Works is continuing for connecting the residential complex "Ozernyi Guy Gatne" to the Kiev sewage system

  • 17/05/2017

"Lake Guy Gatne" RC

 

House number 1: all construction work completed

 

House number 2:

 

Foundation device - 100%.

 

Basement walls waterproofing - 100%.

 

Wall construction - 37% (brickwork of the 3rd floor).

 

The device of monolithic floor slabs - 35% (2nd floor).

 

Partition device - 25% (2nd floor).

 

House number 3:

 

Foundation device - 100%.

 

Basement walls waterproofing - 100%.

 

Wall installation - 42% (brickwork of the 3rd floor).

 

The device of monolithic floor slabs - 35% (2nd floor).

 

Partition device - 25% (2nd floor).

 

House number 4:

 

Preparation for the foundation - 100%.

 

Foundation waterproofing - 100%.

 

A screed for waterproofing the device for the foundation plate (completed by 25%).

 

House number 5:

 

Foundation device - 100%.

 

Basement walls construction - 50% (basement walls flow).

 

 

"Yaskravy" RC

 

House number 4:

 

Installation and commissioning of elevators - 95% (the device of technical elements).

 

Roof structure - 95% (left to lay the upper ruberoid layer).

 

Facade arrangement - 88% (painting continues, ceramic granite tile installation on the 1st floor).

 

Finishing of common areas - 86% (painting; applying decorative plaster, facing ceramic tiles on the 1st floor).

 

Installation of the ventilation system - 99% (everything is ready for commissioning).

 

The internal power supply system is 97.5% (it remains to install electrical switchboards and light bulbs in common areas).

 

Internal heating system - 99% (it remains to install the batteries in the basement).

 

The internal water supply and sewerage system - 98% (installation of dies; it remains to install washbasins in the finished apartments).

 

Fire alarm installation - 73% (installation of meters).

 

Installation of low-voltage systems - 73% (installation of meters).

 

Device on-site networks - 80%.

 

The device of entrance groups - 50% (installation of metal structures, finishing with ceramic granite).

 

Landscaping - 35% (device of sidewalks, access roads, etc.).

 

Delivery of the house is scheduled for May 31.

 

House number 5:

 

The monolithic frame device is 100% complete.

 

The brickwork is 90% complete (the brickwork of the partition walls for the cabinets remains).

 

Installation of window designs - 98% (the work is almost completed).

 

Plumbing works - 65% (the layout of the heating pipes on the floors).

 

Electrical work - 62% (electrical cable layout on the floors).

 

Low-voltage systems - 55% (layout of electrical wiring on the floors).

 

Plaster walls - 32%.

 

Screed floor - 58% (17-18th floors).

 

The device masonry on the roof - 100%.

 

Roof installation - 41% (it remains to install waterproofing).

 

House number 6:

 

In sections 1, 2 and 3, work on the pile field is 100% complete.

 

In sections 2 and 3, concrete preparation for the foundation slab was completed.

 

House number 7:

 

The device of the monolithic frame section number 1 - 39%. In work 12-13th floor.

 

The device of the monolithic frame section number 2 - 40%. In the work of the 13th floor.

 

Brickwork is being carried out: section No. 1 - 8% (in work 2-5, 7 floors), section No. 2 - 3% (and work on the 2nd floor).

 

The device of the ventilation ducts is being carried out: in sections 1 and 2, the work was carried out at 24% (in the work of the 7-8th floors).

 

"Demiivka" RC

 

House number 1: all construction work completed

 

House number 2:

 

Preparation is under way for the construction of vertical elements of the 7th floor.

 

Mounted ventilation units on the 1st and 2nd floors.

 

Backfilling continues.

 

 

"Park Lakes" RC

 

House number 11:

 

The device walls and partitions (masonry) - performed on the basement - 21st floors; works are being performed on the 22nd, 24th floors (85%), on the 25-26th floor - 35%. Laying on the roof is made by 5%.

 

Installation of window structures continues on the 17th to 23rd floors.

 

Plaster walls on the basement – ​​16th; on the 19th floor is 95% completed; work is being done on the 17th and 20th floors.

 

Installation of the internal power supply system - works are performed on the risers of the 25th floor.

 

Installation of internal heating systems - installation of the pipe on the 1-25th floors, horizontal wiring on the 1-8th floors.

 

Installation of internal water supply and sewage systems - installation of a water supply pipe to the 25th floor, sewage is completed to the 23rd floor.

 

Floor screed is made on the basement-6th floor. Works are carried out on the 7th (80%) and 8th (10%) floors.

 

The construction of facades (insulation of balconies), ventilation ducts and installation of elevators continues.

 

House number 12:

 

The monolithic frame is made on floors 13-14. On section No. 1 - reinforcement and concreting of vertical elements of the 14th floor, on sections No. 2 and No. 3 reinforcement and concreting will be performed on the 13th floors.

 

The construction of walls and partitions is carried out in section 1 on the basement (95%), on the 1st floor (40%); in section number 3 - on the 2nd floor (95%).

 

House number 13:

 

The construction of the main pile field, including piles of tower cranes, has been completed.

 

The base plate is made on all 3 sections. The construction of vertical structures of the frame on the basement and the 1st floor continues (75% completed).

 

The basement floor was overlaid in section 3.

 

"Traditsia" RC

 

House number 3:

 

The device of the vertical elements of the 25th floor.

 

Brickwork on the ground floor, on the 17-21st floors.

 

Installation of window structures made on the 2-8th floors.

 

Electrical work is performed on the 2nd-9th floors.

 

The device continues to arrange the piping for heating and water supply on the 2nd to 4th floors.

 

Installation of sanitary risers continues.

 

Plaster walls - in the 5th floor.

 

House number 2:

 

The device continues the vertical elements of the 1st floor.

 

 

"Malachite" RC

 

The following works are being carried out at the construction site of house No. 3:

 

Device monolithic frame:

 

section 301 - 97% (concreting of the floor slab of the 25th floor continues);

 

sections 302-303 - 100%;

 

Section 304 - 99% (work is ending on the construction of a slab of a flight of stairs on the technical floor).

 

The basement waterproofing device is almost complete:

 

section 301 - 98%;

 

sections 302-303 - 98%;

 

section 304 - 95%.

 

The device walls and partitions:

 

section 301 - 58% (laying on the 14th floor);

 

sections 302-303 - 100%;

 

section 304 - 58% (laying on the 17th floor).

 

Installation of window structures:

 

section 301 - 45% (10th floor);

 

sections 302-303 - 99% (work on the glazing of technological openings for the supply of materials is being completed);

 

Section 304 - 42% (9th floor).

 

Backfilling - it remains to perform a vertical layout for the final improvement:

 

section 301 - 90%;

 

sections 302-303 - 90%;

 

section 304 - 90%.

 

House number 4:

 

Works on the device of a ditch are performed. Concreting of the slab of the basement on section 404 is in progress.

 

Work is being done on the device of the pile field of sections 405 and 406: the drilling of piles continues.

 

 

"Nyvky Park" RC

 

House number 1:

 

Device monolithic frame:

 

in sections A, B and C the parapets are finished.

 

The device walls and partitions:

 

section A - the 16th floor in the work, section B - the 13th floor in the work, section C - the 12th floor.

 

The installation of window structures continues (in the 8th floor).

 

The installation of internal engineering continues.

 

Work continues on interior decoration: floor screed and plaster on the 4th-5th floor.

 

Began roofing in section A.

 

House number 2:

 

Device monolithic frame:

 

Section D - the device of parapets on the roof, Section D - the device of the floor slab of the 16th floor.

 

The device walls and partitions:

 

Section G and D - 5th floor.

 

The installation of window constructions continues (in the 1st and 2nd floors).

 

House number 3:

 

In section G, work is underway to arrange the vertical elements of the 1st floor; in sections D and G, work is underway to arrange the basement vertical structures.

 

House number 4:

 

The construction of the foundation slabs begins on sections B, C, E.

 

 

"Otradny" RC

 

House number 1:

 

The monolithic frame device is 77% complete.

 

Brick wall: 1st floor - 100%, 2nd floor - 96%, 3rd floor - 91%, 4th floor - 96%, 5th floor - 90%, 6th floor - 96% , 7th floor - 40%, 8-9th floors - 50%.

 

Installation of window structures continues: work is underway on the 3rd floor.

 

Backfilling is in progress: the work is 90% complete.

 

Works on plastering of walls continue - works are carried out on the 2nd floor.

 

House number 2:

 

The monolithic skeleton device is 72% complete.

 

Work is underway on the construction of brickwork: on the 1st and 2nd floors, the work was done at 100%, on the 3rd floor - 80%, on the 4th floor - 60%.

 

Work has begun on the device waterproofing basement.

 

House number 3:

 

Reinforcement and concreting performed at 29% (in the 6th floor).

 

Work has begun on the device waterproofing basement.

 

House number 4:

 

Base plate is made. Ground floor is reinforced. The technological break continues. In the 20th of May construction work will resume.

 

 

"Teremki" RC

 

On the I stage of the future complex is the construction of the slab of the 2nd floor. Work begins on the device vertical elements of the 2nd floor.

 

On the second stage of construction until May 18, work will continue on testing the piles.