Dynamics of construction as of 11/15/17

  • 15/11/2017

Dynamics of construction as of 11/15/17

"Vladimirsky" RC

Works on the device of the monolithic reinforced concrete frame at the mark of +14,300 (4th floor).

Waterproofing device - 0.5%.

The device masonry - 25%.

Residential complex "Syretsky Gardens"

House number 1

Section 1: completed on the 6th floor concreting of the floor slab. Section 2: completed on the 4th floor concreting the foundation slab.

House number 2

Concreting of the foundation slab completed.

House number 3

Cleared the area.

House number 4

Completed installation of test piles - 56%.

"Yaskravy" RC

House number 6:

In section number 1.
 
Completed construction of the 14th floor.
 
Readiness of the vertical of the 15th floor - 30%.
 
Basement waterproofing - 80%.
 
Basement insulation - 80%.
 
In section number 2.
 
Completed construction of the 12th floor.
 
The construction of the vertical of the 13th floor has begun - 30%.
 
Basement waterproofing - 80%.
 
Basement insulation - 80%.
 
In section number 3.
 
Completed overlap of the 11th floor - 100%.
 
Basement waterproofing - 80%.
 
Basement insulation - 80%.
 
House number 7:
 
The device of the monolithic frame section number 1 - 98%.
 
The device of the monolithic frame section number 2 - 100%.
 
Performed brickwork on the roof - 30%.
 
The device of ventilation ducts in sections No. 1 and No. 2 is carried out:
 
Ventilation and dimovidalenya- 20%.
 
Plumbing works - 27%.
 
Electrical work - 20%.
 
Low-voltage systems - 12%.
 
Plaster walls in sections number 1 and number 2 - 7%.
 
The establishment of screeds in sections 1 and 2 is 14%.
 
Installation of window structures: section number 1 - 44% (floors 2-16), section number 2 - 24% (floors 2-8).
 
"Lake Guy Hatne" RC
 
House number 2:
 
Foundation device - 100%.
 
Basement walls waterproofing - 100%.
 
The device walls - 100% (masonry attic floor).
 
The device of monolithic floor slabs - 100%.
 
The device partitions - 100%.
 
Roof - 78%.
 
Facade - 71%.
 
Interior finish - 80%.
 
Improvement of the local area - 33%.
 
House number 3:
 
Foundation device - 100%.
 
Basement walls waterproofing - 100%.
 
The device walls - 100%.
 
The device of monolithic floor slabs - 100%.
 
The device partitions - 100%.
 
Roof - 75%.
 
Facade - 78%.
 
Improvement of the local area - 31%.
 
House number 4:
 
Completed foundation foundations - 100%.
 
The basement is 100% waterproofed.
 
The device walls - 98% (masonry attic floor).
 
The device of monolithic floor slabs - 100%
 
The device partitions - 100%.
 
Roof - 5%.
 
Facade - 41%.
 
Interior decoration - 50%.
 
Improvement of the local area - 6%

House number 5:
 
Foundation device - 100%.
 
Basement waterproofing device for 100%.
 
Ceiling installation - 65% (6th floor).
 
The device of monolithic floor slabs - 65%.
 
The device partitions - 66%.
 
"Demeevka" RC
 
House number 2:
 
Completed frame.
 
Construction of parapets and reinforced concrete structures of machine rooms was completed on the roof.
 
Completed installation of ventilation units.
 
Completed staircases mounting.
 
Completed laying.
 
The laying continues on floors 17-20.
 
Installation of risers for water supply, heating and domestic sewage continues - 68%.
 
Readiness of monolithic structures of input groups - 99%.
 
Completion of installation of windows to the 9th floor.
 
The windows of the 10th-15th floors are being installed.
 
Dilution of horizontal heating and water supply grounds: 13th floor.
 
Electricity installation works 13th floor.
 
"Park Lakes" RC
 
House number 11:
 
The device of external walls and partitions (masonry) - 100%.
 
The device of internal walls and partitions - 100%.
 
Roof installation - 100%.
 
Installation of window designs - 100%.
 
The device facades - 100%.
 
Plaster walls - 100%.
 
Plumbing work - 85%.
 
Floor screed - 100%.
 
Installation of the internal power supply system - 95%.
 
Low-voltage systems - the installation of meters is completed (96%).
 
Ventilation and smoke removal - 97%.
 
Installation of elevators - 93%.
 
House number 12:
 
The device is a monolithic frame on the roof, parapets and covers (98%).
 
The device walls and partitions on the 17-26th floor (70%).
 
The device of the ventilation ducts is 74% complete.
 
Installation of window designs was carried out on the 12-17th floor (48%).
 
Plumbing works - vertical up to 25 floors (41%).
 
Electrical work performed breeding on the 12th floor (33%).
 
Low-voltage systems - performed on the 2nd floor (19%).
 
Plaster walls - performed on the 9-10th floor (33%).
 
Decorating common areas - completed on the 2nd floor (4%).
 
House number 13
 
The monolithic frame device is made on the 20-22nd floor (74%).
 
Started equipping walls and partitions on floors 2-4 (7%).
 
The device of the ventilation ducts is installed on the 19-21st floor (59%).
 
Residential complex "Tradition"
 
House number 2:
 
The device slabs 27 floors.
 
The brickwork is on floors 18-21.
 
Installation of window designs - 4-5th floor
 
House number 3:
 
Facade work - 80%.
 
Plumbing works - from the 1st to the 25th floor.
 
The installation of heat meters of the 1st and 2nd zones is completed.
 
Wiring availability - 85%.
 
Improvement of the local area - 50-60%.
 
External networks - 90%.
 
Roof - 80%.
 
Interior decoration of apartments - 70%.
 
Installation of elevator equipment - 50%.
 
"Malachite" RC
 
House number 3:
 
In the sections 302-303, internal finishing works were carried out from the 2nd to the 9th floor - 100%.
 
We started to improve the recreation area on the roof - 50-60%.
 
Work is underway on the installation of external engineering networks:
 
- domestic sewage K1 - 99%.
 
- Rainwater drain K2 - 99%.
 
- water supply system В1 - 90%.
 
- electrical networks - 90%.
 
House number 4:
 
Monolithic frame section 404 - 100%.
 
Work on the brickwork on the first and sixth floor section 404 - 100%.
 
Work is underway on the construction of vertical reinforced concrete structures in section 405-406, Spec.-0.100.
 
Parking P1 - overlapping with monolithic slabs 100%.
 
Parking P2 - overlapping with monolithic slabs 100%.
 
Section 401 foundation - 100%, mark - 3,100.
 
Section 402-403 - concreting of reinforced concrete foundation - 1st floor.
 
"Nyvky Park" RC
 
House number 1:
 
The device is a monolithic frame - 100%.
 
The device walls and partitions - 100%.
 
Installation of window designs - 100%.
 
Installation of internal engineering at the final stage.
 
Section A - screed and plaster - 100%.
 
Section B - screed and plaster - 100%.
 
Section B - screed and plaster - 100%.
 
Work continues on interior decoration - decorative plaster, renovation of apartments.
 
The device facade is made by 90%.
 
Work is underway on the installation of elevators.
 
Work is underway on trim the input groups.
 
Work is underway on the design of external engineering networks.
 
Work is underway to improve the courtyard of the House 1.2.
 
House number 2:
 
The device is a monolithic frame - 100%.
 
The device walls and partitions - 100%.
 
Installation of window designs - 100%.
 
Installation of internal engineering at the final stage.
 
Section G - screed and plaster - 100%;
 
Section D - floor screed - 100%, plaster on the 12th, 13th, 14th floor in work;
 
Work continues on interior decoration - decorative plaster, renovation of apartments.
 
Work is underway on the device lifts.
 
The facade was completed at 65%.
 
Work is underway on the design of external engineering networks.
 
House number 3:
 
In sections G, D, W, work is underway to build a monolithic frame on the 16th floor.
 
The laying of the walls continues: work is being carried out on floors 8-10 of sections G, D, J.
 
House number 4:
 
In sections E, B, C, a monolithic frame of the 12th floor is maintained.
 
The laying of the walls continues: works are being carried out on floors 4-6 of sections E, B, C.
 
"Otradny" RC
 
House number 1:
 
The monolithic frame device is 100% complete.
 
The brickwork of the exterior walls is 100% complete.
 
Works on painting the facade - 95%.
 
Plastering work performed at 100%.
 
The coupler is made to 100%.
 
Finishing work is underway at the MZK (American, roach).
 
Work is underway on the roofing - 70%.
 
Work is underway on the improvement device - 35%.
 
House number 2:
 
The monolithic frame device is 100% complete.
 
Work is underway on the installation of brickwork on the roof.
 
Work is underway on the roofing - 70%.
 
Plastering works are underway on the 5th floor.
 
Electrical and plumbing works are underway on the 7th floor.
 
House number 3:
 
Reinforcement and concreting performed up to the 17th floor.
 
Brickwork is performed on the 10th, 11th, 12th floor.
 
House number 4:
 
Work is underway on the reinforcement of the 9th floor slab.
 
Brickwork is performed on the 2nd, 3rd, 4th floor.
 
House number 5:
 
Work is underway to reinforce the vertical of the 2nd floor.
 
"Teremki" RC
 
1st stage - the arrangement of elements of horizontal overlap of the 22nd floor is carried out, on the 23rd floor - the arrangement of vertical monolithic-frame structures is carried out.
 
The brickwork is 100% completed on the 14th floor, inclusive. From the 15th to the 17th floor - masonry work is underway.
 
On the ground floor is arranged waterproofing.
 
2nd stage 2nd section - vertical overlapping elements of the 2nd floor are being made.
 
2nd stage 3rd section - horizontal overlapping of the 1st floor is performed.
 
3rd phase 4th section - arrangement of the foundation for a tower crane. Completed work on the development of the pit.