PROGRESS OF CONSTRUCTION AS OF 18.01.19

  • 18/01/2019
Tags:

LCD "Vladimirsky"

Waterproofing device - 5-10 floor.
Masonry - TE, 17, 18, 19 floor.
The device of internal power supply networks - 5-9 floor.
The device of door structures and hatches - 4-24 floor
Roof installation - 16%
The installation of metal fencing staircases - 6 floors.
The device of external engineering networks - 18%

Residential complex "Syretsky Gardens"

House number 1
In the work of interior decoration - screed and plaster.

House 2
Windows - 12th floor.

The House 3
Masonry - 13-15 floor.

House 4
Masonry - 1-22 floor.
Windows - 2-14 floor.

House 5
Vertical element of the 1st floor.

LCD "Yaskravy"

House number 6
Works on the construction of walls and partitions, masonry (external contour - 96%)
Installation of window designs - 76%
Plumbing works - 54.2%
Electrical work - 27.4%
Ventilation and smoke removal - 8.3%
Low-voltage systems - 18.5%
Plaster walls - 43.3%
Screed device - 59.6%
Finishing MOS - 23.6%
Installation of elevators and commissioning - 71.7%
Facade arrangement - 95%
Roof installation - 92.3%
Entrance group - 82.3%
Improvement - 0,7%

LCD "Park Lakes"

House number 13
The device walls, partitions, masonry (internal) - 97%
Installation of window designs - 96%
Plumbing works - 84%
Electrical work - 67%
Ventilation and smoke removal - 46%
Low-voltage systems - 44%
Plaster walls - 93%
Screed device - 97%
Finishing MOS - 73%
Installation of elevators and commissioning - 90%
Facade arrangement - 96%
Thermal insulation of facades - 98%
Facade finishing - 96%
Roof installation - 97%
Entrance group - 81%
 

LCD "Lake Guy Hatne"

House number 5
Interior finish - 94%
Facade - 99.9%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 95%
2nd floor - internal - 97%
3rd floor - internal - 99%
4th floor - external - 90%; internal - 50%
5th floor - external - 40%

House number 9
Basement walls: 3, 4 section - 10%

Residential complex "Tradition"

House number 2
Active finishing is carried out apartments.
 
House number 4
Vertical element of the 15th floor, floor slab of the 15th floor.
Masonry - 8th floor and basement.
External networks - 5%


LCD "Malachite"

House number 4
Section 401 - masonry - on the roof.
Windows - 99%
Finishing works 1-19 floor.
Facade work - 25%
Improvement - promenade area - 40%

House number 5
Floor slab 1 floor.
 
LCD "Nyvky Park"
 
House number 3
Work is underway on commissioning of heat supply.
Transfer apartments to investors.

House number 4
Elevators are being adjusted.
Work is underway on the finishing of apartments with repairs.
Finishing work on the arrangement of the facade.
Work is underway on the installation of window sills and baskets for air conditioning.

House number 5
The laying is carried out: in the basement, on the 8th, 11th, 12th floors and the roof of section A; on the 9th, 11th floors and basement of section E; on the 8th, 11th floor of section B.
Work is underway on laying the vent. mines on the roof of sections B and E.
Work is underway on waterproofing the basements of sections A, B and E.
Work is underway on backfilling the excavation.
Works on installation of windows are in progress: floor 6-8 in sections A, B and E.

House number 6
Device parapets on section G.
The device of the floor slab of the 17th floor in section E.
The device of the floor slab of the 17th floor in section D *.
The laying 4, 5, 7 floor and a cellar on section G is carried out; 5, 7, 8 floor on section E; 1, 7, 8 floor on section D *.
Work is underway on waterproofing basements.
Work is underway on backfilling the excavation.
Works on installation of windows are in progress: floor 2-4 in sections G, E, D *

House number 7
Work is underway to set up vertical basement elements in section E2.
Work is underway to arrange the vertical basement elements in section E1.
Work is underway to arrange the vertical basement elements in section B.
Work is underway on the installation of a tower crane.

House number 8
Work is underway on the construction of the floor slab of 3 floors in section G *.
Work is underway on the construction of the floor slab of the 3rd floor in section B **.
Work is underway to arrange the vertical elements of the 3rd floor in section B.

LCD "Otradny"

House number 2
Finishing works are carried out in apartments with a fine finish - 1st floor.

House number 3
Installation of plastic windows - 98%
Facade works - 98%
Work is underway on the device electrical installation and plumbing works - ground floor, ITE, switchboard and engine room, lamps.
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th and 14th floors.

House number 4
Installation of plastic windows - 98%
Facade works - 95%
Work is underway on the device of electrical installation and plumbing works - ITE
Installation of radiators for apartments - 3-16 floor.
Work is underway on the device of ceramic tiles in MOS - 1, 13, 16 and base.
Work is underway to install apartment doors and technical rooms.

House number 5
Installation of metal windows - 95%
Plastering works are underway - 6, 10th floor.
Work is underway on the device of electrical installation and plumbing works - floors 3-16.
Installation of equipment for passenger and freight elevators.

LCD "Academ-Quarter"

House number 1
Vertical element of the 16th floor, floor slab of the 15th floor.
Masonry - 2, 3, 4th floor.

House 2
Floor slab 16 floors.