Dynamics of Intergal-Bud facilities for July 2026
Throughout July, Intergal-Bud maintained steady construction progress across all its projects.
Monolithic, façade, engineering, and finishing works are being carried out simultaneously at the construction sites.
CITY HUB Residential Complex is already nearing completion, while the monolithic structures of the first Polar Park buildings are at the final stage.
In July, we are also beginning to report on the construction of the multi-level above-ground parking facility at the Syretski Sady Residential Complex, continuing the development of this already commissioned complex.
More details on the construction progress of all projects are available in our monthly report.
City Hub Residential Complex, address: 8-10 Mokra St.
A residential complex that harmoniously combines the comfort of urban living with the cosiness of private space. Residents will enjoy spacious apartments, underground parking, children’s and sports grounds, as well as well-developed on-site infrastructure. Scheduled construction completion: Q3 2026.
Building 2:
- Roofing works — 66%
- Façade works — 80%
- Waterproofing of the underground plinth area — 91%
- Installation of metal-plastic windows and doors — 99%
- Installation of the electrical switchboard room — 95%
- Plumbing works in the basement, apartments and common areas (water supply, sewerage and heating) — 99%
- Ventilation and smoke extraction systems — 83%
- Electrical installation works in apartments, common areas and the basement — 95%
- Fire protection system — 70%
- Installation and commissioning of lifts — 95%
- Installation of small metal structures — 75%
- Installation of the individual heating substation — 42%
- Landscaping and greenery works — 26%
- Outdoor lighting — 13%
Building 2 parking facility:
- Parking waterproofing — 95%
- Entrance area construction — 82%
- Electrical installation works — 92%
- Installation of the electrical switchboard room — 99%
- Plumbing works — 82%
- Ventilation and smoke extraction systems — 90%
- Parking floor covering installation — 90%
- Fire protection system — 74%
- Installation of metal doors and gates — 99.5%
- Installation of metal-plastic windows — 99%
- Landscaping and greenery works — 51%
Kaskad Residence residential complex, address: 5A Prychalna St.
A comfort-class residential complex located just 200 metres from the Dnipro River. It combines cascading architecture, a gated territory, well-developed infrastructure, full autonomy and energy independence. All apartments are delivered to buyers in White Box condition.
Section 1:
- First floor: monolithic works fully completed
- Second floor: reinforcement works are underway, followed by concreting
- Shelter in Section 1: monolithic works have been completed; preparation of the walls for external waterproofing is underway
Section 2:
- Foundation works completed
- Concrete pouring of the basement-level walls is underway
Section 3:
- Foundation pit completed
Polar Park residential complex, address: Kyiv, Petro Kalnyshevsky St., 2
Building No. 1:
- Monolithic frame construction — 99%
- Construction of walls and partitions — 94%
- Installation of metal-plastic structures — 95%
- Internal water supply and sewerage system — 48%
- Internal heating system — 48%
- Internal power supply system — 49%
- Roofing works — 35%
Building No. 2:
- Monolithic frame construction — 93%
- Construction of walls and partitions — 57%
- Installation of ventilation ducts and prefabricated staircases — 88%
- Installation of metal-plastic structures — 30%
- Internal power supply system — 15%
Building No. 3:
- Monolithic frame construction — 80%
- Construction of walls and partitions — 37%
- Installation of ventilation ducts and prefabricated staircases — 74%
Parking facility:
- Construction of the monolithic parking frame — 83%
- Construction of walls and partitions — 22%
Sky Avenue Residential Complex, address: st. Svyatoslav Khorobryho, 3
A comfort+ residential complex located near Sevastopolska Square. The project comprises six residential buildings with commercial premises on the ground floors and cosy courtyards featuring children’s and sports grounds, as well as recreation areas.
Building No. 3:
- Waterproofing of the underground plinth area — 62%
- Entrance area construction — 85%
- Construction of external ceramic-block walls — 87%
- Construction of internal ceramic-block walls and partitions — 86%
- Installation of metal-plastic windows and doors — 67%
- Installation of small metal structures — 86%
- Electrical installation works in apartments, common areas and the basement — 39%
- Roofing works — 44%
- Installation of lift equipment — 26%
- Plumbing works in the basement, apartments and common areas (water supply, sewerage and heating) — 31%
- Installation of utility networks in fully finished apartments — 23%
Parking facility No. 2 under Building No. 3:
- Parking waterproofing — 36%
- Backfilling — 50%
Preschool educational facility:
- Brickwork — 15%
- Waterproofing of external walls — 95%
- Backfilling — 90%
- Parking facility at the Syretski Sady Residential Complex, address: 10D Ivana Vyhovskoho Street
- Construction of the monolithic basement and plinth frame — 100%
- Construction of the monolithic frame — 9%
BFK INTERGAL CITY, address: st. Staronavodnytska, 16B
A premium multifunctional complex combining elegance, futuristic architecture, advanced technology and the unique location of Pechersk — the centre of the capital’s business, cultural and investment life.
Tower A:
- Installation of ventilated curtain wall systems — 99%; translucent façade structures — 98%
- Installation of internal plumbing networks: K1 — 99%, K2 — 99%, T1/T2 — 98%, V1 — 98%
- Heat supply mains with distribution manifolds — 90%
- Installation of ventilation systems — 95%
- Installation of air-conditioning systems — 99%; installation of unit equipment — 10%
- Installation of the fire suppression system — 92%
- Installation of access control and structured cabling systems — 90%
- Floor screeding in apartments — 100%
- Plastering in apartments — 100%
- Electrical installation works — 93%
- Boiler room installation — 95%
- Terrace surfacing — 40%
- Installation of the individual heating substation and heating modules — 95%
- Installation of apartment entrance doors — 15%
- Finishing works on the technical floors (floors 23–25) — 90%
- Engineering rooms: electrical switchboard room — 95%; pump room — 95%
- Finishing of common areas (floor tiling) — 90%
- Fire-resistant penetrations — 80%
- Installation of terrace railings — 10%
- Installation of roof metal structures — 95%
- Internal gas pipeline — 95%
- Lobby: monolithic works and screeding — 100%; engineering systems V1, K1, K2, electrical systems, air conditioning, ventilation, structured cabling system and translucent façade structures — 40%
Tower B:
- Masonry works — 90%
- Internal plumbing works — 80%
- Installation of heating appliances — 95%
- Floor screeding — 85%
- Ventilation — 80%
- Air-conditioning systems — 60%
Tower C:
- Masonry works — 97%
- Internal plumbing works — 96%
- Installation of heating appliances — 95%
- Floor screeding — 95%
- Ventilation — 30%
- Air-conditioning systems — 15%
- Installation of structured cabling systems — 35%
- Plastering — 32%
Tower D:
- Masonry works — 89%
- Installation of ventilation blocks — 95%
- Installation of ventilated curtain wall systems — 65%; translucent façade structures — 70%
- Concreting — 97%
- Roof metal structures — 30%
- Roofing works — 85%
- Plastering — 50%
- Concreting — 97%
- Installation of ventilation systems — 45%
- Installation of heating systems — 70%
- Internal plumbing works — 75%
- Air-conditioning systems — 20%
Tower E:
- Monolithic works — 99%
- Installation of ventilated curtain wall systems — 70%; translucent façade structures — 90%
- Plastering — 40%
- Floor screeding — 40%
- Roofing works — 10%
- Installation of heating systems — 30%
- Internal plumbing works — 30%
- Air-conditioning systems — 10%
- Ventilation — 10%
Building 6:
- Monolithic works — 50%
Stylobate:
- Monolithic works — 95%
- Surface covering works — 50%
Office slope:
- Monolithic works — 95%
Parking facility:
- Finishing works (sandblasting) — 95%
- Dismantling works — 80%
Retaining walls:
- RW-2 — 30%
External utility networks:
- V1 — 60%
- K1 — 60%
- K2 — 60%
- Gas pipeline — 30%
Other publications
Promotions
Special installment plan for up to 5 years on ready-to-move-in apartments
9/28/2026Promotions
Special installment plan for ready-to-move-in duplex apartments at Sky Avenue
9/25/2026Promotions
Apartments under the “єОселя” program at Sky Avenue. Down payment from UAH 870,000.
9/25/2026News
Building No. 3 has been accredited under the state “єОселя” program with Globus Bank
9/24/2026