Dynamics of construction as of 25.01.19

  • 25/01/2019
Tags:

LCD «Volodymyrsky»
Waterproofing - 5-10 floor, base.
Laying - TP, 17, 18, 25 floor.
The arrangement of internal power supply networks is 5-9 floors.
Installation of finishing works MZK - 7%
The arrangement of door structures and hatches is 4-24 floors.
Roofing - 16%
The arrangement of metal fence staircases - 6 floors.
Arrangement of external engineering networks - 18%

LCD «Syretsky gardens»
House 1
Inside, the interior decoration - screed and plaster.

House 2
Windows - 14, 16th floor.

House 3
Laying - 13-15 floor.

House 4
Laying - 1-22 floor, TP.
Windows - 2-14 floors.

House 5
Vertical element of the 1st floor.

LCD «Bright»
House number 6
Works on the arrangement of walls and partitions, masonry (external contour - 96%)
Installation of window constructions - 76%
Sanitary engineering works - 56.3%
Electrical work - 27,4%
Ventilation and smoke removal - 8.3%
Weak systems - 19,8%
Plastering of walls - 43,4%
Screw arrangement - 65.9%
Finishing of IGC - 27.8%
Installation of elevators and start-up and adjustment works - 71.7%
Facade arrangement - 95%
Roof installation - 92.3%
Incoming group - 82.3%
Amenties - 0.7%

LCD Park Lakes
House No. 13
Arrangement of walls, partitions, masonry (internal) - 97%
Installation of window constructions - 98%
Sanitary work - 86%
Electrical work - 74%
Ventilation and smoke removal - 52%
Weak-current systems - 44%
Plaster Wall - 93%
Stacking - 97%
Decoration of IGC - 83%
Installation of elevators and start-up and adjustment works - 90%
Facade installation - 96%
Insulation of the facades - 98%
Finishing facades - 96%
Roofing - 97%
Incoming group - 92%


LCD «Ozerny Gai Gatne»
House No. 5
Interior finish - 94,5%
Facade - 99.9%
House number 6
Masonry of external and internal walls:
1st floor - internal - 95%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - external - 90%; internal - 70%
5th floor - external 80%; internal - 50%
House No. 9
Basement Walls:
3, 4 sections - 50%
LCD «Tradition»
House number 2
The clean finishing of apartments is being actively pursued.
 
House number 4
Vertical element of the 16th floor, ceiling plate of the 16th floor.
Laying - 5, 6, 7, 8, 9, 10 floor and basement.
Extranets - 7%
 

LCD «Malakhit»
House number 4
Section 401 - Masonry - on the roof - 90%
Windows - 99%
Finishing works 1-19 floor.
Facade works - 25%
Improvement - promenade area - 40%

House number 5
Vertical element of the 2nd floor.

LCD «Nyvky-Park»
House number 3
Work is under way to start the heat supply.
Transfer of apartments to investors.

House number 4
Lifts are being adjusted.
Work is ongoing on the finishing of apartments with renovations.
Finished works on the facade arrangement.
Work is underway on installation of window drafts and baskets for air conditioners.

House number 5
Masonry is carried out: in the basement, on 8, 11, 12, 13, 14, 16 floors and the roof of Section A; on 9, 11 floors and basement section E; on the 8th and 11th floor of Section B.
Work is being done on the laying of Vent. shafts on roof sections B and E.
Works on waterproofing of basements of sections A, B and E are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are underway: 7-9 floors in sections A, B and E.

House number 6
Arrangement of parapets on section G.
Arrangement of parapets in Section E.
Arrangement of the floor slab floor 17 on the section D *.
Masonry is carried out: 4, 5, 7 floor and basement in section Г; 5, 7, 8 floor on section E; 1, 7, 8 floor on section D *.
Works on waterproofing basements are underway.
Work is underway on the backfill of the foundation pit.
Works on installation of windows are underway: 4-6 floors in sections G, E, D *.

House number 7
Works on arrangement of vertical elements of the basement under section E2 are underway.
Work is carried out on the arrangement of vertical elements of the basement in section E1.
Works on the arrangement of vertical elements of the basement under section B.

House number 8
Work is underway on the installation of a floor slab of 3 floors in section G *.
Work is underway on the arrangement of the floor slab of the 3rd floor in section B **.
Work is underway on the arrangement of vertical elements of the 3rd floor in section B.
LCD «Otradny»
House number 3
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 98%
Work is being carried out on installation of electrical and plumbing works - ground floor, ITP, electrical and machine division, installation of fixtures.
There are finishing works on 4, 5, 8, 9, 13, 14 floors (apartments with repair).

House number 4
Installation of metal-plastic windows - 98%
Works on the arrangement of facades - 95%
Work is underway on installation of electrical and plumbing works - a socle.
There are finishing works on 4, 5, 8, 9, 13, 14 floors (apartments with repair).

House number 5
Works on installation of metal-plastic windows - 95%
Work is underway to install plaster on the 9th floor (apartments with repair).
Work is carried out on the arrangement of electrical installation and plumbing works from 6 to 10 floor.
Installation of equipment for passenger and freight elevators.


LCD «Akadem-Kvartal»
House number 1
Vertical element of the 17th floor, ceiling plate of the 16th floor.
Laying - 1, 2, 3, 4 floor.

House number 2
Vertical element of the 18th floor, floor slab 17th floor.
 
LCD «Teremki»
1 queue
Work is being done on painting the facade.
Internal engineering and plumbing work are carried out.
Installing baskets for air conditioners is underway.
Connected to home communication.
Repair works on the 4th floor are underway.
2nd line, 2nd section
Roofing works are being performed.
Work is carried out on insulation of the house.

2nd stage, 3rd section
Roofing works are being performed.
Filling the floor screed is 7th floor.
3rd stage, 4th section
Masonry from 13th to 19th floor is underway.

3rd turn, 5th section
Overlapping of vertical elements of the 25th floor is underway.
Masonry from 11 to 18 floor is underway.

3rd turn, 6th section
The overlap of vertical elements of the 24th floor is underway.
Masonry from 9 to 15 floor is underway.