Dynamics of construction on June 15

  • 15/06/2017

LCD "Yaskravy"

 

House number 4:

 

Installation and commissioning of elevators - 97.5% (device of technical elements).

 

Finishing of common areas - 88% (painting; applying decorative plaster, facing with ceramic tiles on the 1st floor).

 

The internal power supply system is 98% (the installation of electrical switchboards and light bulbs in common areas continues).

 

The internal heating system - 99% (work is almost completed).

 

The internal water supply and sewerage system - 98% (installation of dies; it remains to install washbasins in the finished apartments).

 

Fire alarm installation - 81% (installation of equipment continues).

 
Installation of low-voltage systems - 81% (installation of the control panel).

 
Device on-site networks - 99% (it remains to install lights).

 
Landscaping completed.

 

House number 5:

 
The monolithic frame device is 100% complete.

 
Brickwork completed.

 
Installation of window designs - 98% (the work is almost completed).

 
Plumbing works - 74% (the layout of the heating pipes on the floors).

 
Electrical work - 70% (electrical cable layout on the floors).

 
Low-voltage systems - 60%.

 
Plaster walls - 60% (in the 21st floor).

 
Floor screed - 80% (in the 25th, technical floor and ground floor).

 
The device masonry on the roof - 100%.

 
Roof installation - 56% (waterproofing continues).
House number 6:

 
Section 1 completed the preparation for the device of the base plate. Filling of base plates in sections 2 and ı 3 is completed.

 

 
House number 7:

 
The device of the monolithic frame section number 1 - 45%. In the 15-16th floor.

 
The device of the monolithic frame section number 2 - 48%. In the 15-17th floor.

 
Brickwork is being carried out: section No. 1 - 12% (in the 2nd, 4th and 7th and 9th floors), section No. 2 - 8% (in the 3rd and 3rd floors).

 
The device of the ventilation ducts is being carried out: in sections 1 and 2, the work was done at 30% (in the 10-11th floors).

 
Performed waterproofing and insulation of the basement.


LCD "Lake Guy Hatne"

 
House number 2:

 
Foundation device - 100%.

 
Basement walls waterproofing - 100%.

 
The device walls - 60% (brickwork 4th floor).

 
The device of monolithic floor slabs - 55% (4th floor).

 
The device partitions - 70% (3rd floor).

 

 
House number 3:

 
Foundation device - 100%.

 
Basement walls waterproofing - 100%.

 
Wall construction - 30% (brickwork on the 4th floor).

 
The device of monolithic floor slabs - 60% (3rd floor).

 
The device partitions - 80% (3rd floor).


LCD "Park Lakes"

 
House number 11:

 
The construction of external walls and partitions (masonry) - is performed on the technical floor and roof (97%).

 
The device of internal walls and partitions is performed on the technical floor (97%).

 
Roof installation - the work is completed by 60%.

 
Installation of window structures continues at the 24-25th floors (95%).

 
The construction of the facades continues - insulation of balconies (25%)

 
Wall plastering is performed on the 18th, 23rd floors (77%).

 
Plumbing works - installation of pipes for water supply, sewage and heating (41%).


Floor screed is performed on floors 13-17 (45%).

 
Installation of the internal power supply system - works are carried out on the risers of the 1-25th floors (40%)

 
Low-voltage systems - installation of risers (46%).

 
The installation of ventilation ducts (93%) and the installation of elevators (18%) are continuing.

 

 
House number 12:

 
The monolithic frame device is made on the 17th floor (62%).

 
The device walls and partitions: performed on the basement, 2-5th floors (12%).

 
The device ventilation channels - is performed on the 15th floor (52%).


House number 13:

 
The construction of the main pile field, including piles of tower cranes, has been completed.

 
The base plate is made on all 3 sections.

 
The construction of the monolithic frame continues - reinforcement and concreting of the 3rd-4th floors (14%).

 

 

 
Residential complex "Tradition"

 
House number 3:

 
Device parapets and vertical elements of the 28th floor.

 
Brick masonry on the 18-24th floors.

 
Installation of window structures is made on the 12th-15th floors.

 
Electrical work is performed on the 9th-13th floors.

 
The piping of heating and plumbing on the 8th-11th floors continues.

 
Installation of sanitary risers continues (in the work of the 14-26th floors).

 
Plaster walls - in the basement and the 10th floor.

 
The floor screed continues on the 6th floor.


LCD "Malachite"

 
The following works are being carried out at the construction site of house No. 3:

 
The device of the monolithic frame in all 4 sections is completed.

 
The basement waterproofing device is almost complete:

 
section 301 - 98%;

 
sections 302-303 - 98%;

 
section 304 - 95%.

 
The device walls and partitions:

 
section 301 - 67% (laying on the 17-18th floor);

 
sections 302-303 - 100%;

 
Section 304 - 72% (laying on the 19th-20th floor).

 
Installation of window structures:

 
section 301 - 50% (11th floor);

 
sections 302-303 - 99% (work on the glazing of technological openings for the supply of materials is being completed);

 
section 304 - 45% (11-12th floors).

 
Backfilling - it remains to perform a vertical layout for the final improvement:

 
section 301 - 90%;

 
sections 302-303 - 90%;

 
section 304 - 90%.

 

 
House number 4:

 
Works on the device of a ditch are performed. Section 404 is concreting the vertical elements of the 2nd floor. Concreting of the foundation cushion is being conducted in sections 405 and 406.

 
The foundation of parking №4 has been concreted, the monolithic walls of the parking are being constructed.

 


LCD "Nyvky Park"

 
House number 1:

 
The monolithic frame device is complete.

 
The device walls and partitions:

 
Section A - technical floor in work, Section B - 15th-16th and technical floor in work, Section C - in work 13-15th, technical floor and roof. The 16th floor is completed.

 
The installation of window structures continues: in sections B, C in the 8th floor, in section A - the 12-13th floors.

 
The installation of internal engineering continues.

 
Work continues on interior decoration: screed floor and plaster on the 6-7th floors.

 
The roofing is continued in sections A and B (80%), in section C (20%).

 
The device continues warming parapets and ventilation shafts on the roof.
 

House number 2:

 
Device monolithic frame:

 
Section D — parapet system completed; Section D — parapet system continues.

 
The device walls and partitions:

 
Section G and D - in the 5th-9th floor, on section G, laying on the roof continues.

 
The installation of window constructions continues: in sections G and D - the 4th floor is in operation.

 
Work has begun on internal engineering, as well as finishing work in the basement.

 

 
House number 3:

 
In section G, work is underway to arrange the floor slab of the 3rd floor, on section D the vertical elements of the 3rd floor are being arranged, in Section D the floor slab is being constructed on the 2nd floor.

 

House number 4:

 
Section B continues the construction of the basement slab, section C continues the construction of the vertical basement elements, and in section E, the basement ceiling slab is made.

 

 

 
LCD "Otradny"

 
House number 1:

 
The monolithic frame device is 86% complete.

 
Brick wall: 1st floor - 100%, 2nd floor - 96%, 3rd floor - 96%, 4th floor - 96%, 5th floor - 96%, 6th floor - 96% , 7th floor - 40%, 8th floor - 96%, 9th floor - 93%. In the work of the 10th floor (40%) and the 11th floor (60%).

 
The brickwork of the basement continues.

 
Installation of window structures continues: work on the 6th floor.

 
Backfill done.

 
Plaster walls - work is being done on the 3rd floor.

 
Plumbing work continues (installation of risers).
House number 2:

 
The monolithic frame device is 76% complete.

 
Work is underway on the installation of brickwork: on the 1st and 2nd floors, the work was done at 100%, on the 3rd floor - 84%, on the 4th floor - 84%.

 
Work continues on the installation of waterproofing basement.

 
Began backfilling.

 

 
House number 3:

 
Reinforcement and concreting performed at 40% (floor slab device on the 7th floor).

 
Work continues on the installation of waterproofing basement.

 

 
House number 4:

 
Base plate is made. Ground floor is reinforced. The foundation plate is being reinforced.

 

 
House number 5:

 
The pit is made. Pile test completed.
Residential complex "Teremki"

 
On the 1-st stage, the device of the 5th floor slab is being built.

 
At the 2nd stage, robots on the piling field were started.