Dynamics of construction as of 15.02.19

  • 15/02/2019

RC «Volodymyrsky»

Waterproofing - 5-10 floor, base.
Laying - TP, 17, 19, 24, 25 floor.
The arrangement of internal power supply networks is 5-9 floors.
Installation of internal heating and ventilation networks - 1-10 floors.
The arrangement of internal networks of water supply and sewage - 1-10 floor.
Installation of finishing works of IGC - 12.5%
The arrangement of door structures and hatches is 4-24 floors
Roofing - 16%
The arrangement of window constructions is 5-16 floors.
The arrangement of metal fence staircases - 6 floors.
Arrangement of external engineering networks - 24%

RC «Syretsky gardens»

House 1
Inside, the interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.

House 3
Masonry - 13-16 floors.

House 4
Windows - 2-22 floors.

House 5
Vertical element of the 4th floor.

RC «Bright»

House number 6
Works on the arrangement of walls and partitions, masonry (external contour - 96%)
Installation of window constructions - 79,4%
Plumbing works - 65,9%
Electrical works - 28,9%
Ventilation and smoke removal - 15.7%
Weak systems - 23,5%
Plaster of walls - 53,5%
Screw arrangement - 75,4%
Finishing of IGC - 36%
Installation of elevators and start-up and adjustment works - 75%
Facade arrangement - 95%
Roof installation - 92.3%
Incoming group - 85%
Amenties - 0.7%

RC Park Lakes

House No. 13
Installation of window constructions - 98%
Sanitary work - 86%
Electrical work - 74%
Ventilation and smoke removal - 57%
Weak-current systems - 44%
Finishing of IGC - 99%
Installation of elevators and start-up and adjustment works - 90%

RC «Ozerny Gai Gatne»

House No. 5
Interior decoration - 95,6%
Facade - 99.9%

House number 6
Masonry of external and internal walls:
1st floor - internal - 95%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%
7th floor - external - 2%

House No. 9
Foundation foundation: 1, 2 sections - 50%
Monolithic works:
3, section 4 - 70%
5, section 6 - 5

RC «Tradition»

House number 2

The clean finishing of apartments is being actively pursued.

House number 4

Vertical element of the 18th floor, floor slab 17th floor.

Masonry - 8-13 floor and basement.

External Networks - 25%

RC «Malakhit»

House number 4
Finishing works - 1-21 floor (finishing).
Facade works - 25%
Improvement - promenade area - 40%

House number 5
Plate floor 4 floors.

RC «Nyvky-Park»

House number 3
Work is under way to start the heat supply.
The transfer of apartments to investors is in progress.

House number 4
Lifts are being adjusted.
Work is ongoing on the finishing of apartments with renovations.
Finished works on the facade arrangement.
Work is underway on installation of window drafts and baskets for air conditioners.

House number 5
The laying is carried out: in the basement, on 13, 14, 15, 16, 17 floors of Section A; on 9, 11, 14, 15 floors of section E and basement; on the 8th floor of section B.
Work is being done on the laying of Vent. shafts on roof sections B and E.
Works on waterproofing of basements of sections A, B and E are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are underway: 8-10 floors in sections A, B and E.
The work on laying the fire safety system cable is underway: Section A - 9-13 floor, section E - 2-5 floor.

House number 6
Arrangement of parapets on section G.
Arrangement of parapets in Section E.
Arrangement of parapets in section D *.
Masonry is carried out: on 4, 5, 7, 8 floor and basement on section Г; on the 5th, 7th, 8th floor of Section E; on the 1st, 7th, 8th floor of section D *.
Works on waterproofing basements are underway.
Work is underway on the backfill of the foundation pit.
Works are underway on the installation of windows: 5-7 floors in sections G, E, D *.

House number 7
Work is underway on arrangement of vertical elements of the 1st floor in section Е2.
Work is carried out on the arrangement of vertical elements of the 1st floor in section E1.
Works on the arrangement of the slab ceiling of the cellar under section B.

House number 8
Work is underway to install a slab of floor 5 floors in section G *.
Work is underway on the arrangement of vertical elements of the 5th floor in section B *.
Work is underway on the arrangement of the ceiling slab of the 4th floor in section B.


RC «Otradny»

House number 3
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 98%
Work is underway on installation of electrical and plumbing works - a socle, an ITP, an electrical and mechanical department, installation of fixtures, installation of input automata in apartments.
There are finishing works: 4, 5, 8, 9, 13, 14 floor (apartments with repair).

House number 4
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 95%
Work is underway on installation of electrical and plumbing works - (a socle, an ITP, an electrical and mechanical department, the installation of fixtures, the installation of input automata in apartments).
There are finishing works: 4, 5, 8, 9, 13, 14 floor (apartments with repair).

House number 5
Installation of metal-plastic windows - 95%
Works are underway on plaster laying on the 5th floor (apartments with repair).
Installation of equipment for passenger and freight elevators.
Work is underway to insulate the ground floor.
Works are being carried out on laying of ventilation shafts from brick on a roof.
Works on installation of doors on the technical floor.
Installation of a cement-sand joint: 11, 12th floor.

RC «Akadem-Kvartal»

House 1
Vertical elements of the 19th floor, floor slab floor.
Laying - 7th floor.

House 2
Slab floor 19th floor.
Laying - 3rd floor.

RC «Teremki»

1 queue
Work is being done on painting the facade.
Internal engineering and plumbing work are carried out.
Installing baskets for air conditioners is underway.
Connected to home communication.
Repair works on floors 4, 9, 11, 13 and 14 are underway.
2nd line, 2nd section
Roofing works are being performed.
Execution of plaster walls on the 23rd floor.
Work is carried out on insulation of the house.
Installation of elevators is underway.
2nd stage, 3rd section
Roofing works are being performed.
Execution of plaster walls in apartments on the 23rd floor.
Installation of elevators is underway.
3rd stage, 4th section
Masonry is executed from 1 to 20 floors.
3rd turn, 5th section
Masonry is executed from 1 to 20 floors.
3rd turn, 6th section
Overlapping roof of the house is being performed.
Mortar from 15th to 18th floor is underway.