady” 

Building No. 1
Completion of installation of windows and balconies – 99%.
Plumbing works –4-6, 8, 10  floors. 
Façade – heat insulation of walls – 80%. 
Entrance groups – basements are completed

Building No. 2 
Brickworks – 1st to 14th floor.
Roofing is in progress – sections 1, 2 and 3 - 1st layer.
Windows – 1-2 floors (section 3)

Building No. 3 
Installation of frame structures – 1-16 floors

Building No.4
Installation of frame structures – 1-22th floor
Brickworks – 1st to 14th floor.
Windows – 2nd to 6th floor.

Building No.5
Testing of pile field is completed. Foundation is completed.

RC “Yaskravyi”

Building No.6 
Works on installation of walls, partitions, brickworks (external -90%, internal – 96.7%) are in progress. 
Installation of window structures-76%
Plumbing works –41%
Electric wiring works – 14.7%
Ventilation and smoke exhaust system – 5.6%
Low-current systems – 8.9%
Wall plastering – 22%
Installation of screed – 27.4%
Decoration of GUPs – 8.7%
Installation and adjustment of elevators– 70%
Façade works – 58.3%
Roofing – 88.3%
Entrance group – 30%

Building No. 7 
Plumbing works – 96%
Electric wiring works – 88%
Ventilation and smoke exhaust system – 92%
Low-current systems – 94%
Finishing of GUPs – 98%
Installation and adjustment of elevators – 89%
Development of adjoining territory – 85%

RC “Parkovi Ozera” 

Building No. 12 
Decoration works inside apartments.

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96% 
Plumbing works – 47%
Electric wiring works – 37%
Ventilation and smoke exhaust system – 22%
Low-current systems – 24%
Wall plastering – 68% 
Installation of screed -75% 
Finishing of GUPs – 12%
Installation and adjustment of elevators – 85%
Façade works – 87 %
Façade heat insulation - 92%
Façade finishing – 87%
Roofing – 72%.
Entrance group – 52%

RC “Ozernyi Hai Gatne” 

Building No.2
Internal decoration -99%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration - 96%.

Building No. 5
Internal decoration - 90%.
Glazing – 99%
Façade – 99%

Building No.6
Monolith works: 
Section 1: 5th floor – 80%
Section 2: 6th floor - 10%
Section 3: 6th floor – 40%

Building No.9
Excavation works for the bedding – 95%

RC “Traditsiya” 

Building No.2
Active finishing works inside apartments are ongoing. 

Building No.4
Vertical structure element of the 11th floor, slab over the 10th floor are in progress. Brickworks – 4th floor and basement.

RC “Malakhit”

Building No.4
Section 401 – Brickworks on 18-24 floors.
Sections 402- 403 – facade works – 95%
Section 403 - finishing works - 2-8 floors 
405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-13 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 95%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 40%.
Works on development of the territory of building No.4

Building No.5
Foundation works have been commenced - grillage 

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases in all sections is in progress.
Finishing works at GUP: section Ж – 1st floor, section Г – 9th floor and section Д – 1st floor. 
Water proofing of entrance groups is in progress.
Façade works are about to be completed. Works on development of adjoining territory are ongoing.

Building No.4
Plastering works at GUPs: B – on the 16th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing. 
Adjusting of elevators is in progress.
Finishing works and tiling at GUP: section Б – on the 16th floor, section В – on the 15th floor.

Building No.5
Brickworks on the floors 8, 9, 10, 11 and 12 of section A; section Е - on the 9, 11, 12 floors and basement. Section Б - on the 7, 8, 9 and 10 floors and basement. 
Back filling of the pit is in progress.
Installation of windows: 2nd to 5th floor at sections A, Б and E.   


Building No.6
Installation of vertical elements of the 13th floor at section Г
Installation of vertical elements of the 13th floor at section E.
Installation of the slab over the 12th floor at section Д*
Brickworks on the 3, 4, 5, 6, 7  floors in section Г; on 5, 6, 7, 8 floors in section Е and on 4, 5, 6, 7, 8 floors in section Д *.

Building No.7
Excavating works for the pit at sections Е1, Е2 and В.


Building No.8
Works on installation of vertical elements of the basement section Г*.
Works on installation of vertical elements of the basement section Б*.
Works on installation of vertical elements of the basement at section B is in progress.

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments 
(9 - 13 floors).

Building No.3 
Roofing works are ongoing
Installation of metal and plastic windows - 95%.
Façades works are in progress – 95% 
Wall plastering on 4, 13, 14 floors (apartments) and on the 1st floor is ongoing.
Works on electric wiring and plumbing are in progress.
Works on laying ceramic tiles at GUPs (14, 15, 16 and 17 floors) and basement (technical premises).
Territory development works are in progress.
Painting works at GUPs and staircases (3-12 floors).
Installation of entrance doors at apartments and technical premises.

Building No.4 
Installation of metal and plastic windows – 95%
Façades works are in progress – 90%
Works on electric wiring and plumbing are in progress. 
Installation of cement and sand screed on the 1st, 11th floors is in progress.
Roofing is in progress.
Wall plastering on the 13th and 14th floors (turnkey apartments) and on the 9th floor (GUP).
Painting works on the 4th and 6th floors are in progress.
Tiling on the 2nd and 3d floors (GUP)
Installation of doors at technical premises 


Building No.5 
Brickworks on the 15th floor, basement and roof are in progress.
Works on installation of metal and plastic windows are ongoing – 85%.
Façade works are ongoing 
Works on installation of external mains are ongoing.  

RC “Teremky” 

1st stage - Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are ongoing. Painting of the façade is ongoing. Internal mains and plumbing works are in progress. 
Wall plastering of GUPs on the 1st floor. 
Pouring of screed on the 1st floor. 
Installation of basket holders for air conditioner units.
Installation of entrance doors in apartments on23, 24 and 19 floors.
Stage 2, section 2 – Water-proofing of the basement is ongoing. Roofing works are in progress. Plastering works inside the apartments on the 11 floor is in progress. Electric wiring works on the 13th floor are in progress.
Stage 2, section 3 – Electric wiring works on the 3d floor are in progress.
Installation of windows on 19 to 21st floor is in progress. Heat insulation of the building is ongoing. Wall plastering works inside apartments on the 11th floor. Electric wiring works on the 13th floor are in progress.
Stage 3, section 4 – installation of the slab over the vertical elements of the 21st floor. Brickworks on the floors from the 5th to 10th inclusive are ongoing. 
Stage 3, section 5 – slab over the vertical elements of the 20th floor is in progress. Brickworks on 1, 2, 3, 9, 10 floors inclusive are in progress.
Stage 3, section 6 - Brickworks on 2nd to 8th floor are in progress.