Dynamics of construction as of 23.04.20

  • 23/04/2020

Dear clients! We do not stop to create your dream apartments. We offer you to get acquainted with the up-to-date dynamics of construction. The status of the works is fixed as of 04/23/20.

Residential complex Akadem-Kvartal

House 1

Installation of windows - 98%

Water supply - 97%

Heating - 91%

Electricity supply - 94%

Fire protection systems - 65%

Wall plaster - 96%

Coupler Setting - 90%

IWC Finish - 15%

Facade works- 75%

Elevator installation - 25%

Doors - 68%

Roof works - 92%

Entrance group - 97%

House 2

Installation of windows - 99%

Water supply - 93%

Heating - 77%

Power supply - 83%

Fire protection systems - 42%

Wall plaster - 78%

Coupler Setting - 50%

Installation of metal doors in apartments and MZCs started - 12%

Clean staircase finishing - 30%

Elevator installation - 22%

Facade works - 90%

Roof works - 80%

Entrance group - 87%

Residential complex Nivki-Park

House 5:

Surrounding area improvements.

Final works are carried out in “apartments with design”.

House 6:

Surrounding area improvements.

Final works are carried out in “apartments with design”.

House 8:

Setting up the framework of the enterance group

45% facade arrangement

Section B:

Windows on the 15th floor.

DSK on the 12th floor.

Plaster on the 10th floor.

Section G.

Windows on the 17th floor.

DSK on the 16th floor.

Plaster on the 14th floor.

Section B.

Windows on the 17th floor.

DSK on the 17th floor.

Plaster on the 11th floor.

House 7:

Setting up the framework of the enterance group

Section E2:

Roof arrangement

Windows on the 17th floor.

DSK on the 17th floor.

Plaster on the 12th floor.

Section E1:

Roof arrangement

Windows on the 17th floor.

DSK on the 12th floor.

Plaster on the 9th floor.

Section B:

Windows on the 9th floor.

DSK on the 3rd floor.

Plaster on the 3rd floor.

House 12:

Section D:

Installation of a monolithic frame on the 10th floor.

Laying of masonry on 1-7-th floors.

Section I:

Installation of a monolithic frame on the 10th floor.

The masonry unit on the 1-6 floors.

Section E:

Installation of monolithic frame on the 11th floor.

Laying of masonry on 1-5 th floors.

Section B:

Installation of monolithic frame on the 8th floor.

Laying on the 1st to 3rd floor.

House Parking 12

Section G.

Arrangement of railings on the floor.

Section D.

Vertical adjustment.

House 11:

Foundations I, Z sections.

Residential Complex Syretsky Sady

House 1:

Improvement - 95%

House 2:

Facade insulation - 99%

Elevators - 100%

Renovated apartments - 90%

Installation of windows- 99%

Improvement - 45%

House 3:

Masonry - 98%

Roof arrangement - 95%

Windows - 98%

Facades - 80%

Apartments without repair - 70%

House 4:

Windows - 100%

Facade insulation - 97%

Roof arrangement - 100%

Stacking - 100%

Plaster, ties - 100%

House 5:

Windows - 90%

Roofing - 70%

Facade - 50%

Finish - 15%

House 6:

«Випробувальні кущі свай.» Это и на укр звучит странно

House 7:

Pile field

House 8:

Frame 12 floors.

Brick masonry 3 floor.

Residential Complex Teremky

2nd turn, 2 section.

Completed facade work (100%).

The house is insulated (100%).

Roofing work is done. (100%).

The walls of the apartments were repaired (100%).

Electricity wiring in apartments with repair (100%).

Floor screed (100%).

Plastering of the walls in the MZK (100%)

The ceilings of the MZC (100%) have been painted.

Elevator installation (100%).

Air conditioning baskets installed (100%)

Finished painting of ceilings in apartments with repairs (100%).

Layout of the tiles in apartments with repair (100%).

Pasted wallpaper in apartments with repairs (100%).

Layout of laminate in apartments with repairs (100%).

Installation of interior doors in apartments with renovation (100%).

The territory is being improved (90%).

Cleaning works were performed in apartments with renovation (100%).

2nd turn, 3 section

Completed facade work (100%).

The house is insulated (100%).

Roofing work is done. (100%).

The walls of the apartments were repaired (100%).

Electricity wiring in apartments with repair (100%).

Made of floor screed (100%).

Plastering of the walls in the MZK (100%) was done.

The ceilings of the MZC (100%) have been painted.

Elevator installation (100%).

Air conditioning baskets installed (100%)

Finished painting of ceilings in apartments with repairs (100%).

Layout of the tiles in apartments with repair (100%).

Pasted wallpaper in apartments with repairs (100%).

The layout of the laminate in the apartments with renovation (100%).

Installation of interior doors in apartments with repairs (100%).

The territory is being improved (90%).

Cleaning works were performed in apartments with renovation (100%).

3rd turn - 4th section.

Monolithic works (100%) were completed.

The roof of the house is completed (100%).

Completed masonry (100%).

Installation of windows (100%).

House is insulated (100%)

Completed facade work (100%).

Plastering of the walls in the MZK (100%) was done.

Plastering of walls in apartments (100%) was done.

Filling the floor screed (100%).

Elevator installation (100%).

Installation of radiators inside the apartments (100%).

Installation of entrance doors in apartments (100%).

Layout of floor tiles in MZK (100%),

Electricity wiring in apartments with repair (100%).

Installation of air conditioning baskets (100%)

The territory is being improved (90%).

Finished painting of ceilings in apartments with repairs (100%).

Layout of the tiles in apartments with repair (100%).

Installation of plumbing fixtures in apartments with repair works (50%).

Pasting of wallpaper in apartments with repair (35%).

Laying laminate in apartments with repairs (25%).

Installation of interior doors in apartments with repairs (10%)

The third turn is the 5th section.

Monolithic works (100%) were completed.

The roof of the house is completed (100%).

Completed masonry (100%).

Installation of windows (100%).

House is insulated (100%)

Completed facade work (100%).

Plastering of the walls in the MZK (100%) was carried out.

Plastering of walls in apartments (100%) was done.

Filling the floor screed (100%).

Elevator installation (100%).

Installation of radiators inside the apartments (100%).

Installation of front doors in apartments (100%).

Layout of floor tiles in MZK (100%),

Electricity wiring in apartments with repair (100%).

Installation of air conditioning baskets (100%)

The territory is being improved (90%).

Finished painting of ceilings in apartments with repairs (100%).

Layout of the tiles in apartments with repair (100%).

Installation of plumbing fixtures in apartments with repair works (50%).

Pasting of wallpaper in apartments with repair (35%).

Laying laminate in apartments with repairs (25%).

Installation of interior doors in apartments with repairs (10%)

The third turn is the 6th section.

Monolithic works (100%) were completed.

The roof of the house is completed (100%).

Completed masonry (100%).

Installation of windows (100%).

House is insulated (100%)

Completed facade work (100%).

Plastering of the walls in the MZK (100%) was carried out.

The walls of the apartments were plastered (100%).

Filling the floor screed (100%).

Elevator installation (100%).

Installation of radiators inside the apartments (100%).

Installation of front doors in apartments (100%).

Layout of floor tiles in MZK (100%),

Electricity wiring in apartments with repair (100%).

Installation of air-conditioning baskets (100%)

The territory is being improved (90%).

Finished painting of ceilings in apartments with repairs (100%).

Layout of the tiles in apartments with repair (100%).

Installation of plumbing fixtures in apartments with repair works (50%).

Pasting of wallpaper in apartments with repairs (35%).

A llama layout is in progress

Residential complex Sky Avenue

1 section

Monolithic works were carried out on the 16th floor, masonry - 14th floor.

Section 2

14 floors of the monolith, masonry - 11 floors.

Section 3 - installation of formwork of the 2nd floor.

4, 5 section - installation of formwork covering the 4th floor.

Glazing - 1st section 7th floor and 2 2nd floor section.

Finial works on apartments on the 2nd floor of 2 sections are finished

Residential complex City Hub

Section 1

The monolithic foundation slab was poured

Arranged vertical foundation slabs - 90%

Section 2

The monolithic foundation slab was poured

Waterproofing of the foundation - 90%

Residential Complex Ozernyi Hai Hatne

House 6:

Facade works - 99%

Adjacent area -75%

Finishing works:

Apartments without repair - 100%

Renovated apartments - 60%

IAC - 99%

Elevators - 99%

External networks - 95%

House 9:

Laying of exterior and interior walls - 100%

Installation of window blocks - 100%

Facade work - 95%

Finishing works:

Wall Plaster - 97%

Floor screed - 70%

Water supply and sewerage - 95%

Heating - 90%

Electricity supply - 90%

Elevator installation - 99%

Residential complex Prychal 8

Section 1

Facade arrangement - 3%

Roof arrangement - 80%

Wall and partition arrangement - entrance groups - 98%

Installation of metal-plastic structures, entrance doors to apartments and doors of MZK - 95%

Section 2

Monolithic frame arrangement - 98%

Roof arrangement - 70%

Wall and partition arrangement - 98%

Installation of metal-plastic structures, entrance doors to apartments and doors of MZK - 65%

Section 3

Horizontal element 18 floor

Arrangement of walls and partitions 12 floors

Section 4

Horizontal element 18 floor

Arrangement of walls and partitions 15 floors

Section 5

Arrangement of the base plate

Opening of the monolithic frame

Residential Complex Volodymyrskyi

Decor elements (cornices), illumination of facades.

Installation of fences

Landscaping yard, landscaping

Residential Complex Intergal City

On tower "A" - the completed overlapping slab of the 9th floor and PPC.

The tower "D" - reinforced slab floor 12 floors. 

On tower "B" – working on 9 floor’s slab.

Tower "D" works on the construction pit installation.

Sports Complex: monolithic structures of all pools are made. The walls and columns of the 4th floor are being constructed.