The painting of facade has begun in the house number 2 of "Malachite" RC

  • 23/09/2015

House number 2 of the residential complex "Malachite" very soon will play with all shades of this precious mineral and will acquire the appearance of the finished structure - work on the painting of the facade has begun.

The glazing of the house has already been completed. The plastering work inside the premises, as well as the floor screed, was performed at the level of the 16th floor, electrical and plumbing wiring was done on the 15th floor inclusive. In the near future, work will begin on the improvement and landscaping of the territory.

The commissioning of the house number 2 is scheduled for the IV quarter of 2015.

The last unsold apartments are waiting for their owners. Managers of the sales department of the residential complex "Malachite" are ready to acquaint the future new settlers with the options of layouts and hold them inside the already finished apartments. For more information, contact the sales department: (044) 200‒0277.