Dynamics of construction as of 22.02.19

  • 22/02/2019

«Volodymyrsky» RC

Waterproofing - 5-10 floor, base.
Laying - TP, 19, 21, 23 floor.
The arrangement of internal power supply networks is 5-9 floors.
Installation of internal heating and ventilation networks - 1-10 floors.
The arrangement of internal networks of water supply and sewage - 1-10 floor.
Installation of finishing works MZK - 12,75%
The arrangement of door structures and hatches is 4-24 floors.
Mounting of lift equipment - 25% (1-24 floor).
Roofing - 16%
The arrangement of window constructions is 5-16 floors.
The arrangement of metal fence staircases - 6 floors.
Arrangement of external engineering networks - 35%

«Syretsky gardens» RC

House 1
Inside, the interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.

House 3
Masonry - 13-16 floors.

House 4
Windows - 2-22 floors.

House 5
Vertical element of the 4th floor.

«Bright» RC

House number 6
Works on the arrangement of walls and partitions, masonry (external contour - 96%)
Installation of window constructions - 87%
Sanitary engineering works - 72.7%
Electrical work - 29,1%
Ventilation and smoke removal - 18.5%
Weakness systems - 25,9%
Plaster of walls - 56,9%
Screw arrangement - 79,6%
Finishing of IGC - 42.2%
Installation of elevators and start-up and adjustment works - 75%
Facade arrangement - 95%
Roof installation - 92.3%
Incoming group - 85%
Amenties - 0.7%

"Park Lakes" RC

House No. 13
Installation of window constructions - 98%
Sanitary engineering works - 87%
Electrical work - 78%
Ventilation and smoke removal - 63%
Weak-current systems - 53%
Installation of elevators and start-up and adjustment works - 90%

«Ozerny Gai Gatne» RC

House No. 5
Interior decoration - 95.7%
Facade - 99.9%

House number 6
Masonry of external and internal walls:
1st floor - internal - 95%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%
7th floor - external - 80%; internal - 10%

House No. 9
Monolithic works:
5, section 6 - 95%

«Tradition» RC

House number 2
The clean finishing of apartments is being actively pursued.

House number 4
Vertical element of the 19th floor, floor plate of the 18th floor.
Masonry - 8-13 floor and basement.
Extranets - 30%
Plaster - 2nd floor.
Electricity - 2-3 floor
Sewerage - 10%

«Malakhit» RC

House number 4
Finishing works - 1-22 floor (clean).
Facade works - 25%
Improvement - promenade area - 40%

House number 5
Stove floor 5 floors.

«Nyvky-Park» RC

House number 3
Work is under way to start the heat supply.
The transfer of apartments to investors is in progress.

House number 4
Lifts are being adjusted.
Work is ongoing on the finishing of apartments with renovations.
Finished works on the facade arrangement.
Work is underway on installation of window drafts and baskets for air conditioners.

House number 5
A laying is carried out in the basement, on 13, 14, 15, 16, 17 floors of Section A; on 9, 11, 14, 15 floors and basement section E; on the 8th floor of section B.
Work is being done on the laying of Vent. shafts on roof sections B and E.
Works on waterproofing of basements of sections A, B and E are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are underway: 8-10 floors in sections A, B and E.
The work on laying the fire safety system cable is underway: Section A - 9-13 floor, section E - 2-5 floor.

House number 6
Arrangement of parapets in Section E.
Installation of parapets in section D *.
Masonry is carried out: 4, 5, 7, 8 floor and basement on section Г; 5, 7, 8 floor on section E; 1, 7, 8 floor on section D *.
Works on waterproofing basements are underway.
Work is underway on the backfill of the foundation pit.
Works are underway on the installation of windows: 5-7th floor in sections G, E, D *.

House number 7
Work is underway on arrangement of vertical elements of the 1st floor in section Е2.
Work is carried out on the arrangement of vertical elements of the 1st floor in section E1.
Works are underway on the arrangement of vertical elements of the 1st floor in section B.

House number 8
Work is underway on the arrangement of vertical elements of the 6th floor in section G *.
Work is underway on arrangement of vertical elements of the 6th floor in Section B **.
Work is underway on the arrangement of vertical elements of the 5th floor in section B.

«Otradny» RC

House number 3
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 98%
Work is underway on installation of electrical and plumbing works - a socle, an ITP, an electrical and machine department, the installation of fixtures, the installation of input automata in apartments, the installation of meters for heating.
There are finishing works - 4, 5, 8, 9, 13, 14 floor (apartments with repair).

House number 4
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 95%
Work is underway on installation of electrical and plumbing works - a socle, an ITP, an electrical and machine department, the installation of fixtures, the installation of input automata in apartments, the installation of meters for heating.
There are finishing works - 4, 5, 8, 9, 13, 14 floor (apartments with repair).

House number 5
Works on installation of metal-plastic windows - 95%
Works on plaster laying on the 10th floor are under way.
Installation of equipment for passenger and freight elevators
Work is underway to insulate the ground floor.
Work is underway on the arrangement of facades from 2 to 16 floor.
Works on the installation of doors in the basement.
The arrangement of the cement-sand link - 11, 12th floor.

«Akadem-Kvartal» RC

House 1
Slab floor 19th floor.
Laying - 7th floor.

House 2
Floor plate floor 20, vertical element 21 floor.
Laying - 4th floor.


«Teremki» RC

1 queue
Work is being done on painting the facade.
Internal engineering and plumbing work are carried out.
Connected to home communication.
Performed repair work (tile layout): 13th and 14th floor.
2nd line, 2nd section
Roofing works are being performed.
Execution of plaster walls in apartments on the 23rd floor.
Work is carried out on insulation of the house.
Installation of elevators is underway.
2nd stage, 3rd section
Roofing works are being performed.
Execution of plaster walls in apartments on the 23rd floor.
Installation of elevators is underway.
3rd stage, 4th section
Mortar 1 to 21 floor is underway.
3rd turn, 5th section
Mortar 1 to 20 floor is underway.
3rd turn, 6th section
Overlapping roof of the house is being performed.
A masonry is taking place from 19 to 20 floors.