Progress of construction as of 16.11.18

  • 16/11/2018

RC "Volodymyrskyi"

Pouring of vertical structures over the 24th floor is completed.
Reinforcement of the vertical structures of the 25th floor.
Brickworks on the basement, 2-4, 9-16 floors 
Works on concealed wiring on typical residential floors inside monolith structures are in progress. 
Installation of internal heating network and ventilation, internal water supply network and sewage, low-current networks, smart-home system, screed, wall plaster, decoration of GUPs – 5th floor.


RC “Syretski Sady” 

Building No. 1
Completion of installation of windows and balconies – 99%.
Plumbing works –1-16  floors. 
Façade – heat insulation of walls – 80%. 
Entrance groups – basements are completed

Building No. 2 
Brickworks – 1st to 14th floor.
Roofing works are in progress – sections 2 - 1st layer.
Windows – 1-2 floors (section 3)

Building No. 3 
Brickworks – 1st to 3d floor 

Building No.4
Brickworks – 1st to 16th floor.
Windows – 2nd to 8th floor.

Building No.5
Testing of pile field is completed. Foundation is completed.


RC “Yaskravyi”

Building No.6 
Works on installation of walls, partitions, brickworks (external -92.5%, internal – 97.4%) are in progress. 
Installation of window structures-76%
Plumbing works –41.9%
Electric wiring works – 18%
Ventilation and smoke exhaust system – 5.6%
Low-current systems – 8.9%
Wall plastering – 22%
Installation of screed – 32.1%
Decoration of GUPs – 8.7%
Installation and adjustment of elevators– 70%
Façade works – 67.5%
Roofing – 88.3%
Entrance group – 40%

Building No. 7 
Plumbing works – 96%
Electric wiring works – 88%
Ventilation and smoke exhaust system – 92%
Low-current systems – 94%
Finishing of GUPs – 98%
Installation and adjustment of elevators – 89%
Development of adjoining territory – 85%

RC “Parkovi Ozera” 

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96% 
Plumbing works – 52%
Electric wiring works – 41%
Ventilation and smoke exhaust system – 26%
Low-current systems – 24%
Wall plastering – 78% 
Installation of screed -75% 
Finishing works at GUPs – 34%
Installation and adjustment of elevators – 90%
Façade works – 93 %
Façade heat insulation - 97%
Façade finishing – 96%
Roofing – 94%.
Entrance group – 77%

RC “Ozernyi Hai Gatne” 

Building No.2
Internal decoration -99%
Development of adjoining territory -99%

Building No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration - 97%.

Building No. 5
Internal decoration – 90.5%.
Glazing – 9.59%
Façade – 99.5%

Building No.6
Monolith works : 
Section 1: 6th floor – 50%
Section 2: 6th floor - 80%
Section 3: 7th floor – 10%

Building No.9
Excavation works for the bedding – 98%
Gravel bedding – 30%

RC “Traditsiya” 


Building No.2
Active finishing works inside apartments are ongoing. 

Building No.4
Vertical element of the 11th floor, slab over the 11th floor are in progress. Brickworks – 5th floor and basement.

RC “Malakhit”

Building No.4
Section 401 – Brickworks on 20-25 floors.
Sections 402- 403 – facade works – 95%
Section 403 - finishing works - 2-8 floors 
405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-13 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 95%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 40%.
Works on development of the territory of building No.4 – 40%

Building No.5
Active foundation works are in progress - grillage 

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases in all sections is in progress.
Finishing works at GUP: section Ж – 1st floor, section Г – 11th floor and section Д – 1st floor. 
Water proofing of entrance groups is in progress.
Façade works are about to be completed. 
Works on development of adjoining territory are ongoing.


Building No.4
Plastering works at GUPs: B – on the 16th floor.
Installation of external mains is in progress.
Water proofing of entrance groups is in progress 
Adjusting of elevators is in progress.
Finishing works and tiling at GUP: section Б – on the 16th floor, section В – on the 15th floor.

Building No.5
Brickworks on the floors 8 to 12 of section A; section Е - on the 9, 11, 12 floors and basement. Section Б - on the 7, 8, 9, 10, 11 floors and basement. 
Water proofing of basements at sections А, Б and Е is in progress
Back filling of the pit is in progress.
Installation of windows: 2nd to 5th floor at sections A, Б and E. 

Building No.6
Installation of the slab over the 13th floor at section Г
Installation of the slab over the 13th floor at section E.
Installation of vertical elements of the 13th floor at section Д*
Brickworks on the 3 to 7  floors in section Г; on 5, 7, 8 floors at section Е and on 7th and 8th floors of section Д *.

Building No.7
Excavating works for the pit at sections Е1, Е2 and В.

Building No.8
Works on installation of vertical elements of the basement section Г*.
Works on installation of vertical elements of the basement section Б*.
Works on installation of vertical elements of the basement at section B is in progress.

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments 
(11 - 16 floors).


Building No.3 
Roofing works are ongoing
Installation of metal and plastic windows - 95%.
Façades works are in progress  – 95% 
Wall plastering on 13, 14 floors (apartments) is ongoing.
Works on electric wiring and plumbing are in progress.
Works on laying ceramic tiles at GUPs (13, 14, floors, basement, HS, pump station and entrance group).
Territory development works are in progress.
Painting works at GUPs and staircases (3-16 floors).
Installation of entrance doors at apartments and technical premises.

Building No.4 
Installation of metal and plastic windows – 95%
Façades works are in progress – 90%
Works on electric wiring and plumbing are in progress. 
Installation of cement and sand screed on the 12th, 17th 18th floors is in progress.
Roofing is in progress.
Wall plastering on the 13th and 14th floors (turn-key apartments).
Painting works on 5, 7, 8, 9 floors are in progress.
Tiling on the 4th and 5th floors (GUP) and cold passes.
Installation of entrance doors at apartments.
Development of the territory. 

Building No.5 
Works on installation of metal and plastic windows are ongoing – 90%.
Façade works are ongoing. 
Works on installation of external mains are ongoing. 
Roofing is in progress 

RC “Teremky” 

1st stage – Works on heat insulation of the building are in progress. Painting façade works are ongoing. Works on installation of internal mains and plumbing works are in progress. Installation of basket holders for air conditioner units. Connection of communication networks to the building.
Stage 2, section 2 – Water-proofing of the basement is ongoing. Roofing works are in progress. Plastering works inside the apartments on the 11 floor is in progress. Electric wiring works on the 13th floor are in progress. Pouring of screed on the 2nd floor. Works on heat insulation of the building are in progress.

Stage 2, section 3 – Installation of windows on 19 to 25th floor is in progress. Heat insulation of the roof of the building is ongoing. Wall plastering works inside apartments on the 11th floor. Electric wiring works on the 13th floor are in progress. Pouring of screed on the 2nd floor.
Stage 3, section 4 – brickworks on the floors from the 5th to 11th are ongoing. 
Stage 3, section 5 – slab over the vertical elements of the 21th floor is in progress. Brickworks on 1 to 3, and 9 to 10 floors are in progress.
Stage 3, section 6 - slab over the vertical elements of the 20th floor is in progress. Brickworks on 2nd to 10th floor are in progress