PROGRESS OF CONSTRUCTION AS OF 02.08.18
PROGRESS OF CONSTRUCTION AS OF 02.08.18
2 august 2018
PROGRESS OF CONSTRUCTION AS OF 02.08.18

RC "Volodymyrskyi"

Completion of works for installation of frame structure - 5th to 15th floors. Slab over the 16th floor is in progress

Completion of brickworks – basement and from 1st to 7th floors.

Works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system are ongoing.


RC “Syretski Sady” 



Building No. 1

Installation of windows and balconies – from 9th to 16th floors.

Rises for sewage, heating and water supply – 1st to16th floors Installation of water supply mains – 2nd floor;

Electric wiring works - 2nd floor.

Plastering works are ongoing on the 2nd floor.

Pouring of basements for entrance groups has been commenced.

Building No. 2 
Brickworks – 1st to 8th floor.

Building No. 3 
Installation of frame structures – 1st to 7th floor.

Building No.4
Installation of frame structures – 14th floor

Brickworks – 1st to 86th floor

Building No.5

Excavation is completed.

Sample piles have been drilled.


RC “Yaskravyi”


Building No.6 
Active works on installation of walls, partitions, brickworks on the roof are in progress. 
Plumbing and electric wiring works, installation of window structures and elevators, brickworks on the roof and entrance group have been commenced,

Building No. 7 

Final stage of installation of window structures, wall plastering, arrangement of screed.
Active works on plumbing, electric wiring, installation of low-current systems, ventilation and smoke exhaust systems, installation of elevators and finishing of the general use premises, façade works and roofing, works at entrance group.

Brickworks on the roof, development of territory, installation of walls and partitions, brickworks have been commenced


RC "Demiivka" 

Completion of electric wiring and plumbing works, installation of ventilation and fume exhaust systems, lighting protection system.
Adjustment of hardware is conducted 
Finishing works and installation of drains is about to be completed. Paint works on the floor of staircases.


RC “Parkovi Ozera” 

Building No. 12 
Completion of works on installation of window structures, plumbing, low-current and electric wiring works, ventilation and smoke-exhaust systems, installation of elevators, decoration of the general use premises, wall plastering, façade works and roofing; entrance group and development of adjoining territory are in progress.


Building No. 13 
Completion of works on installation of walls and partitions, brickworks, window structures.

Active works for roofing, installation of elevators and entrance groups.

Plumbing, electric wiring, low-current systems, wall plastering, i
Commenced: screed, façade thermal insulation and finishing, ventilation and smoke exhaust systems

RC "Ozernyi Hai Gatne" 

Building No.2
Completion of works for internal decoration and development of adjoining territory


Building No. 3
Façade heat insulation and development of adjoining territory 


Building No. 4
Active works for internal decoration.

Building No. 5
Completion of works on glazing.
Insulation of façade is in progress
Commencement of works on internal finishing.

Building No.6
Basement slab has been poured, works on installation of reinforcement frame have been commenced.


RC “Traditsiya” 

Building No.2

Plumbing/ electric wiring – works at IHSU.
Puttying of GUP –25th floor

Completion of works on the roof and installation of elevators.
Active finishing works inside apartments and development of the territory are in progress.

Building No.4
Slab over the 2nd floor. Water proofing and thermal insulation of the basement are in progress.

RC “Malakhit”

Building No.4
Section 401 – slab over the 14th floor 
Sections 402-403 – installation of window structures – 6-8 floors. Plastering works – 2-4 floors. Roofing is in progress.

Sections 405-406 – finishing works are ongoing:
Section 404 final decoration (tiling and painting) – 1-8 floors. Section 405 – primary and final decoration - from 1st to 13th floor. Section 406 – primary and final decoration - from the 1st to 10th floors.

Works on waterproofing of parking areas П1-П4 are ongoing.


RC “Nyvky-Park” 

Building No.3
Installation of window structures at the staircases in all sections.


Works on arrangement of internal mains are ongoing: 
Section Г –7th floor, section Д –17th floor, section Ж –17th floor.

Finishing works at GUP in section Г are carried out on the 17th floor and section Д on the 15th floor.

Installation works for elevators in section Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.

Roofing is in progress.
Installation of screed at section Г on the 13th floor

Installation of doors: section Ж and Д – on the 15th floor.
and section Д – on the 13th floor, section Г – on the 3d floor.
Installation of façade is ongoing. 

Building No.4

Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed.

Works on installation of window structures: section Е – on the 15th floor, section Б – on the 12th floor and section В – on the 11th floor.
Plastering works at GUP: section Е – on the 8th floor, section Б - on the 7th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed - section Б – 10th floor,

Installation of internal engineering systems is in progress: section Б – 14th floor, section B – on the 12th floor.
Installation of elevators is ongoing.

Building No.5
Installation of monolith frame
section A vertical structures of the 14h floor, 
section E – vertical structures of the 13th floor
section Б – slab over the 12th floor.

Brickworks on the floors 2, 3, 4 of sections A and 2, 3, 4, 5 floors and basement of section Е.
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.


Building No.6
Installation of the slab over the 3d floor at section Г
Installation of the slab over the 3d floor at section E.
Installation of vertical elements of the 3d floor at section Д*

RC “Vidradnyi” 

Building No.2 
Decoration works inside apartments on the floors 1, 5, 6, 7 and 8 are ongoing.

Building No.3 
Completion of works on roofing and installation of metal and plastic windows.

Brickworks on the roof and façade installation are in progress.

Building No.4 

Completion of works on roofing and installation of metal and plastic windows.

Brickworks on the roof and façade installation are in progress

Building No.5 

Reinforcing of walls on the 18th floor is in progress.

Brickworks on the floors 8, 10, 14 and 16.

RC “Teremky” 


1st stage.
Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress.
Plastering of façade is ongoing.
Internal mains and plumbing works are in progress.
Electric wiring inside the building on the 22th floor is in progress.
Plastering of walls inside turn-key apartments on the 22nd floor.

Stage 2, section 2 – Brickworks on the 17th to 22nd floors are ongoing. Installation of windows – on the 9th floor.
Stage 2, section 3 – slabs over the vertical elements on the 25th floor.

Brickworks on the 16th to 19th floors are ongoing. Installation of windows – on the 14th floor.
Stage 3, section 4. Slab over the vertical elements of the 11th floor is completed.
Stage 3- section 5 – Slab over the vertical elements of the 11th floor is completed. 
Stage 3- section 6 – Slab over the vertical elements of the 9th floor is in progress.