Dynamics of construction of residential complexes

  • 05/12/2016

As of December 5, 2016, construction of facilities is carried out in strict accordance with the declared dates for the construction of residential complexes.

Residential complex "Park Lakes"

The following works are being carried out in house 11:

The device is a monolithic frame - the work was performed at 59% (the level of the 16th floor, the crane capacity).

The construction of external walls and partitions is made on 27% - 4,6,7 floors.

The structure of the internal walls and partitions is made on 27% - 4,6,7 floors.

In house number 12:

The device is a monolithic frame on the 1st floor. Waterproofing basement.In house number 13:

Pile test in progress.

Residential complex "Demeevka"

The following works are being carried out in house No. 1:

- roofing: laying insulation and screed 100%, waterproofing - 80%;

- arrangement of walls and partitions: 99%, air ventilation shafts - 100%;

- installation of window structures: 99%;

- device of the facade: wall insulation and decoration of the facade, laying of ceramic-granite tiles is carried out - the works are 70% completed;

- plaster walls: 99%;

 - plumbing works (piping and heating): Section 1: 2‒20 floors - 100%; Section 2: 2‒14, 16‒20 floors - 100%.

- screed, section No. 1: 1‒14, 16‒17 floors - 100%, section No. 2: 2‒10, 12, 13, 14, 16, 17, 19, 20 - 100%;

- installation of doors: section 1: 2‒14, 16 - 100%; Section 2: 2‒10, 12‒14, 16‒17, 19‒20 - 100%;

- electrical work: 2‒20 floors - 100%;

- ventilation system: installation of ventilation. blocks - 60%, smoke removal - 97%;

- fire alarm - 40%, fire system in the parking lot - 70%;

- installation and commissioning of elevators: elevators are mounted, commissioning is under way;

- arrangement of public places: section No. 1: 2‒12 floors (decorative finishing of walls and ceilings, tiles on the floor) - 100%, section No. 2‒13 floors (decorative finishing of walls and ceilings, tiles on the floor) - 100%;

- 301 section - 50%;

- 302‒303 sections - 92%;

- 304 section - 50%.

Base waterproofing device:

- 301 section - 98%;

- 302‒303 sections - 98%;

- 304 section - 82%.

The device walls and partitions:

- 301 section - 18%;

- 302‒303 sections - 43%;

- 304 section - 19%.

Backfilling:

- 301 section - 85%;

- 302‒303 sections - 65%;

- 304 section - 40%.

Residential complex "Yaskravy"

The following works are being carried out in house No. 4

- brickwork done at 98%;

-installation and commissioning of elevators - 72%;

- roofing - 70%;

- device facades - 35%;

- device of metal-plastic windows - 94%;

- final finishing of public places - 28%;

- installation of the ventilation system - 69%;

- internal power supply system - 75%;

- internal heating system - 73%;

- internal water supply and sewage systems - 74%;

- installation of a fire alarm system - 29%;

- low-voltage systems - 19%;

- the device of on-site networks - 37%.

In house number 5:

The monolithic frame device is 88% complete (level of 24 floors). Brickwork done at 33%. The device ventilation channels - 60%.

In house number 7:

The device of the pile section number 2 is 100% complete.

Residential complex "Lake Hai Hatne"

In the house №1 the following works are performed:

- basement waterproofing - 90%;

- backfilling - 80%;

- roofing - 50%;

- brickwork - 95%;

- installation of windows - 95%;

- device facade - 45%;

- plumbing work - 40%;

- screed - 33%;

- installation of doors - 10%;

- electrical work - 40%;

- ventilation and smoke removal - 100%;

- installation and commissioning of elevators - 80%;

- gas network - 35%;

-final finishing of public places - 35%;

- landscaping - 15%.

Residential complex "Nyvki-Park"

The following works are being carried out in house No. 1:

Base waterproofing device:

Section "A" - 95%, section "B" - 95%, section "B" - 90%.

Backfilling:

Section "A" - 95%, section "B" - 95%, section "B" - 90%.

Device monolithic frame:

Section "A" - 50% (10th floor), section "B" - 30% (10th floor), section "C" - 100% (9th floor).