Progress of construction as of 21.12.18

  • 21/12/2018
Tags:

RC "Volodymyrskyi"

Brickworks for vent ducts at the HEU, on the 17th, 18th, 19th floors.

Installation of internal electric wiring system

Roofing – 10%

Installation of still fencing of staircases – 6th floor.

Installation of external engineering networks  -18%


RC “Syretski Sady” 

Building No. 1
Internal decoration works are in progress – screeds and plastering

Building No. 2 
Windows – 2-8 floors (section 2,3)

 

Building No. 3 
Brickworks – 1st to 10th floor


Building No.4
Brickworks – 1st to 22th floor.

Windows – 2nd to 11th floor.

Building No.5
Vertical element of the basement is in progress.

 

RC “Yaskravyi”
 

Building No.6 
Works on installation of walls, partitions, brickworks (external -96%) are in progress. 
Installation of window structures-76%
Plumbing works –51.7%

Electric wiring works – 26.9%

Ventilation and smoke exhaust system – 8.3%

Low-current systems – 14.8 %
Wall plastering – 38.6%
Installation of screed – 52.6%

Decoration of GUPs – 20%
Installation and adjustment of elevators– 70%
Façade works – 90.5%

Roofing – 92.3%
Entrance group – 69.3%

Development of the territory – 0.7%
 

Building No. 7 
Plumbing works – 98%
Electric wiring works – 96%
Ventilation and smoke exhaust system – 94%
Low-current systems – 97%
Finishing of GUPs – 99%
Installation and adjustment of elevators – 95%
Development of adjoining territory – 90%

 

RC “Parkovi Ozera” 

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96%

Plumbing works – 67%
Electric wiring works – 52%
Ventilation and smoke exhaust system – 30%
Low-current systems – 44%
Wall plastering –93% 
Installation of screed -85%

Finishing works at GUPs – 52%

Installation and adjustment of elevators – 90%
Façade works – 96%
Façade heat insulation - 98%
Façade finishing – 96%
Roofing – 95%.
Entrance group – 81%

 

RC “Ozernyi Hai Gatne” 
Building No. 5
Internal decoration – 93.35%.
Façade – 99.9%

Building No.6
Monolith works : 

Section 3: parapet  – 30%

 

Building No.9
Gravel bedding – 85%

Concrete bedding - 61%

Water proofing -60%

Reinforcement of the basement at sections 5 and 6 – 40%

 

RC “Traditsiya” 
Building No.2
Active finishing works inside apartments are ongoing.


Building No.4
Vertical element of the 14th floor and the slab over the 14th floor are in progress.

Brickworks – 7h floor and basement.
 

RC “Malakhit”
Building No.4
Section 401 – Brickworks on 24-25 floors.

Decoration works on the 1st to 18th floors.

Active roofing works.

Façade works – 25%
Development of promenade zone – 40%.


Building No.5
Vertical element of the 1st floor is in progress

 

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases in all sections is in progress.
Finishing works at GUP: section
Ж – 1st floor.

Façade works are about to be completed. Works on development of adjoining territory are ongoing.

Works on arrangement of heat supply system are in progress.

 

 

Building No.4
Works on adjustment of elevators are ongoing.


Building No.5
Brickworks on the basement and 8, 11, 12 floors and roof of section A; on the 9, 10, 11, 12 floors and basement of the Section  E; on the 7, 8, 10, 11 floors and basement of section
Б.

Brickworks for ventilation shafts on the roof at sections A and E are in progress.

Water proofing of basements at sections А, Б and Е is in progress.

Back filling of the pit is in progress.

Installation of windows: on the 5th to 7th floor at sections A, Б and E.  

Building No.6
Installation of vertical elements of the 17th floor at section Г
Installation of slab over the 16th floor at section E.
Installation of slab over the 16th floor at section Д*
Brickworks on the 4, 5, 7 floors and on basement in section Г; on 5, 7, 8 floors at section Е and on the 1st, 7th and 8th floors of section Д *.

Works on water proofing of basements are in progress.

Works on backfilling of the pit are ongoing.

Building No.7
Works on reinforcement of the basement slab at section E2.

Installation of vertical elements of the basement at section E1 is in progress.

Installation of vertical elements of the basement at section B is in progress.

Works on reinforcement of the basement for tower crane are in progress.

 

 

Building No.8
 

Works on installation of the slab over the 2nd floor at section Г.

Works on installation of the slab over the 2nd floor at section Б.

Works on installation of vertical elements of the 1st floor at section B are in progress.

 

 

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments (1 floor).


 

Building No.3 

Installation of metal and plastic windows - 98%.
Façades works are in progress  – 98%.

Works on electric wiring and plumbing are in progress (basement, IHU, pumping station, electric cabinet and machine room, installation of lighting devices).

Territory development works are in progress.

Painting works at GUPs and staircases (2-16 floors).
Installation of decorative plaster on the 14th floor is in progress.

 

 

 

Building No.4 
Installation of metal and plastic windows – 98%
Façades works are in progress – 95%

Works on electric wiring and plumbing are in progress (IHU), installation of radiators inside apartments from 3d to 16th floors.

Tiling works on GUPs from 2nd to 7th and 9, 10, 12, 17, 18 floors and basement are in progress.

Installation of cement and sand screed on 3, 4, 9 floors (baths).

Installation of entrance doors to apartments and technical premises is in progress.

Development of the territory is ongoing.

 

Building No.5 
Works on installation of metal and plastic windows are ongoing – 95%.

Works on arrangement of cement and sand screed on the 5th floor are ongoing.

Plastering works on the basement floor are in progress.

 

 

RC “Teremky” 

1st stage

Works on heat insulation of the building are in progress 90%

Painting façade works are ongoing -90%.

Works on installation of internal mains and plumbing works are in progress.

Installation of basket holders for air conditioner units – 95%. Connection of communication networks to the building.

 

Stage 2, section 2

Roofing works are in progress -80%

Works on heat insulation of the building are in progress - 20%

 

Stage 2, section 3

Roofing works are in progress – 80%.

Pouring of screed on the 6th floor - 14%

 

Stage 3, section 4

Slab over the vertical elements of the 25th floor is installed.

Brickworks – 11th to 16th floor - 30%.

 

 

Stage 3, section 5

Slab over the vertical elements of the 24th floor

 Brickworks on 11th to 16th floors are in progress - 30%.


 

Stage 3, section 6 

Slab over the vertical elements of the 23d floor is installed.

Brickworks on 2nd to 10th floor - 30%.

 

 

RC «Academ-Kvartal»

 

Building No.1

Vertical element of the 15th floor, slab over the 14th floor are in work.

Brickworks – 2nd and 3d floors and basement.
 

Building No.2

Vertical element of the 15th floor, slab over the 14th floor are in work.

Brickworks - 2nd floor and basement.