Progress of construction as of 25.10.18

  • 25/10/2018

RC "Volodymyrskyi"

Pouring of vertical structures over the 23d floor is completed.
Brickworks at the basement and on 2, 4, 9, 10, 11, 12, 13, 14 floors are ongoing. 
Works on installation of concealed wiring on typical residential floors inside monolith structures are in progress. 
Installation of internal heating network and ventilation, internal water supply network and sewage, low-current networks, smart-home system, screed, wall plaster, decoration of GUPs – 5th floor.


RC “Syretski Sady” 

Building No. 1
Completion of installation of windows and balconies – 95%.
Plumbing works –water supply, sewage and heating risers are completed; installation works inside apartments are ongoing; heating devices and sanitary ware have been installed – 4-6 floors) 
Electric wiring – all installation works prior to plastering have been completed (outlets etc.) – section 2- 95%
Plastering works – 90%.
Façade – heat insulation of walls – 65%. Decorative finishing works – 35%.
Entrance groups – basements are completed

Building No. 2 
Brickworks – 1st to 14th floor.

Building No. 3 
Installation of frame structures – 1-15 floors

Building No.4
Installation of frame structures – 1-22th floor
Brickworks – 1st to 12th floor.
Windows – 2nd to 5th floor.

Building No.5
Testing of pile field is completed

RC “Yaskravyi”

Building No.6 
Works on installation of walls, partitions, brickworks (external -90%, internal – 75.8%) are in progress. 
Installation of window structures-76%
Plumbing works –36.6%
Electric wiring works – 13.2%
Ventilation and smoke exhaust system – 2.8%
Low-current systems – 3.7%
Wall plastering – 13.6%
Installation of screed – 15.1%
Decoration of GUPs – 5.9%
Installation and adjustment of elevators– 70%
Façade works – 36.3%
Roofing – 88.3%
Entrance group – 30%

Building No. 7 
Plumbing works – 94%
Electric wiring works – 86%
Ventilation and smoke exhaust system – 91%
Low-current systems – 93%
Finishing of GUPs – 96%
Installation and adjustment of elevators – 86%
Brickworks on the roof – 1%
Development of adjoining territory – 82%

RC “Parkovi Ozera” 

Building No. 12 
Decoration works inside apartments.

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96% 
Plumbing works – 44%
Electric wiring works – 37%
Ventilation and smoke exhaust system – 22%
Low-current systems – 17%
Wall plastering – 63% 
Installation of screed -70% 
Finishing of GUPs – 10%
Installation and adjustment of elevators – 10%
Façade works – 82 %
Façade heat insulation 91%
Façade finishing – 84%
Roofing – 69%.
Entrance group – 52%

RC “Ozernyi Hai Gatne” 

Building No.2
Internal decoration -99%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration - 92%.

Building No. 5
Internal decoration - 89%.
Glazing – 98%
Façade – 98%

Building No.6
Monolith works : 
Section 1: 4th floor – 70%
Section 3: 5th floor - 40%

Building No.9
Excavation works for the basement – 70%

RC “Traditsiya” 

Building No.2
Active finishing works inside apartments are ongoing. 

Building No.4
Vertical structure element of the 9th floor, slab over the 9th floor are in progress. Brickworks – 3d floor and basement.

RC “Malakhit”

Building No.4
Section 401 – slab over the 25th floor is being poured. Brickworks on 10-23 floors.
Sections 402 - 403 –  facade works – 85%. 
Sections 403 – finishing works – 2-8 floors
405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-13 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 95%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 35%.
Works on development of the territory of building No.4

Building No.5
Arrangement for the pile field - 60%

RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases of all sections is in progress.
Finishing works at GUP: section Ж – 1st floor, section Г – 8th floor and section Д – 1st floor. 
Installation of external mains is in progress.
Water proofing of entrance groups is in progress.
Façade works are ongoing. Works on development of adjoining territory are ongoing.

Building No.4
Plastering works at GUPs: B – on the 16th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing. 
Adjusting of elevators is in progress.
Finishing works and tiling at GUP: section Б – on the 15th floor, section В – on the 14th floor.

Building No.5
Installation of monolith frame
section Б – parapet installation – 50%, 
Brickworks on the floors 7, 8, 9, 10, 11 of section A; section Е - 
on the 8, 9, 11 floors and basement. Section Б - on the 1, 7, 9 and 10 floors. Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of the slab over the 11th floor at section Г
Installation of the slab over the 11th floor at section E.
Installation of vertical elements of the 11th floor at section Д*
Brickworks on the 3, 4, 5, 6, 7  floors in section Г; on 4, 5, 6, 7 floors in section Е and on 4, 5, 6, 7 floors in section Д *.

Building No.8
Installation of vertical elements of the basement at section Г *
Works on installation of vertical elements of the basement at section Б **.
Reinforcement of the basement at section B is in progress.
Works on installation of tower crane are in progress.


RC “Vidradnyi” 


Building No.2 
Decoration works inside “turn-key” apartments 
(6, 7, 8, 9, 13, 14, 15, 16 floors).

Building No.3 
Roofing works – 70%
Installation of metal and plastic windows - 95%.
Façades works are in progress  – 90% (works on the roof and cold passes)
Installation of cement and sand screed is in progress on the 1st floor.
Wall plastering on the 13th 14th floors (GUPs) is ongoing.
Works on electric wiring and plumbing are in progress.
Works on laying ceramic tiles at GUPs (3, 4, 6 and 8 floors)
Territory development works are in progress.
Painting works at GUPs (2, 5, 7 floors) are going.

Building No.4 
Installation of metal and plastic windows – 95%
Façades works are in progress – 85%
Works on electric wiring and plumbing are in progress.
Installation of cement and sand screed on the 7th floor is in progress.
Roofing is in progress.
Wall plastering at basement floor – 98%
Wall plastering on 4, 14 floors (turn-key apartments).

Building No.5 
Brickworks on the 16th floor, basement and roof are in progress.
Works on installation of metal and plastic windows are ongoing – 75%.
Façade works are ongoing. 


RC “Teremky” 

1st stage - Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are ongoing. Painting of the façade is ongoing. Internal mains and plumbing works are in progress. 
Wall plastering of GUPs  on the 1st floor. Pouring of screed  - 20-21 floors. Installation of basket holders for air conditioner units.
Stage 2, section 2 – Installation of windows on 24, 25 floors inclusive. Water-proofing of the basement is ongoing. Roofing works are in progress. Electric wiring works on the 4th floor are in progress.
Stage 2, section 3 – Installation of windows on the 19th floor.
Heat insulation of the roof is ongoing. Electric wiring works on the 3d floor are in progress. Wall plastering works inside apartments on the 4th floor. Water-proofing of the basement is ongoing.

Stage 3, section 4 - Brickworks on the floors from the 4th to 10th inclusive are ongoing.
Stage 3, section 5 – slab over the vertical elements of the 19th floor is in progress. Brickworks on 2, 3, 9,10 floors inclusive are in progress.
Stage 3- section 6 – slab over the vertical elements of the 18th floor is in progress. Brickworks on 2nd to 8th floor are in progress.