Dynamics of construction as of 29/03/19

  • 29/03/2019

LCD "Academ-Quarter"

House number 1
Floor slab 22 floors.
Masonry - 10th floor.
House 2
Floor slab of the 22nd floor, vertical element of the 23rd floor.
Masonry - 6th floor.

LCD "Vladimirsky"

Waterproofing device - 28%
Masonry - TE, 3, 4, 19, 23, 24 floor.
Electrical work - 7% (floor 5-11).
Ventilation and smoke removal - 12% (1-11 floor).
Plumbing works - 24% (1-16 floor).
The device finishing works MOP - 37% (13, 14 floor).
Door construction device - 45% (floor 4-24)
Installation of elevator equipment - 47% (1-24 floor).
Roof installation - 25%
The device window designs - 5-16 floor.
Facade arrangement - 26%

LCD "Malachite"

House number 4
Finishing works - 1-23 floor (finishing).
Facade work - 75%
Improvement - promenade area - 40%

House number 5
Vertical element of the 11th floor.
Masonry - 1-4 floor.
Waterproofing cap.

LCD "Nyvky Park"

House number 5
The laying is carried out on the 14th, 15th, 16th floors of section A; on 9, 11, 14, 16, 17 floors of section E; - 8, 12-15, 17th floor of section B.
Laying vent mines on the roof of sections B.
Works on waterproofing the basements of sections A, B and E.
Work is underway on backfilling the excavation.
The installation of windows is in progress: floor 14–17 in section A, floor 11–14 in sections B and E.
Work is underway on laying the cable of the fire safety system: Section E - 4-15 floors, Section B - 3-13 floor, Section A - 8-17 floor.
Finishing work is underway in sections A, E, B– basement, 2-5 floor.
Work is underway on the construction of the roof on section A, B and E.
Work is underway on the device facade.
Work is underway to connect the engineering networks.
Work is underway on the construction of the pit under the TE.

House number 6
The laying is carried out 7, 9, 10, 11, 12, 13, 15 floor and a roof on section G; on 1, 7, 9, 10, 11, 12, 14, 15th floor in section E; on 10, 11, 12, 13, 14 floor and basement in section D.
Work is underway on waterproofing basements.
Work is underway on backfilling the excavation.
Work is underway on the installation of windows: 5-8 floor sections G, E, D.
Finishing works are underway on the 3-4 floor of section D, D and E.
Work is underway on the device screed: Section B - 4th floor.
Work is underway to connect the engineering networks.

House number 7
Work is underway on the construction of the floor slab of the 3rd floor of section E2.
Work is underway to arrange the vertical elements of the 3rd floor of the E1 section.
Work is underway to arrange the vertical elements of the 3rd floor in section B.
The device of a waterproofing of cellars on the sections B, E1, E2.

House number 8
Work is underway on the arrangement of the floor slab of the 8th floor in section G.
Work is underway to arrange the vertical elements of the 8th floor in section B.
Work is underway on the arrangement of the floor slab of the 7th floor in section B.
The device of waterproofing basements on sections G, B, B.

LCD "Lake Guy Hatne"

House number 5
Interior finish - 96.9%
Entrance groups - 98%
Facade - 99.9%
House territory - 52%

House number 6
Masonry exterior and interior walls:
1st floor - internal - 97%
2nd floor - internal 97%
3rd floor - internal 99%
4th floor - internal - 97%
5th floor - internal - 97%
6 floor - internal - 97%
7th floor - internal - 97%
8th floor - internal - 97.5%
9th floor - internal - 97%
Installation of window units: 1 section 3 floor - 80%
Water supply (risers) - 2%

House number 9
Basement:
1, 2 section - 50%
1st floor:
1, 2 section - 2%
2nd floor:
5.6 section - 60%
3rd floor:
3, 4 section - 80%

LCD "Otradny"

House number 3
Installation of plastic windows - 98%
Facade works - 98%
Electrical installation and plumbing works - 95%
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 4
Installation of plastic windows - 98%
Facade works - 95%.
Electrical installation and plumbing works - 95%
Finishing works are being carried out on the 4th, 5th, 8th, 9th, 13th, 14th floors (renovated apartments).

House number 5
Installation of metal windows - 95%
Work is underway on the installation of plaster on the 12th, 16th floor.
Installation of equipment for passenger and freight elevators.
Work on the device ventilation - 85%
Work is underway to arrange facades from the 2nd to the 16th floor.
The device is a cement-sand screed on the 16th floor.
Warming of the staircase with mineral wool - up to the 16th floor.
Work on the facade insulation on the roof - 90%

LCD "Park Lakes"

House number 13
Plumbing works - 95%
Electrical work - 88%
Ventilation and smoke removal - 80%
Low-voltage systems - 65%
Installation of elevators and commissioning - 97%

Residential complex "Syretsky Gardens"

House number 1
In the work of interior decoration - paint brushes.

House 2
Windows - 14, 16th floor.
Plaster, screeds - section 3, 2, 1 - work started.
Facade insulation -10%

The House 3
Masonry - 13-16 floor.

House 4
Windows - 2-22 floor.
Facade insulation - 15%
Roof installation - 10%

House 5
Vertical element of the 10th floor.
Masonry - 3rd floor.

Residential complex "Teremki"
1st turn
Work on the painting of the facade.
Internal engineering and plumbing works are being carried out.
Connection of communications to the house is made.
Repair work in progress:
- tile: 23 floor.
- Wallpaper: 13, 19, 24 floor.
- laminate floor: 9th floor.
2nd stage, 2nd section
Roofing work is underway.
Plastering of walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors is carried out.
Filled floor screed from 2 to 22 floor.
Plaster walls in common areas from 3 to 25 floor.
Work on the insulation of the house.
Painting of MOP ceilings from 4th to 15th floor.
Installation of elevators.
2 stage, 3 section
Roofing work is underway.
The plastering of the walls in the apartments on the 3rd and 4th floors, 9 and 11, 13, 14, 18, 19, 23 and 24 floors.
Filled floor screed from 2 to 22 floor.
The plastering of the walls in the common areas from the 3rd to the 25th floor was completed.
Work on the insulation of the house.
Installation of elevators.
3rd stage, 4th section
The laying is carried out - 22-24 floor.
Windows - 5-6 floor.
3 stage, 5 section
The laying is carried out - 22-24 floor.
Windows - 8th floor.
3rd stage, 6th section
Overlapping roof of the house.
The laying is carried out on the 23rd floor.
Windows - 7-8 floor.

Residential complex "Tradition"

House number 4
Vertical element of the 21st floor, floor slab of the 21st floor.
Masonry - 12-17 floor and basement.
External networks - 55%
Plaster - 2-4, 6, 8 floor.
Electricity - 2-6 floor
Sewerage (risers) - 30%
Paint brushes - 2-3 floor.
Couplers - 2, 5 floor.

LCD "Yaskravy"

House number 6
Installation of window designs - 90%
Plumbing works - 83.1%
Electrical work - 55%
Ventilation and smoke removal - 56.7%
Low-voltage systems - 38%
Plaster walls (apartments) - 59.8%
Screed device - 98%
Finishing MOS - 87.8%
Installation of elevators and commissioning - 85%
Facade arrangement - 96.3%
Roof installation - 96%
Entrance group - 87.7%
Improvement - 4%