Kiev: Dynamics of construction

  • 04/10/2016

On the 3-rd of October 2016, the construction of facilities is carried out in strict accordance with the declared construction period of RC-s.

Residential complex "Park Lakes"

In house number 11 the following work is performed:

The device is a monolithic frame - the work is completed by 31% (work is underway to arrange the vertical elements of the 8th floor and the floor slab of the 9th floor).

The device walls and partitions performed at 2% (work is underway in the basement).

In house number 12:

Execution of piles - 88%.

Residential complex "Demiivka"

The following works are being carried out in house No. 1:

- masonry exterior walls: 1 section - 99%, 2 section - 99%;

- brickwork of internal walls: 1 section - 90%, 2 section - 90%;

- installation of windows: 1 section - 97%, 2 section - 97%;

- installation of doors: 1 section - on the 12th, 13th floors of work are performed, 2 section - on the 9th floor are installed;

- plaster walls: 16, 17, 20 floors in work;

- screed: 1 section - on the 12th floor the work is done, 2 section - on the 9th floor the work is done;

- piping: 1 section - on the 13th floor the work is done, section 2 - 12, 13, 14 floors in the work;

- device retaining walls: PS-1 is made at 90%;

- laying of networks: K-1 - 98%, K-2 - 45%, heating mains - 97%, external power grids - 80%;

- the water supply system is being installed - 30%, and the power supply systems - 80%;

- roofing: on 1 section - the roofing material is being glued (40%), section 2 - the screed is 100% complete.

- entrance groups: 1 section - 90%, 2 section - 20%;- parking roof: expanded clay - 60%, screed - 60%;

- facades - 20%.

Residential complex "Traditsia"

In the house number 2:

Completed the foundation. Reinforcement of the walls of the basement.In the house number 3:

The installation of the walls of the basement floor.

Residential complex "Malachite"

The following works are being carried out at the construction site of house No. 3:

Device monolithic frame:

- 301 section - the work was performed by 25%;

- 302‒303 sections - 30%;

- 304 section - 15%.

Backfilling:

- 301 section - 70%;

- 302‒303 sections - 30%;

- 304 section - 5%.

Waterproofing of the basement and basement are made by 60%.

Residential complex "Yaskravy"

The following works are being carried out in house No. 4:

- brickwork done at 79%;

- installation and commissioning of elevators - 9%;

- device of metal-plastic windows - 72%;

- final finishing of public places - 19%;

- installation of the ventilation system - 58%;

- internal power supply system - 34%;

- Internal heating system - 32%;

- internal water supply and sewage systems - 31%;

- installation of a fire alarm system - 15%;

- low-voltage systems - 10%;

- device facades - 1%.

In house number 5:

The device is made of monolithic frame 57% (level 15 floors). Bricklaying done at 3%. Device ventilation channels - 20%.

In house number 7:

Performance of piles is 25%.

Residential complex "Lake Hai Hatne"

In the house №1 the following works are performed:

- basement waterproofing done by 50%;

- monolithic frame device - 95%;

- device walls and partitions - 75%;

- installation of windows - 50%;

- device facades - 15%;

- plaster walls - 8%;

- low-voltage systems - 45%;

- plumbing work - 5%;

- installation and commissioning of elevators - 50%.

Residential complex "Nyvki-Park"

The following works are being carried out in house No. 1:

Section "A": the floor slab is flooded with 3 floors.

Section "B": the device of vertical elements of the 3rd floor.

Section "B": the device of the vertical elements of the 3rd floor.

Performed waterproofing the walls of the basement.In the house number 2:

Concrete preparation has been carried out for the construction of the base plate of the section “G”.

Residential complex "Otradny"

House number 1:

Reinforcement of the base plate. On Saturday start concreting.

House number 2:

Waterproofing base plate.