Dynamics of construction of residential complexes on the 24-th of September, 2015

  • 24/09/2015

We inform that on the 24-th of September, 2015, the construction of facilities is carried out in strict accordance with the construction schedule.

Dynamics of construction of the residential complex "Park Lakes"

In the house number 9 is laying from 16 to 25 floor; front works: warming by mineral wool; plaster - on the 11th floor; screed - 5th floor; fire alarm installation - 10th floor; glazing - on the 25th floor; Sewer risers - 12th floor.

In House No. 10, monolithic frame works are being carried out on the 23rd floor, brickwork on the 8th floor, and interior work in the showroom on the 2nd floor.

Dynamics of the construction of the residential complex "Tradsia"

The following works are being carried out in House No. 1:

- monolithic frame works: the overlap of 23 floors;

- brick masonry 14, 16 floors;

- installation of windows on the 6th floor;

- putty ceilings and installation of doors on the 2nd floor.

Dynamics of construction of the residential complex "Malachite"

The following works are carried out in House No. 2:

- brickwork - 26th floor in work;

-plastering 22‒25 floors;

- screed on the 17th floor;

- metal-plastic structures are set at 99%;

- electrical work: 23‒25 floors in work;

- works on the facade (3 sides of the facade) are completed by 90%;

- installation of apartment doors on the 16th floor;

-installation of elevators is 98%;

- Roof: waterproofing layer is made;

- fine finishing is performed in MOPs on the 9th floor;

- laying tiles on the 8th floor;

- supply to the house of electrical networks;

- dismantling of the tower crane;

- connection of the heating main to the urban networks;

- supply to the home low-voltage systems.

Dynamics of construction of a residential complex on prospect K. Komarova, 46

The following works are being carried out in House No. 1:

- installation of doors: 16th floor in work;

- installation of internal heating systems: 15‒16 floors in operation;-

fire alarm installation: wiring is 100% complete;

- plaster: the 11th floor is 100% completed, 12-15 floors are in operation, 16-18 floors are 100% completed;

- roof: the first layer is 100%;

- The device and the painting of the facade are 90% complete;In the house number 2:

- door installation: 13‒14 floors;

- installation of internal heating systems: 16th floor;

- fire alarm installation: wiring is 100% complete;

- plaster: the 11th floor is 100% completed, 12-15 floors are in operation, 16-18 floors are 100% completed;

- roof: the first layer is 100%;

- The device and the painting of the facade are 90% complete;

- repairs in apartments: from 3‒9 floor performed by 85%.