Progress of construction as of 18.10.18

  • 18/10/2018

RC "Volodymyrskyi"

Pouring of the vertical elements of the 23d floor has been commenced. Installation of the formwork for the slab over the 23d floor has been commenced. 
Brickworks at the basement and on 2, 4, 9, 10, 11, 12, 13 floors are ongoing. 
Works on installation of concealed low-current wiring on typical residential floors inside monolith structures are in progress. 
Installation of internal heating network and ventilation, electric wiring, water supply, sewage, low-current networks and smoke exhaust system “smart-house”, screed, wall plastering, finishing works at GUP – 5th floor.


RC “Syretski Sady” 

Building No. 1
Completion of glazing of windows and balconies – 95%.
Plumbing works –water supply, sewage and heating risers are completed, installation works inside apartments are ongoing ; sanitary ware and radiators are installed - 2 floor;
Electric wiring – all installation works prior to plastering have been completed; installation of equipment (outlets etc.) section two – 90%.
Plastering works – 4th to 13th floors.
Façade – heat insulation of walls is ongoing – 65%. 
Works on decorative finishing – 35%.
Entrance groups – basements are completed

Building No. 2 
Brickworks – 1st to 13th floor.

Building No. 3 
Installation of frame structures – 1-14 floors

Building No.4
Installation of frame structures – 1-20th floor
Brickworks – 1st to 11th floor.
Windows – 2nd to 5th floor.

Building No.5
Pile field is completed


RC “Yaskravyi”

Building No.6 
Works on installation of walls, partitions, brickworks (external -90%, internal – 75.8%) are in progress. 
Installation of window structures-76%
Plumbing works –35.5%
Electric wiring works – 11.9%
Ventilation and smoke exhaust system – 2.8%
Low-current systems – 3.7%
Wall plastering – 13.2%
Installation of screed – 12.8%
Finishing works at GUP – 3.7%
Installation of elevators and adjustment – 70%
Façade works – 23.8%
Roofing – 88.3%
Entrance group – 30%

Building No. 7 
Plumbing works – 93%
Electric wiring works – 85%
Ventilation and smoke exhaust system – 90%
Low-current systems – 92%
Finishing of GUP – 95%
Installation of elevators and adjustment – 85%
Brickworks on the roof – 1%
Development of adjoining territory – 81%

RC “Parkovi Ozera” 

Building No. 12 
Decoration works inside apartments.

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96% 
Plumbing works – 41%
Electric wiring works – 33%
Ventilation and smoke exhaust system – 22%
Low-current systems – 17%
Wall plastering – 57% 
Installation of screed -43% 
Finishing works at GUP -10%
Installation of elevators and adjustment – 85%
Façade works – 70 %
Façade heat insulation 88%
Façade finishing – 74%
Roofing – 69%.
Entrance group – 42%


RC “Ozernyi Hai Gatne” 

Building No.2
Internal decoration -99%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration - 90%.

Building No. 5
Internal decoration - 88%.
Glazing – 96%
Façade – 98%

Building No.6
Monolith works : 
Section 1: 3d floor – 40%
Section 3: 3d floor - 50%

Building No. 9
Excavation works for the basement. – 30%

RC “Traditsiya” 

Building No.2
Active finishing works inside apartments. 

Building No.4
Vertical structure element of the 9th floor, slab over the 8th floor are in progress. Brickworks – 3d floor and basement.


RC “Malakhit”

Building No.4
Section 401 – slab over the 24th floor. Brickworks on 10-21 floors.
Sections 402-403 – façade works – 80%
Section 403 - finishing works – 2-8 floors. 
Sections 405-406 – finishing works are ongoing: section 404 - final decoration (tiling, painting) – 1-13 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 95%

Works on waterproofing of parking areas are ongoing. Development of promenade zone – 35%.
Works on development of the territory of the building N0.4 are ongoing.

Building No.5
Installation of the pile field – 50%

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases of all sections is in progress.
Finishing works at GUP: section Ж – completed except 1st floor, section Г – 8th floor and section Д – everything is completed except 1st floor. 
Installation of external mains is in progress.
Works on waterproofing of entrance groups are ongoing.
Installation of façade is in progress. Works on development of adjoining territory are ongoing.

Building No.4
Works on installation of window structures: section B – on the 17th floor. 
Plastering works at GUP: section E – engine room; section B – on the 16th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing. 
Adjusting of elevators is in progress.
Finishing works and tiling at GUP: section Е – on the17th floor, section Б – on the 14th floor, section В – on the 13th floor.

Building No.5
Installation of monolith frame
section E – parapet installation – 90%, 
section Б – parapet installation – 30%.
Brickworks on the floors 5, 7, 8, 9, 10, 11 of section A; section Е - 
on the 8, 9, 11 floors and basement. Section Б - on the 1, 3, 6, 7, 8, 10 floors. 
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of the slab over the 10th floor at section Г
Installation of the slab over the 10th floor at section E.
Installation of vertical elements of the 10th floor at section Д*
Brickworks on the floors 3, 4, 5, 6, 7 at section Г. 2, 3, 4 and 5 floors at section Е and 2, 3, 4, 5, 6, 7 floors in section Д *.

Building No.8
Installation of the vertical elements of the basement at section Г *
Reinforcement of the basement plate at section Б** is in progress.
Works on arrangement of chip basis at sections B are in progress.

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments (1, 6, 7, 8, 9, 11, 13, 14, 15, 16 floors).

Building No.3 
Roofing works are ongoing.
Installation of metal and plastic windows - 95%.
Façades works are in progress – 85% 
Installation of cement and sand screed is in progress on the 14th floor.
Wall plastering on the 12, 13 floors is in progress (GUPs), ) and on the 8th floor (turn-key apartments).
Works on installation of electric cable from the 7th to 8th chamber. 
Tiling on the 18th floor is in progress.
Wall plastering decoration works on the floors 4, 5, 7.

Building No.4 
Installation of metal and plastic windows – 95%
Brickworks on the roof are in progress – 95%
Façades works are in progress – 85%
Works on electric wiring and plumbing are in progress.
Installation of cement and sand screed on the 5th floor is in progress.
Roofing is in progress.
Wall plastering on the basement floor – 4th, 14th (turn-key apartments) 
Works on installation of the frame for the boiler room are in progress.
Roof boiler room is completed.

Building No.5 
Brickworks on the basement are in progress.
Works on installation of metal and plastic windows are ongoing – 70%.
Façade works are ongoing.

RC “Teremky” 

1st stage. Completion of installation of windows up to the 25th floor inclusive. Roofing works are ongoing. Painting of the façade is ongoing. Internal mains and plumbing works are in progress. 
Wall plastering of GUPs on the 1st floor.
Pouring of screed - 20-21 floors. Installation of basket holders for air-conditioners. 
Stage 2, section 2 – Installation of windows on 24 to 25 floors. Water-proofing of the basement is ongoing. Roofing works are ongoing. Electric wiring works on the 4th floor. Wall plastering inside apartments on the 3d floor.
Stage 2, section 3 – Installation of windows on the 19th floor. Heat insulation of the roof. Electric wiring works on the 4th floor are ongoing. Water-proofing of the basement is in progress.
Stage 3, section 4 – pouring of the slab over the vertical elements of the 18th floor. Brickworks - on the 2nd to 9th floors.
Stage 3, section 5 – pouring of the slab over the vertical elements of 18th floor is completed. Brickworks - on the 5th to 8th floors.
Stage 3- section 6 – pouring of the slab over the vertical elements of 17th floor is completed. Brickworks - on the 2nd to 5th floor are in progress inclusive