PROGRESS OF CONSTRUCTION AS OF 01.06.18
PROGRESS OF CONSTRUCTION AS OF 01.06.18
1 june 2018
Progress of construction as of 01.06.18


RC Volodymyrskyi

Completion of works for installation of frame structure - 5th to 9th floors. Works on the 11th floor have been commenced.
Active brickworks – basement from 1st to 4th floors
Commencement of works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system

RC Syretski Sady 

Building No. 1
Section 1: active works on the roof.
Section 2: fencing of balconies.
Windows – 8th floor


Building No. 2
Works on vertical element on the roof and parapet
Brickworks – 1-3 floors


Building No. 3
Installation of vertical structures of the 1st floor.

Building No.4
Installation of vertical structures on the 9th floor is in progress.
Brickworks – 2nd and 3d floor.


RC Yaskravyi

Building No.6
Completion of works for monolith frame
Active installation of walls, partitions, brickworks
Commenced works: Plumbing and electric wiring works, installation of window structures

Building No. 7
Final stage of completion of works on installation of walls, partitions, brickworks and window structures.
Active works for plumbing, electric wiring, installation of ventilation and smoke exhaust systems, wall plastering, arrangement of screed and installation of elevators and decoration of the general use premises.
Brickworks o the roof and entrance group.

RC Demiivka 

Plumbing works: – 1st to 20th floors.
Installation of heating radiators is being completed.
Screed: basement, 1st to 20th floors, balconies.
Wall plastering: basement, IHSU, 1st to 20th floors.
Low-current systems – 1st to 20th floors and in basement.
Installation of window structures – 1st to 12th floors

Preparation works for waterproofing are ongoing.
Installation of doors in apartment and in basement.
Acrive decoration works inside apartments.
Completion of electric wiring and heat supply networks.

RC Parkovi Ozera

Building No. 12
Completion of walls and partitions, wall plastering and installation of window structures
Active plumbing and electric wiring works are in progress.
Low-current systems, ventilation and smoke-exhaust systems, decoration of the general use premises, installation of elevators are in progress.
Façade installation, screed on the roof are in progress.

Building No. 13
Installation of walls and partitions, brickworks
Installation of window structures – in progress
Plumbing and electric wiring works, wall plastering and screed have been commenced.

RC Ozernyi Hai Gatne

Building No.2
Completion of works for internal decoration and development of adjoining territory.


Building No. 3
Façade heat insulation and development of adjoining territory


Building No. 4
Completion of works on the roof and façade heat insulation.
Active internal decoration works and development of adjoining territory.


Building No. 5
Completion of works on installation of partitions. Active glazing works are in progress.


Building No.6
Ground excavation is completed

RC Traditsiya

Building No.2
Plastering works – floors 18, 19.
Plumbing/ electric wiring – installation of risers, water supply and electric boxes.
Screed – 23th and 25th floors.
Puttying – 11th to 16th floors
Active works on the roof, heat insulation of façade and installation of elevators are in progress.
Tiling in corridors – 14th floor
Decoration works – 11th floor
Completion of heat insulation on façade

RC Malakhit

Building No. 4
Section 405-406 – brickworks – 13th floor
Section 401 vertical element of the 7th floor.
Sections 402-403 – works on installation of ventilation ducts are in progress.
Brickworks at sections 402-403 - works on the 7th floor are ongoing.
Installation of window structures: Section 404 – 406, - from 7th to 13th floor.
Decoration works at section 404 on the floors 7, 8 and 9.
Section 405 – on the floors 1, 2 and 3.
Installation of the basement slab of P3 parking place.

RC Nyvky-Park 

Building No.1
Completion of works on development of adjoining territory.
Installation of brackets for air-conditioners is in progress

Building No.2
Completion of works on development of adjoining territory. Installation of brackets for air-conditioners is in progress

Building No.3
Brickworks for walls; works are completed except the locations where protruding platforms have been installed.
Installation of window structures is in progress at sections Д, on the 13th floor, section Ж – on 16th and 17th floors and section Г – on the 13th and 14th floors.
Works on arrangement of internal mains are ongoing.
Decoration works inside general use premises at sections Г on the 5th floor and Д on 11th floor.
Installation works for elevators in section Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of screed at sections Г on the 7th floor and section Д on the 5th floor is ongoing.
Installation of doors: section Ж – on the 5th floor and section Д – on the 4th floor.
Installation of façade is ongoing.

Building No.4
Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed. Works on the floors 14, 15, 16 and 17 at section E, Б are ongoing.
Installation of window structures: at section E on the 15th floor and section Б – on the 11th floor.
Plastering works inside general use premises: at section E - on the 7th floor and section Б – on the 2nd floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing
Installation of internal engineering systems is in progress

Building No.5
Installation of monolith frame
section A vertical structures of the 8th floor,
section E – slab over the 7th floor
section Б – slab over the 5th floor.

Building No.6
Installation of vertical elements of the basement at section Г
Installation of vertical elements of the basement at section E.
Installation of vertical elements of the basement at section Д

RC Vidradnyi

Building No.2
Water proofing on the roof are ongoing.
Electric wiring and plumbing works on the 8th and 10th floors are in progress.
Completion of façade works.
Tiling works on the floors 5, 6, 7, 14 and 15 are ongoing.
Decoration works (painting) on the basement floor, 1, 10, 11, 14 and 15 floors.
Works on arrangement of entrances and bunkers at the basement floor.
Development of the territory.

Building No.3
Brickworks are ongoing on the basement floor.
Active roofing works are ongoing.

Building No.4
Completion of concrete pouring on the 18th floor

Building No.5
Installation of vertical elements on the 16th floor

Brickworks on the floors from 5 to 13.

RC Teremky

1st stage
Brickworks for vent ducts on the roof are ongoing.
Completion of installation of windows on 24th floor. Preparation works for window installation on the 25th floor are ongoing.
Internal engineering and plumbing works are in progress. Electric wiring works inside the building are in progress (13th floor).
Plastering works inside the turn-key apartments on the 11th and 13th floors are ongoing.
Pouring of floor screed on the 2nd, 3d and 5th floor.

Stage 2, section 2 – slab over the vertical elements on the 18th floor is in progress. Brickworks on the 10th to 12th floors are ongoing
Stage 2, section 3 - slab over the vertical elements on the 18th floor is in progress. Brickworks on the 10th to 12th floors are ongoing.
Stage 3, section 4. Pouring of slabs over the vertical elements of the 7th floor is ongoing.
Stage 3- section 5 – Pouring of slabs over the vertical elements of the 5th floor is ongoing.
Stage 3- section 6 – Pouring of slabs over the vertical elements of the basement is in progress.