Progress of construction as of 23.11.18

  • 23/11/2018

LCD «Volodymyrsky»

Concrete verticals 25th floor. The installation of the formwork of the technical floor slab is carried out.
A laying is carried out - a socle, 1, 4, 14, 15, 16 floor.
The works on the installation of a hidden extension of power supply networks on typical residential floors in monolithic structures in a plate over 24 floors have been completed.
The pipework was started on the 5th floor.
The arrangement of lightning protection is carried out only in monolith.
The arrangement of the metal fence of staircase cages - 6th floor.

LCD «Syretsky gardens»

House 1
Finished window and balcony glazing - 99%
Facades - insulation work on walls - 80%
Incoming groups - foundations are made.

House 2
Laying - 1-16 floor.
Roofing works in all three sections - 1 layer.
Windows - 2-4 floor (3 sections).

House 3
Laying - 1-5 floor.

House 4
Laying - 1-16 floor.
Windows - 2-8 floor.

House 5
Pile field works completed. Foundations are made.

LCD «Bright»

House number 6
Works on the arrangement of walls and partitions, masonry (external contour - 92.5%, internal - 97.4%)
Installation of window constructions - 76%
Sanitary engineering works - 43.2%
Electrical works - 18,4%
Ventilation and smoke removal - 5.6%
Weak systems - 8.9%
Plaster walls - 24,9%
Screw arrangement - 33.7%
Decoration of IGC - 13%
Installation of elevators and start-up and adjustment works - 70%
Facade arrangement - 71.3%
Roofing - 88.3%
Incoming group - 40%

House number 7
Sanitary engineering works - 97%
Electrical work - 91%
Ventilation and smoke removal - 93%
Weakness systems - 95%
Finishing of IGC - 99%
Installation of elevators and start-up and adjustment works - 90%
Amenties - 86%

LCD park lakes

House No. 13
Arrangement of walls, partitions, masonry (internal) - 97%
Installation of window constructions - 96%
Sanitary engineering works - 56%
Electrical works - 46%
Ventilation and smoke removal - 26%
Weak-current systems - 33%
Plaster of walls - 83%
Stacking - 75%
Interior decoration - 37%
Installation of elevators and start-up and adjustment works - 90%
Facade installation - 96%
Insulation of facades - 97%
Decoration of facades - 96%
Roofing - 94%
Incoming group - 77%

LCD «Ozerny Gai Gatne»

House number 2
Interior decoration - 99%
Improvement of the adjoining territory - 99%

House number 3
Improvement of the adjoining territory - 99%

House No. 4
Interior decoration - 98%

House No. 5
Interior decoration - 91%
Shrinkage - 99.8%
Facade - 99.8%

House number 6
Monolithic works:
2nd section, 7th floor - 5%
3 section, 7 floor - 50%

House No. 9
Rubbing Pillow - 50%

LCD «Tradition»

House number 2
Permanent finishing of apartments is being actively pursued.

House number 4
Vertical element of 11th floor, ceiling plate of 12th floor.
Laying - 5th floor and basement.

LCD «Malakhit»

House No. 4
Section 401 - Masonry - 20-25th floor.
Section 402-403 - facade work - 98%
Section 403 - Pure finishing - 2-8 th floor.
Section 405-406 - finishing works are carried out - 95%
Facade works - 98%
Works on waterproofing of parking lots are underway. Improvement - Promoters Area - 40%
Works on improvement of the house №4 are carried out - 60%

House number 5
Containment of vertical elements of the ground floor is carried out.

LCD «Nyvky-Park»

House number 3
Work is underway on the installation of window constructions on staircase marches in all sections.
Work is underway on the finishing of the IGC in section Ж - 1 floor, section D - 13 floor and section A - 1 floor.
Work is ongoing on the installation of waterproofing incoming groups.
The work on the facade arrangement ends. Work is underway on improvement.

House number 4
Performed works on the installation of window constructions.
Plastering works in IZK are underway: Section B - 16th floor.
Work is being conducted on the arrangement of external networks.
Work is ongoing on the installation of waterproofing incoming groups.
Lifts are being adjusted.
Work is underway on finishing work and laying of tiles in MZK: Section B - 16 floor, section B - 16 floor.
Works on the installation of doors - Section B - 16th floor
Plasterboard and painting works are conducted in lobbies of 1 floors of sections E, B, V.

House number 5
A laying on 8, 9, 11, 12 floors of section A is carried out; sections E - on 9, 10, 11, 12 floors and basement; section B - 7, 8, 10, 11 floor and basement.
Works on waterproofing of basements of sections A, B and E are underway.
Work is being carried out on the backfill of the foundation pit.
Works on installation of windows are underway: 3-6 floors in sections A, B and E.

House number 6
Arrangement of the floor slab of the 13th floor on section G.
Arrangement of the floor slab floor 13 on the section E.
Arrangement of vertical elements of the 13th floor on section D *.
Masonry is carried out 3-7th floor in section Г; 5, 7, 8 on floors E, 7, 8 floors on section D.

House number 7
Work is underway to install the foundation pit in sections E1, E2.
Work is underway to reinforce the base plate in section B.

House number 8
Work is underway on the arrangement of vertical elements of the basement in section G *.
Works on the arrangement of vertical elements of the basement under Section B **.
Work is underway on the arrangement of vertical elements of the basement in section B.

 

LCD «Otradny»

House number 2
There are finishing works in apartments with finishing (8, 9, 12, 13, 14 floor).

House number 3
Work is underway on the arrangement of roofing works.
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 98% (works are conducted in the base).
Arrangement of plaster walls - 9, 13, 14 floor (apartments).
Work is underway on installation of electrical and plumbing works.
Works are underway to install ceramic tiles at the entrances to the basement floor.
Works are underway to make landscaping.
Work is underway on arrangement of painting works in the IGC from 3 to 16 floor.
Work is underway to install a door on the first floor.

House number 4
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 95%
Work is underway on installation of electrical and plumbing works.
Arrangement of cement-sand screeds on the basement floor.
Work is underway on the arrangement of roofing works.
Arrangement of plaster on 13, 14 floors (apartments with decoration).
Painting works in IZK from 3 to 16 floor.
Arrangement of ceramic tiles on the 17th floor (IZK).
Work is underway to install apartment doors.
Works are underway to make landscaping.

House number 5
Works on installation of metal-plastic windows are underway - 92%
Work is being conducted on the arrangement of external networks.

LCD «Teremki»

1 queue Work is carried out on insulation of the house. Works on painting the facade are carried out. Internal engineering and plumbing work are carried out. Installing baskets for air conditioners is underway. Connected to home communication.
2nd stage, 2nd section - waterproofing of the ground floor is performed. Roofing work is carried out. Execution of plaster walls in apartments on the 11th floor. Expansion of electricity on the 13th floor.
Filling the floor screed on the 2nd floor. Work is carried out on insulation of the house.
2nd stage, 3rd section - installing windows from 22 to 25 floor. Warming up the roof of the house. Execution of plaster walls in apartments on the 11th floor. Expansion of electricity on the 13th floor.
Filling the floor screed on the 2nd floor.
3rd stage, 4th section - the laying is carried out on the 5th floor, and from 7th to 12th floor inclusive.
3rd stage, 5th section - the overlapping of vertical elements of the 21st floor is performed. Masonry is carried out on floors 3, 9 and 10 inclusive.
3rd stage, 6th section - masonry from 2nd to 10th floor incl.