PROGRESS OF CONSTRUCTION AS OF 29.11.17
PROGRESS OF CONSTRUCTION AS OF 29.11.17
29 november 2017

PROGRESS OF CONSTRUCTION AS OF 29.11.17:

RC «Volodymyrskyi» 
  
Installation of the frame of the 5th floor at the level. +17.300 – 25%  
Installation of brickwork – 26% 
Installation of water proofing – 0,5%
Installation of lightning protection system - (0.07%) 
Installation of the internal electric network  –  commenced (0,05%) 
 
RC «Syretski Sady» 
  
Building No. 1 
Section 1: At the level of the 7th floor – concrete works for walls and pillons.
Section 2: slab over 5the floor has been poured. 

Building No. 2 
concrete works for walls at ground floor. 

Building No 3 
Clearing of territory is completed. 

Building No 4 
The installation of test piles has been completed – 100% 

RC «Yaskravyi» 

Building No.6 
Section No.1:
Construction of 15th floor completed.
Readiness of the vertical of 16th floor – 20%
Waterproofing o basement – 80%
Heat insulation of basement – 80% 
Section No.2:
Construction of 13th floor completed.
Waterproofing o basement – 80%
Heat insulation of basement – 80 %
Section No. 3:
Floor/ceiling slab of 12th floor – 100 % 
Readiness of the vertical of the 13th floor – 45%
Waterproofing o basement – 80 %
Heat insulation of basement – 80 %

Building No.7  
Installation of the monolith frame of section No.1 – 100 % 
Installation of the monolith frame of section No.2 – 100 % 
Installation of walls and partial walls, brickwork 1 section – 71%
Installation of walls and partial walls, brickwork 2 section – 36%
Brick works on the roof – 70%
Installation of ventilation ducts in sections  1 and 2 – 100% 
Ventilation and smoke exhausting system– 24% 
Plumbing works – 30%
Electrical works – 24% 
Low-current systems – 14% 
Plastering of walls in sections 1 and 2 – 8%
Installation of screed in sections1 and 2 – 15%
Installation of windows: section 1 – 53 % (2-19 floors),
section  2 – 25 % (2-8 floors). 

RC «Ozernyi Hai Gatne » 

Building No. 2
Installation of basement – 100%
Waterproofing o basement – 100%
Installation of walls – 100% (brickwork at mansard floor).
Installation of monolith floor/ceiling slabs – 100%
Installation of partitions – 100%
Roof – 80%
Façade – 80 %
Internal finishing – 80 %
Improvement of the adjoining territory – 40 %  
   
Building No. 3
Installation of basement – 100 %
Waterproofing o basement walls– 100 %
Installation of walls – 100 %
Installation of monolith floor/ceiling slabs – 100 %
Installation of partitions – 100 %
Roof – 78,5 %
Façade – 90%
Improvement of the adjoining territory – 35 %

Building No. 4
Installation of the basement completed – 100 %
Waterproofing of basement completed 100 %
Installation of walls – 98 % (brickwork at mansard floor).
Installation of monolith floor/ceiling slabs – 100 %
Installation of partitions – 100 % 
Roof – 30 %
Façade  – 50 %
Internal finishing - 40 % 
Improvement of the adjoining territory – 5 %

Building No. 5
Installation of the basement – 100 %
Waterproofing of basement 100 %
Installation of ceilings – 70 % (7th floor)
Installation of monolith floor/ceiling slabs – 70 %
Installation of partitions – 60 %

RC «Demiivka» 

Building No. 2
On the roof: works on the arrangement of parapets and reinforced concrete structures for machine rooms completed.
Installation of ventilation blocks completed.
Installation of stairwells completed.
Installation of water supply, heating and domestic sewage pipes is ongoing – 68%
Readiness of monolith structures of entrances – 99 %.
Installation of windows up to the 9th floor completed.
Installation of windows at 10-15-floors is in progress.
Installation of horizontal piping of heating and water supply systems: 13 floor.
Electrical works: 13 floor. 
heating and water supply systems completed in 1 and 2 zones. 
Domestic sewage  - 95% 
Installation of risers (vertical) - 100% 
Installation of pipes (horizon) at the level of the 14th floor. 
Installation of electric wiring at the level of the 8th floor. 
Roofing works are in progress. 

RC «Parkovy Ozera» 

Building No. 11
Installation of external wells and partitions (brickwork) – 100%
Installation of internal wells and partitions – 100%
Installation of roof – 100%
Installation of window structures – 100%
Installation of facades – 100%
Plastering of walls – 100%
Plumber works – 89%
Screed works – 100%
Installation of the system of internal mains – 95%
Low-current systems – installation of electric meters are being completed - 96 %
Ventilation and smoke exhausting – 97 %
Installation of elevators – 93 %

Building No. 12 
Installation of monolith frame is carried out at the roof, parapets and covers (100%)
Installation of walls and partitions is carried out at 18-26 floors (76%)
Installation of ventilation ducts – 78%
Installation of window structures –17-22 floors (59%)
Plumber works  – vertical works up to 26 floor (48%)
Electric installation works – wiring at 12 floor completed (33%)
Low-current installation is carried out at 2nd floor (19%)
Plastering of walls is carried out at 10-11 floors (39%)
Finishing of the places of common use is completed at the 2nd floor (4%)

Building No.13
Installation of monolith frame is carried out at the 23-24 floors (85%)
Installation of walls and partitions is carried out at 2-4 floors (10%)
Installation of ventilation ducts is carried out at the 21-23 floors (70%) 

RC «Tradition»

Building No.2
Installation of the floor/ceiling slab at 28th floor;
Brickworks at 18-22 floors;
Installation of window structures at the 7th floor; 
Plastering - 2-3 floors; 
Plumber/ electrical works – 2-3  floors.

Building No. 3
Façade works – 85 %
Plumber works – 95%
Installation of heat meters of 1st and 2nd zones completed.
Readiness of electric wiring – 90 %
Improvement of adjoining territory – 70 %
External networks – 100 %
Roof – 85 %
Internal finishing of apartments – 80 %
Installation of elevator equipment – 80%   

RC «Malakhit» 
  
Building No. 3
Sections 302-303 – internal finishing works completed from 2 to 9 floor - 100 %
Commenced to improvement of recreation zone at the roof - 70%
Works on installation of external engineer networks are in progress:
- household sewage К1 – 99 %
- rain sewage К2 – 100 %
- water supply В1 – 99%
- electric wiring - 99%

Building No. 4
Monolith frame, section 404 – 100 %
Brickworks on the first and sixth floors, section 404 – 100%
Installation of vertical reinforced concrete structures at section 405-406, level-0.100
Parking П1 – ceiling slabs 100%
Parking П2 - ceiling slabs 100%
Section 401 basement- 100 %, level – 3.100
Section 402-403 – concrete works for vertical structures of the first floor.

RC «Nyvky-Park» 

Building No.1
Installation of monolith frame completed.
Installation of walls and partitions completed.
Installation of window structures completed.
Installation of internal engineering networks is in progress.
Pouring of screed and plastering completed.
Internal finishing works in premises are in progress:
Installation of doors completed.
Installation of façade completed for 90%.
Works on commissioning the elevators are in progress.
Installation of still structures of entrance groups are in progress.
Installation of external engineering networks are in progress.
Works on improvement of adjoining territory within the yard are in progress.

Building No.2
Installation of monolith frame completed.
Installation of walls and partitions completed.
Installation of window structures completed.
Installation of internal engineering networks is in progress.
Pouring of screed and plastering completed.
Installation of doors completed.
Internal finishing works in premises are in progress:
Works on commissioning the elevators are in progress.
Installation of façade completed for 75%.
Works on improvement of adjoining territory within the yard are in progress.

Building No.3
Sections Г, Д, Ж – works on installation of monolith frame of the 17th floor are in progress.
Brickwork for walls: works are carried out on 9-12-floor sections Г, Д, Ж.

Building No.4
Sections Е, Б, В Ж – works on installation of monolith frame of the 14th floor are in progress.
Brickwork for walls: works are carried out on 3-7- floor sections Е, Б, В.

Building No.5
Testing of the bearing capacity of piles.

Building No.6
Pit works. 

RC «Vidradnyi» 

Building No.1
Installation of monolith frame completed 100% 
Brickworks for external walls completed 100% 
Paint works on façade are in progress - 95% 
Plastering works completed 100% 
Screed completed 100% 
Finishing works at МЗК- 1st floor 
Finishing works – ground floor are in progress 
Roofing is in progress  - 90%          
Improvement of territory is in progress - 65% 

Building No.2
Installation of monolith frame completed 100%. 
Façade works on the roof are in progress. 
Roofing is in progress 70% 
Plastering works on the 5th floor. 
Electrical and plumbing works on the 7th floor are in progress. 
Cement and sand screed on the 5th floor. Works are in progress 

Building No.3 
Reinforcing and pouring completed up to the 17th floor. 
Brickworks on 10,11, 12, 13 floors are in progress. 

Building No.4 
Reinforcing of the slab on the 10th floor is in progress. 
Brickworks on the 4th floor is in progress. 

Building No.5
Reinforcing and pouring for vertical structures on the 3d floor are in progress. 

RC «Teremky» 

1 stage – installation of vertical structures of the 24th floor. 
Brickworks completed 100% up to 17th floor inclusive, 18th floor – brickworks are in progress. 
2 stage 2nd section - installation of vertical structures of the 3d floor. 
3 section – installation of the slab elements on the 2nd floor. 
3 stage – testing of piles completed, installation of basement for crane. Preparation of the design project for works.