Dynamics of construction of Intergal-Bud facilities for May 2026
In May, the development company Intergal-Bud continued its active implementation of residential complexes in Kyiv. Monolithic, facade and engineering works, installation of internal networks, landscaping of territories and interior decoration are ongoing at the construction sites.
At the same time, at some facilities, for example, the CITY HUB residential complex, construction is entering the final stages with the launch of engineering systems, installation of elevator equipment and preparation for the completion of key works.
More details about the progress of construction works last month can be found in the latest monthly report.
Polar Park residential complex, address: Kyiv, Petro Kalnyshevsky St., 2
A large-scale comfort-class residential complex located in Kyiv’s Obolon district. The project includes the construction of five residential buildings connected by a stylobate level that will accommodate various infrastructure facilities and an underground parking garage with a shelter. The complex combines a convenient urban location, excellent transport accessibility, and thoughtfully designed internal infrastructure.
Building No. 1:
- Monolithic frame construction – 94%
- Wall and partition installation – 71%
- Installation of ventilation shafts and precast staircases – 94%
- Installation of uPVC windows and door structures – 42%
- Internal water supply and sewage systems – 13%
- Internal heating system – 6%
- Internal power supply system – 10%
Building No. 2:
- Monolithic frame construction – 75%
- Wall and partition installation – 41%
- Installation of ventilation shafts and precast staircases – 51%
- Installation of uPVC windows and door structures – 14%
Building No. 3:
- Monolithic frame construction – 55%
- Wall and partition installation – 20%
- Installation of ventilation shafts and precast staircases – 25%
Parking Garage:
- Monolithic frame construction of the parking facility – 65%
CITY HUB Residential Complex, address: 8–10 Mokra St., Kyiv
A residential complex that harmoniously combines the comfort of urban living with the coziness of private space. Residents benefit from spacious apartments, an underground parking garage, children's and sports playgrounds, as well as well-developed on-site infrastructure. Planned construction completion: Q3.
Building No. 2:
- Roof installation – 52.5%
- Façade works – 60%
- Waterproofing of the underground basement section – 91%
- Installation of uPVC windows and doors – 98%
- Electrical switchboard installation – 95%
- Plumbing works in the basement, apartments, and common areas (water supply, sewage, heating) – 70%
- Ventilation and smoke extraction systems – 80%
- Electrical installation works (apartments, common areas, basement) – 95%
- Fire protection system – 50%
- Elevator installation and commissioning works – 91%
- Installation of minor metal structures – 75%
- Installation of the Individual Heating Substation (IHS) – 22.5%
Parking Garage of Building No. 2:
- Monolithic frame construction of the parking garage – 100%
- Parking garage waterproofing works – 80%
- Entrance group construction – 20%
- Brick walls and partitions construction – 73%
- Electrical installation works – 65%
- Electrical switchboard installation – 90%
- Plumbing works – 65%
- Ventilation and smoke extraction systems – 75%
- Parking garage floor finishing works – 60%
- Fire protection system – 20%
- Installation of metal doors and gates – 20%
- Installation of uPVC windows – 40%
- Landscaping and greening works – 25%
Sky Avenue Residential Complex, address: 3 Sviatoslava Khorobroho St., Kyiv
A comfort+ class residential complex located near Sevastopolska Square. The project includes six residential buildings with commercial premises on the ground floors and cozy inner courtyards with children’s and sports playgrounds, as well as recreation areas.
Building No. 3:
- Waterproofing of the underground basement section – 55%
- Entrance group construction – 75%
- Construction of external ceramic block walls – 73%
- Construction of internal ceramic block walls and partitions – 73%
- Installation of uPVC windows and doors – 50%
- Installation of minor metal structures – 85%
- Electrical installation works (apartments, common areas, basement) – 34%
- Roof installation – 33%
- Elevator equipment installation – 12%
Parking Garage No. 2 under Building No. 3:
- Parking garage waterproofing works – 13%
- Backfilling – 50%
Children’s Educational Facility:
- Frame construction – 100%
- Waterproofing of external walls – 95%
- Backfilling – 90%
INTERGAL CITY Multifunctional Complex, address: 16B Staronavodnytska St., Kyiv
A premium multifunctional complex that combines elegance, futuristic architecture, advanced technologies, and a unique location in Pechersk — the capital’s center of business, cultural, and investment activity.
Tower A:
- Installation of ventilated façade systems (VFS) – 99%, structural glazing system (SGS) – 98%
- Installation of internal plumbing networks: K1 – 99%, K2 – 99%, T1/T2 – 98%, V1 – 98%
- Heating mains with manifold systems – 90%
- Installation of ventilation systems – 89%
- Installation of air conditioning systems – 99%
- Installation of fire suppression systems – 85%
- Installation of access control and structured cabling systems – 89%
- Floor screeding in apartments – 98%
- Apartment plastering works – 98%
- Electrical installation works – 90%
- Boiler house installation – 90%
- Terrace finishing works – 30%
- Installation of the Individual Heating Substation (IHS) and heating modules – 90%
- Apartment entrance door installation – 15%
- Finishing works on technical floors (23rd–25th floors) – 70%
- Engineering facilities: electrical switchboard room – 90%, pumping station – 90%
- Finishing of common areas – 30%
Tower B:
- Masonry works – 80%
- Internal plumbing works – 70%
- Installation of heating appliances – 95%
- Floor screeding – 80%
- Ventilation systems – 70%
- Air conditioning systems – 50%
Tower C:
- Masonry works – 90%
- Internal plumbing works – 70%
- Installation of heating appliances – 95%
- Floor screeding – 85%
Tower D:
- Masonry works – 85%
- Steel structure installation – 100%
- Installation of ventilation blocks – 90%
Tower E:
- Monolithic works – 95%
- Installation of ventilated façade systems (VFS) and structural glazing systems (SGS) – 65%
- Plastering works – 30%
- Floor screeding – 30%
Building 6:
- Monolithic works – 50%
Stylobate:
- Monolithic works – 95%
- Surface finishing works – 25%
- Office Slope Area:
- Monolithic works – 95%
Parking Facility:
- Finishing works (sandblasting) – 75%
- Demolition works – 70%
Retaining Walls:
- RW-2 – 10%
- RW-1 – 100%
External Utility Networks:
- Water supply (V1) – 60%
- Stormwater/sewer network (K1) – 60%
- Sewer network (K2) – 60%
- Gas pipeline – 20%
Other publications
Promotions
Special installment plan for up to 5 years on ready-to-move-in apartments
9/28/2026Promotions
Special installment plan for ready-to-move-in duplex apartments at Sky Avenue
9/25/2026Promotions
Apartments under the “єОселя” program at Sky Avenue. Down payment from UAH 870,000.
9/25/2026News
Building No. 3 has been accredited under the state “єОселя” program with Globus Bank
9/24/2026