In February, the Intergal-Bud company maintained an active pace of construction of all its facilities. Monolithic and masonry works, installation of engineering systems, decoration of facades and public areas are ongoing at the sites. At the same time, two complexes - Teremky and Syretski Sady residential complexes - have entered the final stage of work before putting the buildings into operation.

For more details on the progress of construction work at Intergal-Bud facilities, see our monthly report:

Syretski Sady residential complex, address: 10D Ivan Vyhovsky St.

A modern comfort-class residential complex with the concept of a "city within a city". Combines a convenient location in a green part of Kyiv and its own infrastructure.

House No. 10

  • Installation of window structures - 93%
  • Entrance groups - 100% readiness
  • Roofing arrangement - 85%
  • Engineering - 61%
  • Heating - 83%
  • Fire safety - 65%
  • Facade arrangement - 87%
  • Finishing (without apartment renovation) - 100% readiness
  • Finishing of MZK - 100% readiness
  • Installation and commissioning of elevators - 95%
  • Frame arrangement entrance groups – 100%
  • Arrangement of landscaping with finishing of entrance groups and fences - 15%.

BFK INTERGAL CITY, address: 16B Staronavodnytska St.

The premium multifunctional complex combines elegance, technological sophistication and a unique location in Pechersk - the center of business, cultural and investment life of the capital.

Tower A

  • Masonry - 99%
  • Installation of hinged ventilated facade systems (HVF) - 95%, SPOK (facade) - 95%
  • Installation of internal plumbing networks: K1 - 99%, K2 - 98%, T1/T2 - 95%, B1 - 95%
  • Installation of ventilation systems - 85%
  • Installation of air conditioning systems - 60%
  • Installation of fire extinguishing systems - 72%
  • Installation of SKD and SKS systems - 80%
  • Screed and plaster in apartments - 75%
  • Electrical installation work - 85%
  • Boiler room installation - 55%
  • Terrace covering - 20%
  • Installation of ITP and heating modules - 80%
  • Installation of doors to apartments - 15%
  • Finishing work of technical floors (23-25 ​​floors) - 40%
  • Engineering premises: electrical panel - 50%, pump room - 60%
  • Finishing of common areas - 5%

Tower B

  • Masonry - 80%
  • Internal plumbing works - 64%
  • Screed - 10%

Tower B

  • Masonry - 80%
  • Internal plumbing works - 65%

Tower G

  • Masonry - 75%
  • Installation of metal structures - 50%
  • Installation of ventilation blocks - 25%

Tower D

  • Monolithic works - 95%
  • Installation of NVF and SPOK systems (facade) - 55%

Building 6

  • Monolithic works - 50%

Stylobate

  • Monolithic works - 85%

Office slope

  • Monolithic works - 90%

Parking

  • Finishing works (sandblasting) - 75%
  • Dismantling works - 60%

Supports walls

  • PS-19 - 100%
  • PS-2 - 5% (installation of the tongue and groove - 80%)
  • PS-1 - 90%

External networks

  • B1 - 50%
  • K1 - 50%
  • K2 - 55%

Polar Park residential complex, address: Kyiv, st. Petro Kalnyshevsky, 2

A large-scale comfort-class residential, commercial and office complex in the Obolonsky district of Kyiv, which involves the construction of five buildings with a stylobate part and parking. Combines a convenient urban location with a well-thought-out internal infrastructure.

House 1

  • Installation of a monolithic frame - 67%
  • Installation of walls and partitions - 50%
  • Installation of ventilation ducts and stairs (prefabricated) - 53%
  • Installation of metal-plastic structures - 19%

House 2

  • Installation of a monolithic frame - 48%
  • Installation of walls and partitions - 22%
  • Installation of ventilation ducts and stairs (prefabricated) - 40%

House 3

  • Installation of monolithic frame - 29%
  • Installation of walls and partitions - 10%
  • Installation of ventilation ducts and stairs (prefabricated) - 3%

Parking

  • Installation of foundation slab completed - 100% readiness
  • Installation of monolithic frame of parking lot - 31%

CITY HUB residential complex, address: st. Mokra, 8-10

A residential complex that harmoniously combines the comfort of city life and the coziness of personal space. For the comfort of residents, spacious apartments, underground parking, children's and sports grounds, as well as a developed own infrastructure are available.

House 2

  • Installation of a monolithic frame - 100%
  • Installation of low-current systems and electricity - 100%
  • Installation of external brick walls - 96.5%
  • Installation of metaplastic windows and doors - 96.5%
  • Plumbing work in the basement, apartments and common areas (water supply, sewage, heating) - 63%
  • Electrical installation work (apartments, MZK, basement) - 63.6%
  • Wall decoration of common areas and apartments – 95%

Parking

  • Installation of a monolithic frame for the parking lot – 88%
  • Installation of waterproofing for the parking lot - 87%
  • Installation of drainage under the parking lot slab of building 2 - 90%
  • Installation of the foundation - 87%
  • Installation of brick walls and partitions: building 2 – 67%, building 1 -100%

Sky Avenue residential complex, address: Svyatoslav Khorobryho St., 3

Comfort+ class complex, located next to Sevastopol Square. The project includes 6 residential buildings with commercial premises on the first floors and cozy courtyards with children's and sports grounds and recreation areas.

House No. 3

  • Installation of waterproofing of the basement underground part - 55%
  • Installation of entrance groups - 75%
  • Installation of external walls made of ceramic blocks - 55.45%
  • Installation of internal walls and partitions made of ceramic blocks - 51.6%
  • Installation of metal-plastic windows and doors - 24.5%
  • Installation of small metal structures - 84.71%

Parking lot No. 2 (under house No. 3)

  • Installation of the foundation - 85%
  • Installation of a monolithic frame for a parking lot - 75%
  • Installation of waterproofing for a parking lot - 5%
  • Backfilling - 5%

Teremky Residential Complex, address: 15 Akademika Zabolotnogo St.

A comfort-class complex surrounded by forests and parks, with modern layouts and its own developed infrastructure, 5 minutes from the Teremky metro station.

Building No. 5

  • Decoration of common areas - 97%
  • Installation of ventilation and smoke exhaust - 92%
  • Internal heating system - 92%
  • Internal water supply and sewage system - 91%
  • Internal power supply system - 90%
  • Installation of fire protection systems - 91%

Parking

Part 1-2:

  • Installation of internal water supply and sewage engineering - 92%
  • Installation of internal ventilation network - 91%

Part 3-4:

  • Installation of internal water supply and sewage engineering - 91%

Part 5:

  • Installation of internal water supply and sewage engineering - 91%
  • Installation of internal ventilation network - 90%

Part 6: