Dynamics of construction of Intergal-Bud facilities for June 2026

The development company "Intergal-Bud" maintained a high pace of construction at all its facilities in June.

Various works are underway at all construction sites: monolithic, facade, engineering, installation of internal networks, landscaping, interior decoration, etc.

The key achievement of the month was obtaining the occupancy certificate and the official postal address for Building No. 10 of the Syretski Sady residential complex.

We are also starting to share the dynamics of the construction of a new large-scale project on the left bank of Kyiv - Kaskad Residence.

More details about the construction progress are in the monthly report.

Polar Park residential complex, address: Kyiv, Petro Kalnyshevsky St., 2

A large-scale comfort-class residential complex in the Obolonsky district of Kyiv. It involves the construction of five buildings with a stylobate part, which will house various infrastructure facilities and underground parking with shelter. The complex combines a convenient urban location, transport accessibility and well-thought-out internal infrastructure.

House No. 1:

  • Installation of a monolithic frame – 99%
  • Installation of walls and partitions – 88%
  • Installation of ventilation ducts and stairs (prefabricated) – 100%
  • Installation of metal-plastic structures – 59%
  • System of internal heating networks – 32%
  • Internal heating system – 24%
  • Internal power supply system – 34%

House No. 2:

  • Installation monolithic frame – 86%
  • Installation of walls and partitions – 48%
  • Installation of ventilation ducts and stairs (prefabricated) – 78%
  • Installation of metal-plastic structures – 22%

House No. 3:

  • Installation of monolithic frame – 70%
  • Installation of walls and partitions – 29%
  • Installation of ventilation ducts and stairs (prefabricated) – 64%

Parking:

  • Installation of monolithic parking frame – 70%

City Hub Residential Complex, address: 8-10 Mokra St.

A residential complex that harmoniously combines the comfort of city life and the coziness of personal space. For the comfort of residents, spacious apartments, underground parking, children's and sports grounds, as well as its own developed infrastructure are available. Scheduled completion of construction – III quarter.

Building 2:

  • Roofing installation – 52.5%
  • Facade installation – 75%
  • Waterproofing of the basement underground part – 91%
  • Installation of metaplastic windows and doors – 99%
  • Installation of the electrical panel – 95%
  • Plumbing work in the basement, apartments and common areas (water supply, sewage, heating) – 75%
  • Ventilation and smoke extraction – 83%
  • Electrical installation work (apartments, MZK, basement) – 95%
  • Fire protection system – 50%
  • Installation and commissioning of elevators – 92%
  • Installation of small metal structures – 75%
  • Installation of an Individual Heat Point – 30%
  • Landscaping and landscaping – 24.5%

Parking lot of building 2:

  • Installation of waterproofing of the parking lot – 80%
  • Installation of entrance groups – 82%
  • Installation of brick walls and partitions – 100%
  • Electrical installation works – 76%
  • Installation of electrical panel – 99%
  • Plumbing works – 65%
  • Ventilation and smoke extraction – 80%
  • Installation of parking floor coverings – 60%
  • Fire protection system – 20%
  • Installation of metal doors, gates – 99%
  • Installation of metal-plastic windows – 90%
  • Landscaping and landscaping – 25%

Sky Avenue Residential Complex, address: st. Svyatoslav Khorobryho, 3

Comfort+ class complex, located next to Sevastopol Square. The project includes 6 residential buildings with commercial premises on the first floors and cozy courtyards with children's and sports grounds and recreation areas.

Building No. 3:

  • Installation of waterproofing of the basement underground part – 56%
  • Installation of entrance groups – 85%
  • Installation of external walls made of ceramic blocks – 81%
  • Installation of internal walls and partitions made of ceramic blocks – 79%
  • Installation of metal-plastic windows and doors – 55%
  • Installation of small metal structures – 86%
  • Electrical installation works (apartments, MZK, basement) – 36%
  • Roofing – 42%
  • Installation of elevator equipment – ​​25%

Parking lot No. 2 (under building No. 3):

  • Installation of parking lot waterproofing – 35%
  • Backfilling – 50%

Children's educational institution:

  • Installation of frame – 100%
  • Performance of waterproofing of external walls – 95%
  • Installation of backfilling – 90%

Kaskad Residence residential complex, address: 5A Prychalna St.

Comfort-class complex, located just 200 meters from the Dnieper River. Combines cascading architecture, a closed territory, developed infrastructure, complete autonomy and energy independence. All apartments are transferred to buyers in White Box format.

Section 1:

  • The excavation, pile field, foundation and underground part of the frame have been installed, which according to the project will serve as a dual-purpose structure (shelter).
  • Further work on installing the frame above the 0 mark is ongoing.

Section 2:

  • The excavation has been installed.
  • Work on installing the pile field is being completed.
  • Installation of the tower crane is in progress.
  • Foundation has begun.

BFK INTERGAL CITY, address: st. Staronavodnytska, 16B

Premium multifunctional complex that combines elegance, futuristic architecture, technologicality and a unique location in Pechersk - the center of business, cultural and investment life of the capital.

Tower A:

  • Installation of hinged ventilated facade systems (HVF) - 99%, SPOK - 98%
  • Installation of internal plumbing networks: K1 - 99%, K2 - 99%, T1/T2 - 98%, B1 - 98%
  • Heating mains with combs - 90%
  • Installation of ventilation systems - 90%
  • Installation of air conditioning systems – 99%, installation of block equipment – ​​10%
  • Installation of fire extinguishing system – 90%
  • Installation of SKD and SKS systems – 90%
  • Screed in apartments – 99%
  • Plastering of apartments – 99%
  • Electrical installation works – 92%
  • Installation of boiler room – 95%
  • Covering of terraces – 40%
  • Installation of ITP and heating modules – 95%
  • Installation of doors in apartments – 15%
  • Finishing works of technical floors (23-25 ​​floors) – 90%
  • Engineering premises: electrical panel – 95%, pumping – 95%
  • Decoration of common areas (tiles, wall panels, hatches) – 80%
  • Decoration of walls of common areas – 20%
  • Fireproof penetrations – 80%
  • Installation of terrace fences – 10%
  • Installation of roof metal structures – 90%
  • Internal gas pipeline – 95%

Tower B:

  • Masonry – 80%
  • Internal plumbing works – 70%
  • Installation of heating appliances – 95%
  • Screed installation – 80%
  • Ventilation – 70%
  • Air conditioning systems – 50%

Tower B:

  • Masonry – 95%
  • Internal plumbing works – 85%
  • Installation of heating devices – 95%
  • Screed installation – 92%
  • Installation of SCS systems – 15%

Tower G:

  • Masonry – 85%
  • Installation of metal structures – 100%
  • Installation of ventilation units – 90%
  • Installation of NVF systems – 65%, SPOK (facade) – 70%
  • Concreting – 97%
  • Metal roof structures – 30%
  • Roofing installation – 80%
  • Installation of ventilation systems – 40%
  • Installation of heating systems – 70%
  • Internal plumbing works – 70%

Tower D:

  • Monolithic works – 99%
  • Installation of NVF systems – 61%, SPOK (facade) – 81%
  • Plastering – 30%
  • Screeding – 30%
  • Roofing – 4%
  • Heating system installation – 20%
  • Internal plumbing works – 20%

Building 6:

  • Monolithic works – 50%

Stylobate:

  • Monolithic works – 95%
  • Covering – 40%

Office slope:

  • Monolithic works – 95%

Parking:

  • Finishing works (sandblasting) – 95%
  • Dismantling works – 70%

Retaining walls:

  • PS-2 – 10%
  • PS-1 – 100%

External networks:

  • B1 – 60%
  • K1 – 60%
  • K2 – 60%
  • Gas pipeline – 30%