Dynamics of construction as of 10.05.19

  • 10/05/2019

Dear customers, we offer you the dynamics of construction as of 05.10.19

RC "Academ-Quarter"

House number 1
Vertical element of the 25th floor.
Masonry - 14th floor.
Glazing - 5th floor.
House 2
Vertical element of the 25th floor.
Masonry - 10th floor.
Glazing - 3rd floor.

RC "Vladimirsky"
Hydro thermal insulation device in the passage area - 30%
Masonry - 3rd floor and basement.
Electrical work - 11% (floor 5-18).
Ventilation and smoke removal - 12% (111 floor).
Plumbing works - 33% (1-24 floor).
The device finishing works MOP - 47% (putty ceilings 6-10, 12-14 floor).
Door construction device - 45% (floor 4-24)
Installation of elevator equipment - 70% (1-24 floor).
Roof structure - 50% (steam and hydro barriers are arranged, an extruder is built, claydite concrete slope-forming screed, fine-grained concrete screed, mineral wool along the perimeter. Work has begun on covering the ventilation mine.)
The device window designs - 5-16 floor.
Installation of facades - 26% (in the metal balcony blocks, vapor barrier is performed).

RC "Malachite"
 
House number 4
Finishing works - 1-25 floor (finishing).
Facade work - 95%
Improvement - promenade area - 50% (waterproofing of parking lots).

House number 5
Vertical element of the 16th floor.
Masonry - 1-9 floor.
Active work is underway on the laying of utilities.

RC "Nyvky-Park"
 
House number 5
The laying is carried out: section B –15 floor.
Work is underway on waterproofing basements sections A, B and E.
Work is underway on backfilling the excavation.
The installation of windows is in progress: in sections A and E - 1st floor, in sections B and E - 16-17 floor.
Work is underway on laying the cable of the fire safety system: Section E - 4th-17th floor, Section B - 3-15th floor, Section A - 8-17th floor.
Finishing works are carried out in sections A, E, B– basement, 5-12, 17th floor.
Work is underway on the construction of the roof on section A, B and E.
Work is underway on the device facade.
Work is underway to connect the engineering networks.
Work is underway on the construction of the pit under the TE.
Conducted monolithic work on the device input groups.
Work is underway on the installation of elevators.

House number 6
The laying of the 7th, 11th, 14th, 16th floor on the section G; 10, 12, 13, 15, 16 floor and roof on section E, 10, 11, 13, 14 floor and basement on section D.
Work is underway on waterproofing basements.
Work is underway on backfilling the excavation.
Work is underway on the installation of windows: 7-9 floor sections G, E, D.
Finishing works are being carried out on the 3rd-8th floor of Section D, E and E.
Work is underway on the device screed: Section B - 8-11 floor.
Work is underway to connect utilities.

House number 7
Work is underway to arrange the vertical elements of the 7th floor of section E2.
Work is underway to arrange the vertical elements of the 6th floor of the E1 section.
Work is underway to arrange the vertical elements of the 6th floor in section B.
The device of a waterproofing of cellars on the sections B, E1, E2.
Backfilling of the sinuses of the pit.

House number 8
Work is underway on the construction of the floor slab of the 11th floor in section G.
Work is underway to arrange the vertical elements of the 11th floor in section B.
Work is underway on the construction of the floor slab of the 10th floor in section B.
The device of waterproofing basements on sections G, B, B.
Backfilling of the sinuses of the pit.
Laying of walls and partitions on section B: 1st and 3rd floor; on section B: 3rd floor.

RC "Lake Guy Hatne"
 
House number 5
Interior finish - 98%
Entrance groups - 98.5%
Facade - 99.9%
House territory - 70%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 99%
2nd floor - internal 99%
3rd floor - internal 99%
4th floor - internal - 99%
5th floor - internal - 99%
6 floor - internal - 99%
7th floor - internal - 99%
8th floor - internal - 99%
9th floor - internal - 99%
Installation of window units:
1 section - 7 floors - 90%
2 section - 7 floors - 90%
Section 3 - 9 floors - 90%
Plaster walls:
1, 2, 3 section - 25%
Floor screed:
1, 2 section - 10%
3 section - 2%
Facade work:
1 section - 50%
Roof - 70%
Water supply - 40%

House 8
1st floor - 50%

House number 9
basement:
1, 2 section - 50%
3rd floor:
1, 2 section - 50%
4th floor:
1, 2 section - 2%
Masonry:
3.4 section
1st floor: external - 70%; internal - 50%
2nd floor: external - 90%; internal - 50%
5.6 section
1st floor: external - 90%; internal - 90%
2nd floor: external - 90%; internal - 50%

House 43
Crushed cushion - 50%
Concrete preparation - 50%
Base plate - 50%

RC "Otradny"
 
House number 3
Electrical installation and plumbing works - 98%
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).
House number 4
Electrical installation and plumbing works - 98%
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).
House number 5
Installation of metal windows - 95%
Installation of equipment for passenger and freight elevators - 98%
Work on the device ventilation - 95%
Facade works - 95%
Cement-sand screed works - 98%
Work is underway to finish the MOS and the gathering cell.
Work is underway on the device of the roll roof.
Started work on the device decorative plaster on the cage.
Works on the device tiles in MOP - 95%
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments, painting of ceilings).
The device retaining wall around the perimeter

RC "Park Lakes"
 
House number 13
Plumbing works - 99%
Electrical work - 94%
Ventilation and smoke removal - 86%
Installation of elevators and commissioning - 97%

RC "Berth 8"

Section 1
The device of the monolithic frame (vertical element of the 11th floor) - 41%
The device walls and partitions - 1st floor.
Section 2
The device of the monolithic frame (floor slab above the 12th floor) - 44%
The device walls and partitions - 1st floor.
 
Residential complex "Syretsky Gardens"
 
House number 1
In the work of interior decoration - paint brushes.
Windows - 90%

House 2
Windows - 14, 16th floor.
Plaster, screeds - section 3, 2, 1 - 15%
Warming of the facade - 25%

The House 3
Masonry - 95%

House 4
Windows - 2-22 floor.
Facade insulation - 20%
Roof installation - 15%
Masonry - 95%

House 5
Vertical element of the 14th floor.
Masonry - 5th floor.

Residential complex "Teremki"

1st turn
Internal engineering and plumbing works are being carried out.
Connection of communications to the house is made.
Began to landscaping around the first house.
Repair work in progress:
- Laminate: 18th, 19th, 23rd, 24th floor.
- installation of interior doors: 4, 9, 11, 18
2 turn, 2 section
Roofing work is underway.
The plastering of the walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors is carried out.
Filling of a coupler of a floor from 2 to the 25th floor.
Work on the insulation of the house.
Painting of MOP ceilings from 4th to 15th floor.
Installation of elevators.
2 stage, 3 section
Roofing work is underway.
Plaster walls in apartments on the 3rd and 4th floor, 9 and 11, 13, 14, 18, 19, 23 and 24 floors.
Work on the insulation of the house.
Installation of elevators.
3rd stage, 4th section
Windows - 15, 16, 17th floor.
Plaster walls in the apartments - 2-12 floor.
3 stage, 5 section
Windows - 15, 16, 17th floor.
Plaster walls in the apartments - 2-12 floor.
3rd stage, 6th section
Performed reclaiming the roof of the house.
Windows - 15, 16, 17th floor.
Plaster walls in the apartments - 2-12 floor.
 
Residential complex "Tradition"
 
House number 4
Vertical element of the 25th floor, floor slab of the 25th floor.
Masonry - 15, 16, 18, 19, 21 floor and basement.
External networks - 60%
Plaster - 9, 10, 12 floor.
Electricity - 8-10 floor.
Sewerage (risers) - 50%
Paint brushes - 2-3 floor.
Couplers - 3-5 floor.

RC "Yaskravy"
 
House number 6
Installation of window designs - 95%
Plumbing works - 93%
Electrical work - 70%
Ventilation and smoke removal - 75%
Low-voltage systems - 47.7%
Plaster walls (apartments) - 98.7%
Screed device - 99%
Finishing MOS - 98%
Installation of elevators and commissioning - 90%
Facade arrangement - 98%
Roof installation - 97%
Entrance group - 95%
Improvement - 36.7%