Company "Intergal-Bud": the dynamics of construction on 06.10.17

  • 15/09/2017

Company "Intergal-Bud": the dynamics of construction on 06.10.17

 

Residential complex "Vladimirsky"

Foundation device - 100%.

Basement walls waterproofing - 100%.

Completed overlap of the 2nd floor.

The construction of vertical walls - 3rd floor.

 

Residential complex "Syretsky Gardens"

House number 1

Completed overlapping plates of the 1st floor.

 

House number 2

The excavation work has been completed.

 

House number 3

Clearing the area continues.

 

House number 4

Completed soil testing piles.

 

Residential complex "Yaskravy"

House number 4:

Fire alarm installation - 99% (installation of equipment continues).

Installation of low-voltage systems - 99% (installation of the control panel).

Internal power supply system - 100%.

Device on-site networks - 100%

Landscaping completed.

 

House number 5:

The monolithic frame device is 100% complete.

Brickwork completed.

Installation of window structures is completed.

Plumbing works - 95.5%.

Electrical work - 91%.

Ventilation and smoke removal - 77%.

Low-voltage systems - 86%.

Plaster walls - 100%.

Floor screed - 100%.

Roof installation - 99% (waterproofing continues).

Installation and commissioning of elevators - 70%.

 

House number 6:

In section number 1:

Completed construction of the 4th floor.

Readiness of the 5th floor vertical - 40%.

Basement waterproofing - 50%.

 

In section 2:

Completed construction of the 4th floor.

Finished vertical 5th floor.

Basement waterproofing - 50%.

 

In section number 3:

Completed construction of the 4th floor.

The readiness of the 5th floor vertical is 50%.

Basement waterproofing - 50%.

 

House number 7:

The device of the monolithic frame section number 1 - 84%. In the 23rd and 23rd floors.

The device of the monolithic frame section number 2 - 85%. There are 24 floors in the work.

 

Brickwork is being carried out: section No. 1 - 49% (in the 12th, 14th, 15th, 16th floors), section No. 2 - 23% (in the 7th, 8th, 9th floors).

The arrangement of the ventilation ducts is being carried out: in section 1, the work was completed on 76% (in the work of the 20-22nd floors); in section number 2 the work was performed on 79% (in the work of the 20th to 23rd floors).

Plumbing works have been started: on section 2 works are being carried out on the 1st and 2nd floors.

Installation of window constructions: in sections 1 - 3-4-5 and № 2 in the work 2nd floors.

 

Residential complex "Lake Guy Gatne"

 

House number 2:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 100% (masonry attic floor).

The device of monolithic floor slabs - 100%.

The device partitions - 100%.

Roof -10%

Facade -30%

Interior finish -10%

 

House number 3:

Foundation device - 100%.

Basement walls waterproofing - 100%.

The device walls - 95% (masonry attic floor).

The device of monolithic floor slabs - 100%.

The device partitions - 90%.

Roof -20%

Facade -10%

Interior finish -5%

 

House number 4:

The foundation is completed - 100%.

The basement is 100% waterproofed.

The device walls -60% (brickwork of the third floor).

 

House number 5:

Foundation device - 100%.

The basement is 100% waterproofed.

The device walls-25%.

 

Residential complex "Demiivka"

House number 2:

The slab of the 14th floor is being built.

Mounted ventilation units and staircases on the 10th floor, inclusive.

The brickwork on the 1st, 5th and 7th floors is finished.

Work continues on the brickwork on the 6th, 9th, 10th, 11th floors.

Finished waterproofing basement.

Readiness of monolithic structures of input groups - 90%.

Installation of windows on the 2nd floor is underway.

 

Residential complex "Park Lakes"

House number 11:

The construction of external walls and partitions is completed.

The construction of internal walls and partitions is completed.

Roof installation - 98%, completion of waterproofing, insulation of ventilation.

Installation of window structures is almost complete (99%).

The construction of facades continues - 95%.

Plaster walls are almost finished.

Plumbing works - installation of pipes for water supply, sewage and heating (90%).

Floor screed is finished.

Installation of the internal power supply system - 96%.

Low-voltage systems - 90%.

The construction of ventilation ducts (95%) and the installation of elevators (90%) are continuing.

 

House number 12:

The monolithic frame device is made on the 25-26th floors (85%).

The device walls and partitions: performed on the 15-17th floor (44%).

The device ventilation channels - is performed on the 19th floor (68%).

 

House number 13:

The monolithic frame is made on the 14th to 17th floors (53%).

The device ventilation channels - is performed on the 10-12th floor (34%).

Entrance group - partly made iron-concrete frame (11%).

 

Residential complex "Tradition"

House number 3:

Brickwork completed.

Facade work - 25% readiness.

Installation of sanitary equipment - up to 20 floors.

Work on the electrical wiring at home - 70% readiness.

 

House number 2:

The device slabs of the 19th floor.

The brickwork is on the 8th floor.

 

Residential complex "Nyvky Park"

House number 1:

The monolithic frame device is complete.

The construction of walls and partitions on sections A, B and C is complete.

The installation of window constructions continues: in section B, the 15th to 16th floors are in operation, in section B in the work of the 13th and 14th floors, in section A - the works have been completed.

The installation of internal engineering continues.

Work continues on interior decoration:

Section A - floor screed and plaster on the 10th floor;

Section B - screed to the 15th floor, plaster - 8th-9th floors;

Section B - screed and plaster - 9th floor.

The roofing on 3 sections is almost complete.

 

House number 2:

The device of the monolithic frame in sections G and D is completed.

The device walls and partitions:

In section D - completed, in section D - completed.

The installation of window constructions continues: in sections D - completed and D - in the 13th-16th floors.

Work continues on internal engineering, as well as finishing work on the floors.

The roofing on 3 sections is almost complete.

 

House number 3:

In sections G, D, W, work is underway to construct a monolithic frame of the 13th floor.

The laying continues: works are carried out on the 5-6th floors of the sections G, D, J.

 

House number 4:

In sections E, B, C, a monolithic frame of the 8th floor is maintained.

The laying continues: works are carried out on the basement floor of section B, 1st floor of section B, 1,2.3 floors of section E.

Work is underway on waterproofing basement parts.

 

Residential complex "Otradny"

House number 1:

The monolithic frame device is 100% complete.

The brickwork of the external walls is 100% complete.

Began painting the facade.

 

House number 2:

The monolithic frame device is 100% complete.

Work is underway on the installation of brickwork: on the 15th floor.

Roofing works on the arrangement of the roof of the gas boiler.

The device waterproofing basement completed.

Backfill done.

 

House number 3:

Overlap of the 14th floor is completed.

The construction of the 15th floor has begun.

The waterproofing device of the basement is completed.

The laying of the balcony is finished on the 4th floor.

 

House number 4:

Base plate is made.

The device is vertical elements of the 2nd floor.

 

House number 5:

Completed piling device. Concrete preparation completed.

 

Residential complex "Teremki"

1st house:

Installation of vertical floors 15 floors;

Facade work on the 8th floor

 

2nd house:

Installation of vertical floors of the basement.

 

Residential complex "Malachite"

3rd house:

At sections 302-303, finishing works from the 2nd to the 9th floor were carried out - 80% completed.

Work is done on the installation of external engineering networks:

- domestic sewage K1;

- rainwater drain K2;

- plumbing B1;

- Electricity of the net.

 

4th house:

Monolithic frame, section 404 - 100%.

Work is underway on the brickwork on the first and second floors of section 404.

Work is underway to install vertical reinforced concrete structures on sections 405-406, the mark is 0.100.

Parking P1. Work is underway on the installation of reinforced concrete foundations, the mark is 6.300.

Parking P2. Work is underway to install vertical reinforced concrete structures, the mark is 6.300.