Company "Intergal-Bud": the dynamics of construction on 14.08.17

  • 14/08/2017

Company "Intergal-Bud": the dynamics of construction on 14.08.17

Residential complex "Vladimirsky"

Foundation of the foundation - 100%.

Waterproofing the base - 100%.

The wall is continuing - 60% (2nd floor).

The installation of monolithic floor slabs is continuing - 70% (2nd floor).

 

Residential complex «Syretsky gardens»

 

House number 1

The basement arrangement is made by 10%. The mounting of the tower crane is being carried out.

 

House number 4

Test piling is complete.

The test piles are completed.

 

House number 2 and number 3

The territory is being restored.

 

Residential complex «Yaskravy»

House number 4:

Installation of fire alarm - 94% (installation of equipment is ongoing).

Installation of low-current systems - 94% (installation of the control panel).

Internal electricity supply system - 98%.

Inner-floor network arrangement - 99%.

Improvement of the territory is completed.


 

House number 5:

The arrangement of the monolithic frame is 100%.

Brick masonry completed.

Installation of window constructions is completed.

Sanitary engineering works - 84%.

Electrical works - 83%.

Weak-current systems - 76%.

Plastering of walls - 82%.

Floor tension - work is almost complete (95%).

Roof installation - 70% (installation of waterproofing continues).

Installation and commissioning of elevators - 40%.

Tentative completion date of construction works: the second half of August.


 

House number 6:

In section №1 the arrangement of vertical elements of the basement is carried out.

In sections №2 and №3 there is an arrangement of a floor slab of 1 floors.


 

House number 7:

Position of the monolithic frame of section №1 - 69%. In the 20-21 th floor.

Position of the monolithic frame of section №2 - 72%. Works 20-23rd floors.

Bricklaying is carried out: section number 1 - 35% (in the work of the 5th, 8th, 10th-11th floors), section number 2 - 20% (in the works 5-8th floors).

Installation of ventilation ducts is carried out: in sections No. 1 the work is carried out on 66% (in the work of 18-19th floors); in section №2 the work is executed on 49% (in the work of 13-16th floors).

Plumbing works started: in the section number 2 works are carried out on the 1st-2nd floors.

Assembling of window constructions: in the sections №1 and №2 in work 2 floors.


 

Residential complex «Ozerny Gai Gatne»

House number 2:

Foundation of the foundation - 100%.

Waterproofing the walls of the cap - 100%.

Arrangement of walls - 95% (brick masonry floor).

The installation of monolithic slabs is 100%.

Arrangement of partitions - 90%

 

House number 3:

Foundation of the foundation - 100%.

Waterproofing the walls of the cap - 100%.

Arrangement of walls - 95% (brick masonry floor).

The installation of monolithic slabs is 100%.

Arrangement of partitions - 90%.


 

House number 4:

Foundations foundation completed - 100%.

The waterproofing of the cap is 100% executed.

Wall arrangement - 20% (1st floor brickwork).


 

House number 5:

Foundation of the foundation - 100%.

Sealing of the waterproofing of the cap on 100%.

Wall arrangement - 3%.

 

Residential complex «Demiivka»

House number 2:

The arrangement of the 14th floor ceiling is continuing.

Fitted ventilation units and stairs marches on the 10th floor inclusive.

Backflow continues.

Mortar lasts: on the basement, on the 1st and 2nd floors, works are executed on 100%, works on the 3rd-4th floors continue.

The installation of monolithic structures of entrance groups, entrances to basements, and so on.


 

Residential complex “Park Lakes”

House number 11:

The arrangement of exterior walls and partitions (masonry) is completed.

The arrangement of internal walls and partitions is completed.

Roofing - the work is done on 85%

The installation of window constructions is almost completed (99%).

The installation of the facades continues - the insulation of balconies (50%).

Plastering of walls is practically completed (95%).

Plumbing works - installation of pipes of water supply, sewage and heating (90%).

The tension of the floor is almost done (95%).

Installation of the system of internal power supply - work is carried out on risers 1-25-th floors (75%).

Weak-current systems - mounting of risers (70%).

The installation of ventilation ducts (95%) and mounting of elevators (33%) are ongoing.

Estimated completion date of construction works: end of September.


 

House number 12:

The installation of a monolithic frame is carried out on floors 21-23 (85%).

The arrangement of walls and partitions is carried out on the 11th floor (25%).

The arrangement of ventilation ducts is carried out on the 19th floor (68%).


 

House number 13:

The arrangement of the main pile field, including piles of tower cranes, has been completed.

The base plate is made on all 3 sections.

The installation of a monolithic frame is continuing - reinforcement and concreting of the 9th-10th floors (40%).


 

Residential complex «Traditsia»

House number 3:

The brickwork is completed.

Installation of window constructions is carried out on the 21st floor.

Installation of internal networks, plastering of walls and installation of screeds is ongoing.


 

House number 2:

The placement of the floor slab is on the 11th floor.

Brick masonry is on the 4th floor.


 

Residential complex «Malakhit»

The following works are carried out on the construction site of the house №3:

The arrangement of the monolithic frame in all 4 sections is complete.

The seating of the waterproofing of the cap is practically completed:

Section 301 - 98%;

sections 302-303 - 98%;

section 304 - 95%.

Arrangement of walls and partitions:

Section 301 - 90%;

sections 302-303 - 100%;

section 304 - 93%.

Installation of window constructions:

Section 301 - 80% (23-24rd floors);

Sections 302-303 - 99% (works with the glazing of process holes for the submission of materials);

section 304 - 97%.

Reverse falling asleep - it was left to perform vertical planning under the finishing of the accomplishment:

Section 301 - 90%;

section 302-303 - 90%;

section 304 - 90%.


 

House number 4:

The excavation work is completed. At sections 402 and 403, pile works are completed. On section 404 there is an arrangement of a floor slab of the 8th floor. The installation of the basement floor in sections 405 and 406 continues.


 

Residential complex «Nyvky-Park»


 

House number 1:

The structure of the monolithic frame is complete.

Arrangement of walls and partitions A, B and B is completed.

The mounting of window constructions continues: in section B - 15-16 th floors in work, in section B in the work of 13-14 th floors, in section A of the work performed.

The installation of internal engineering continues.

Work is ongoing on the interior decoration of the premises:

Section A - floor screed and plastering on the 10th floor;

Section B - screed to the 15th floor, plastering - 8-9th floors;

Section B - screed and plastering - 9th floor.

The arrangement of the roof in 3 sections is complete.


 

House number 2:

The arrangement of the monolithic frame in Sections G and D is completed.

Arrangement of walls and partitions:

In Section G - completed, in Section D in the work of 11-12 th floors.

The mounting of window structures continues: in sections G and D in the work of the 8th floor.

Work is continuing on internal engineering, as well as decoration in the basement.


 

House number 3:

In sections G, D, and F work is carried out on the arrangement of a floor slab of 8 floors.

Masonry is ongoing: works are being carried out on the basement, 2-3rd floors.


 

House number 4:

In the sections B and E there is an installation of a floor slab of 3 floors.

 

Residential complex «Otradny»

House number 1:

The structure of the monolithic frame is 98%.

Brick masonry of exterior walls is made 100%.

Bricklaying of internal walls: on the 13th floor works are executed on 95%, work on the 14th-16th floors continues.

The mounting of window constructions continues: works on the 11th-14th floors.

Plastering of walls - works are made on the 2nd-11th floors. Works are on the 13th floor.

Plumbing works are ongoing (installation of the risers is carried out, work on wiring and laying of heating pipes on floors is carried out: works are executed on 2-9 floors).

Fitting of the floor - works are made on 2-6th and 9th floors, work is carried out on the 7th floor.

Work began on the facade arrangement. The brickwork of the roof has begun.

 

House number 2:

The structure of the monolithic frame is 90%.

Works on the laying of brickwork are underway: on the 1st to 5th floors works are executed on 95%, works are conducted on the 6-8th floors.

Construction of the waterproofing of the basement floor is completed.

Backflow is complete.


 

House number 3:

Reinforcement and concreting are made on 60% (arrangement of vertical elements of the 11th floor).

Construction of the waterproofing of the basement floor is complete.

Brick masonry is executed on the 1st to 3rd floors.

 

House number 4:

The foundation slab is executed. The arrangement of vertical elements of the 2 nd floor is carried out.


 

House number 5:

The piling is completed. Concrete preparation is complete.


 

Residential complex «Teremki»

On the first stage of the construction of the complex there is an arrangement of the floor slab of the 10th floor, as well as facade work on the 5th floor.

In the second stage of construction work on the construction of a pile field is completed