Dynamics of construction as of 22/03/19

  • 22/03/2019

Dynamics of construction as of 03/22/19

"Academ-Quarter" RC

House number 1
Floor slab 21 floors.
Masonry - 10th floor.

House 2
Floor slab 21 floors, vertical element 22 floors.
Masonry - 6th floor.

"Vladimirsky" RC

Waterproofing device - 28% (5-10 floor, basement).
Masonry - TE, 23, 24 floor.
The device of internal power supply networks - 5-11 floor.
The device of internal networks of heating and ventilation - 1-11 floor.
The device of internal water supply and sewerage networks - 1-16 floor.
Device finishing works MOP - 35%
Door construction device - 45% (floor 4-25)
Installation of elevator equipment - 45% (1-24 floor).
Roof installation - 16%
The device window designs - 5-16 floor.
Facade arrangement - 26%

"Malachite" RC

House number 4
Finishing works - 1-23 floor (finishing).
Facade work - 55%
Improvement - promenade area - 40%

House number 5
Vertical element of the 9th floor.
Masonry - 1-4 floor.

"Nyvky Park" RC

House number 5
The laying is carried out on the 13th, 14th, 15th, 16th, 17th floors of section A; on 9, 11, 14, 15 floors of section E; on 8, 12, 14 floor of section B.
Work is underway on the laying of ventilation shafts on the roof of section B.
Works on waterproofing the basements of sections A, B and E.
Work is underway on backfilling the excavation.
The installation of windows is in progress: floor 14–17 in section A, floor 11–14 in sections B and E.
Work is underway on laying the cable of the fire safety system: section E 4-10 floor, section B - 3-10 floor, section A - 8-14 floor.
Finishing works are being carried out for section A - basement, floor 2-5 of section A, E, B.
Work is underway on the construction of the roof on section A, B and E.
Work is underway on the device facade.
Work is underway to connect the engineering networks.

House number 6
The laying is carried out: 5, 7, 9, 10, 11, 12 floor and a cellar on section G;
7, 8, 9, 10, 11, 12 floor on section E; 9, 10, 11, 12, 13, 14 floor and basement in section D.
Work is underway on waterproofing basements.
Work is underway on backfilling the excavation.
Work is underway on the installation of windows: 5-7 floor sections G, E, D.
Finishing works are being carried out on the 3rd floor of section D, E and E.
Work is underway to connect the engineering networks.

House number 7
Work is underway to arrange the vertical elements of the 3rd floor of section E2.
Work is underway to arrange the vertical elements of the 3rd floor of the E1 section.
Work is underway on the construction of the floor slab of 2 floors in section B.
The device of a waterproofing of cellars on the sections B, E1, E2.

House number 8
Work is underway to arrange the vertical elements of the 8th floor of section G *.
Work is underway to arrange the vertical elements of the 8th floor in section B **.
Work is underway on the arrangement of the floor slab of the 7th floor in section B.
The device of waterproofing basements on sections G, B, B.

"Lake hai Gatne" RC

House number 5
Interior finish - 96.9%
Entrance groups - 98%
Facade - 99.9%
House territory - 52%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 97%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%
6 floor - internal - 97%
7th floor - internal - 97%
8th floor - internal - 97, 5%
9th floor - internal - 97%
Installation of window units: 1 section 3 floors - 50%

House number 9
basement:
1, 2 section - 50%
3rd floor:
3, 4 section - 50%

"Otradny" RC

House number 3
Installation of plastic windows - 98%
Facade works - 98%
Work is underway on electrical installation and plumbing (installation of automatic machines in the apartments, installation of meters for heating).
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 4
Installation of plastic windows - 98%
Facade works - 95%
Work is underway on the device of electrical installation and plumbing works (lamps on the floors of the MSC, the installation of household appliances in the apartments with repair).
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 5
Installation of metal-plastic products - 95%
Work is underway on the installation of plaster on the 13th, 15th floor.
Installation of equipment for passenger and freight elevators.
Work is underway on the device ventilation - 75%
Work is underway on the device facades from 2 to 16 floor.
The device cement-sand screed on the 11th floor.
The insulation of the staircase with mineral wool is up to the 7th floor.
Work is being done on the warming of the facade on the roof.

Plumbing and electrical work is being carried out from the 2nd to the 16th floor.

"Park Lakes" RC

House number 13

Plumbing works - 95%

Electrical work - 88%

Ventilation and smoke removal - 80%

Low-voltage systems - 65%

Installation of elevators and commissioning - 97%

Residential complex "Syretsky Gardens"

House number 1
In the work of interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.
Plaster, screeds - section 3, 2, 1 - work started.

The House 3
Masonry - 13-16 floor.

House 4
Windows - 2-22 floor.
Facade insulation - 10%

House 5
Vertical element of the 9th floor.
Masonry - 1-2 floor.
 

"Teremki" RC

1st turn

Work on the painting of the facade.

Internal engineering and plumbing works are being carried out.

Connection of communications to the house is carried out.

Repair work in progress:

tile layout:

4, 9, 11, 13, 14, 19, 23, 24th floor.

- glueing wallpaper:

4, 9, 13, 18th floor.

2nd stage, 2nd section

Roofing work is underway.

Plastering of walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors.

Filled floor screed from 2 to 17 floor.

Plaster walls in common areas from 3 to 15 floor, except 5

Work on the insulation of the house.

Painting of MOP ceilings from 4th to 15th floor

Installation of elevators.

2 stage, 3 section

Roofing work is underway.

Plastering of walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors.

Filled floor screed from 2 to 17 floor.

Plastering of walls in common areas from the 3rd to the 15th floor, except 5

Work on the insulation of the house.

Installation of elevators.

3rd stage, 4th section

The laying is carried out on the 22, 23, 24 floor.

Windows - 2-4 floor.

3 stage, 5 section

The laying is carried out on the 22, 23, 24 floor.

Windows - 2-4 floor.

3rd stage, 6th section

Overlapping roof of the house.

The laying is carried out on the 23rd floor.

Windows - 2-4 floor.

"Tradition" RC

House number 2
Active finishing is carried out apartments.

House number 4
Vertical element of the 21st floor, floor slab of the 20th floor.
Masonry - 11-15 floor and basement.
External networks - 50%
Plaster - 2-4, 6, 8 floor.
Electricity - 2-6 floor
Sewerage - 25%
The artist - 2-3 floor.


"Yaskravy" RC

House number 6

Installation of window designs - 90%

Plumbing works - 82.7%

Electrical work - 54%

Ventilation and smoke removal - 43%

Low-voltage systems - 30%

Plaster walls - 76.4%

Screed device - 96.8%

Finishing MOS - 75%

Installation of elevators and commissioning - 80%

Facade arrangement - 96.3%

Roof installation - 93%

Entrance group - 87.7%

Improvement - 2.7%