PROGRESS OF CONSTRUCTION AS OF 14.12.18

  • 14/12/2018

 

RC "Volodymyrskyi"

 

Brickworks for vent ducts at the HEU, on the 14, 16 and 17 floors.

Installation of lighting protection system is carried out solely in monolith structures.

Elevator equipment has been delivered.

Installation of still fencing of staircases – 6th floor.

Waterproofing  and heat insulation in the zone of traffic -80%


RC “Syretski Sady” 

Building No. 1
Internal decoration works are in progress – screeds and plastering


Building No. 2 
Windows – 2-8 floors (section 2,3)

 

Building No. 3 
Brickworks – 1st to 10th floor


Building No.4
Brickworks – 1st to 20th floor.

Windows – 2nd to 9th floor.

Building No.5
Testing of pile field is completed. Foundation is completed.

 

RC “Yaskravyi”
 

Building No.6 
Works on installation of walls, partitions, brickworks (external -92.5%, internal – 97.4%) are in progress. 
Installation of window structures-76%
Plumbing works –47.3 %

Electric wiring works – 24.2%

Ventilation and smoke exhaust system – 5.6%

Low-current systems – 11.5 %
Wall plastering – 35.1%
Installation of screed – 48.5%

Decoration of GUPs – 17.2%
Installation and adjustment of elevators– 70%
Façade works – 90.5%

Roofing – 88.3%
Entrance group – 65.7%

Development of the territory – 0.7%
 

Building No. 7 
Plumbing works – 98%
Electric wiring works – 95%
Ventilation and smoke exhaust system – 94%
Low-current systems – 97%
Finishing of GUPs – 99%
Installation and adjustment of elevators – 94%
Development of adjoining territory – 90%

 

RC “Parkovi Ozera” 

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96%

Plumbing works – 63%
Electric wiring works – 48%
Ventilation and smoke exhaust system – 26%
Low-current systems – 41%
Wall plastering –93% 
Installation of screed -80%

Finishing works at GUPs – 52%

Installation and adjustment of elevators – 90%
Façade works – 97%
Façade heat insulation - 97%
Façade finishing – 96%
Roofing – 94%.
Entrance group – 77%

 

RC “Ozernyi Hai Gatne” 
 

Building No.2
Internal decoration -99%
Development of adjoining territory -99%

Building
No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration – 99.9%.

Building No. 5
Internal decoration – 99.3%.
Façade – 99.9%

Building No.6
Monolith works : 

Section 1: parapet – 70%

Section 2: parapet - 80%

Section 3: 9th floor – 60%

 

Building No.9
Gravel bedding – 81%

Concrete bedding - 60%

Water proofing -30%

 

 

RC “Traditsiya” 

Building No.2
Active finishing works inside apartments are ongoing.


Building No.4
Vertical element of the 13th floor, slab over the 12th floor are in progress.

Brickworks – 7h floor and basement.
 

RC “Malakhit”

Building No.4
Section 401 – Brickworks on 24-25 floors. Works on the roof are in progress. Façade works – 25%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 40%.

Works on development of the territory of building No.4 – 85%

Building No.
5
Pouring of the slab over the basement is in progress.

 

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases in all sections is in progress.
Finishing works at GUP: section
Ж – 1st floor.

Façade works are about to be completed. Works on development of adjoining territory are ongoing.

Works on arrangement of heat supply system are in progress.

 

Building No.4
Works on adjustment of elevators are ongoing.

Installation of drywalls and paint works in the halls of the first floors at section Е, Б, В are in progress.

Building No.5
Brickworks on the floors 8
, 11, 12  of section A; section Е - on the 9, 10, 11, 12 floors and basement of the Section  E; on the 7, 8, 10, 11 floors and basement of section Б .

Brickworks for ventilation shafts on the roof at sections A and E are in progress.

Water proofing of basements at sections А, Б and Е is in progress.

Back filling of the pit is in progress.

Installation of windows: on the 5th to 6th floor at sections A, Б and E.  

Building No.6
Installation of slab over the 16th floor at section Г
Installation of slab over the 16th floor at section E.
Installation of vertical elements of the 16th floor at section Д*
Brickworks on the 4, 5, 7 floors in section Г; on
5, 7, 8 floors at section Е and on the 1st, 7th and 8th floors of section Д *.

Works on water proofing of basements are in progress.

Works on backfilling of the pit are ongoing.

Building No.7
Excavating works for the pit at section E2 are ongoing.

Installation of vertical elements of the basement at section E1 is in progress.

Installation of vertical elements of the basement at section B is in progress.

Works on reinforcement of the basement for tower crane are in progress.

 

Building No.8
Works on installation of the slab over the 1st floor at section Г*

Works on installation of vertical elements of the 1st floor  at section Б**.

Works on installation of vertical elements of the 1st floor at section B are in progress.

 

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments (1,
9, 12 floors).

Building No.3 

Roofing works are ongoing.

Installation of metal and plastic windows - 98%.
Façades works are in progress  – 98%.

Works on electric wiring and plumbing are in progress (basement, IHU, pumping station).
Decoration works on the 1st floor are ongoing.

Territory development works are in progress.

Painting works at GUPs and staircases (2-5 floors).
Installation of decorative plaster on the 3,4 floors and staircase of the 1-12 floors are in progress.

 

 

Building No.4 
Installation of metal and plastic windows – 98%
Façades works are in progress – 95%

Works on electric wiring and plumbing are in progress.

Installation of cement and sand screed on 3, 4, 9 floors (baths).

Wall plastering on 3, 4, 9 floors (baths)

Roofing works are in progress.

Wall plastering on the 13th floor (turn-key apartments - baths) as well as at GUPs on the 1st floor is in progress.

Painting works at GUPs and staircases from 3d to 6th floors.

Installation of entrance doors to apartments and technical premises is in progress.

Development of the territory is ongoing.

 

 

 

 

Building No.5 
Works on installation of metal and plastic windows are ongoing – 95%.

Works on arrangement of cement and sand screed on the 3d floor are ongoing.

 

RC “Teremky” 

1st stage

Works on heat insulation of the building are in progress 90%

Painting façade works are ongoing -90%

. Works on installation of internal mains and plumbing works are in progress.

Installation of basket holders for air conditioner units – 85%. Connection of communication networks to the building.

 

Stage 2, section 2

Roofing works are in progress -80%

Plastering works inside the apartments on 14, 18 floors

Works on heat insulation of the building are in progress - 20%

 

Stage 2, section 3

Roofing works are in progress – 80%.

 Wall plastering works inside apartments on the 14th and 18th floors. Pouring of screed on the 6th floor.

 

Stage 3, section 4

Slab over the vertical elements of the 24th floor is installed.

Brickworks – 1st to 12th floor.

 

Stage 3, section 5

slab over the vertical elements of the 23nd floor

 Brickworks on 1st to 10th floors are in progress.


Stage 3, section 6 

Slab over the vertical elements of the 22nd floor is installed.

Brickworks on 2nd t to 10th floor.

 

RC «Academ-Kvartal»

Building No.1

Vertical element of the 14th floor.

Brickworks 2nd and 3d floors and basement.
 

Building No.2

Vertical element of the 15th floor, slab over the 14th floor.

Brickworks - 2nd and 3d floors and basement.