PROGRESS OF CONSTRUCTION AS OF 03.07.18
PROGRESS OF CONSTRUCTION AS OF 03.07.18
3 july 2018
Progress of construction as of 03.07.18

RC "Volodymyrskyi"

Completion of works for installation of frame structure - 5th to 12th floors. Works on the 13th floor have been commenced. Active brickworks – basement from 1st to 5th floors
Commencement of works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system


RC “Syretski Sady”

Building No. 1
Works on the roofing are about to be completed.
Installation of window structures and balconies– from 8st to 14th floors .
Plumbing works have been commenced.

Building No. 2
Monolith elements are being completed.
Brickworks – 4-5 floors.

Building No. 3
Installation of vertical structures on the 4nd floor.

Building No.4
Installation of vertical structures on the 12th floor is in progress.
Brickworks – 5th floor.


RC “Yaskravyi”

Building No.6
Active works on installation of walls, partitions, brickworks are in progress.
Plumbing and electric wiring works, installation of window structures and elevators are commenced,
Brickworks on the roof.

Building No. 7
Final stage of works for installation of walls, partitions, brickworks and window structures.
Active works on plumbing, electric wiring, installation of ventilation and smoke exhaust systems, wall plastering, arrangement of screed and installation of elevators and decoration of the general use premises, brickworks on the roof.
Works on arrangement of entrance group are commenced.


RC "Demiivka"

Plumbing works are being completed: – 1st to 20th floors.
Installation of heating radiators is being completed.
Screed: 18th to 20th floors, balconies.
Wall plastering: basement, IHSU, 1st to 20th floors.
Low-current systems – 1st to 20th floors and in basement.
Installation of window structures is completed – 1st to 12th floors. Installation of aprons is in progress
Installation of heat insulation layer, decorative layer and painting of balcony walls in apartments and on main façade. Preparation works for water proofing. Installation of apartment entrance doors.
Active decoration works inside apartments.
Completion of works on electric wiring and heat supply networks.


RC “Parkovi Ozera”

Building No. 12
Completion of walls and partitions, wall plastering and installation of window structures, plumbing and electric wiring works, installation of screed and elevators.
Ventilation and smoke-exhaust systems, decoration of the general use premises, entrance group and development of adjoining territory.

Building No. 13
Active installation of walls and partitions, brickworks,
window structures.
In progress – roofing works and entrance group.
Plumbing, electric wiring, low-current systems, wall plastering are in progress.
Commenced: screed, façade insulation, installation of elevators.


RC "Ozernyi Hai Gatne"

Building No.2
Completion of works for internal decoration and development of adjoining territory \

Building No. 3
Façade heat insulation and development of adjoining territory

Building No. 4
Completion of works on the roof and façade heat insulation.
Active internal decoration works and development of adjoining territory.


Building No. 5
Completion of works on glazing.
Active works on internal decoration.
Works on façade insulation have been commenced.


Building No.6
Installation of drainage system. Preparation works on pouring the basement have been commenced.

RC “Traditsiya”

Building No.2
Plastering works – inside apartments
Plumbing/ electric wiring – installation of water supply raises and electric boxes + IHSU.
Puttying – 22nd to 23d floors
Works on the roof as well as heat insulation of façade and installation of elevators are being completed.
Tiling in corridors – 19th, 20th floors
Active decoration works inside apartments.
Completion of façade heat insulation.
Works on development of adjoining territory have been commenced.

RC “Malakhit”

Section 401 vertical element of the 10th floor.
Sections 402-403 – installation fo window structures – 2-3 floors.
Brickworks at sections 402-403 - works on the 8th floor are being completed.
Sections 404 – 406 – competition of installation for window structures: from 7th to 13th floor.
Decoration works at section 404 on the floors 7, 8 and 9.
Section 405 – on the floors from the 1st to 10th. Section 406 – from 1st to 3d floors.

RC “Nyvky-Park”

Building No.3
Brickworks for walls; works are completed except the locations where protruding platforms have been installed.
Installation of window structures is in progress at sections Д, on the 16th floor, section Ж – on 17th, and section Г – on the 16th and 17th floors.
Works on arrangement of internal mains are ongoing:
Section Г – the 5th floor, section Д – the 16th floor, section Ж – the 17th floor.
Decoration works at section Г on the 12th floor and section Д on the 14th floor are in progress.
Installation works for elevators in section Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of screed at sections Ж on the 15th floor and section Д on the 15th floor is ongoing.
Installation of doors: section Ж and Д – on the 8th floor.
Installation of façade is ongoing.

Building No.4
Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed. Works on the floors16 to 17 at section Б and B are ongoing.
Works on installation of window structures: section Е – on the 14th floor, section Б – on the 1st floor and section В – on the 11th floor.
Plastering works at general use premises: section Е – completed up to 8th floor, section Б - on the 5th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Decoration works inside general use premises on the 4th floor are ongoing.
Installation of screed - section E – 12th floor, section Б – 4th floor.
Installation of internal engineering systems is in progress: section E – 12th floor, section Б – 7th floor.
Installation of elevators is ongoing.

Building No.5
Installation of monolith frame
section A vertical structures of the 12th floor,
section E – vertical structures of the 11th floor
section Б – slab over the 9th floor.
Brickworks on the floors 2, 3, 4 of sections A and Е.
Water proofing of basement at sections А, Б and Е.


Building No.6
Installation of vertical elements of the first floor at section Г
Installation of vertical elements of the first floor at section E.
Installation of vertical elements of the basement at section Д*

RC “Vidradnyi”

Building No.2

Electric wiring and installation of lighting devices on the basement are in progress.
Decoration works inside “turn-key” apartments.
Development of adjoining territory.


Building No.3
Completion of brickworks.
Active roofing works are ongoing.
Installation of window structures is being completed.

Building No.4
Installation of window structures is ongoing.

Building No.5
Reinforcing of parapet on the 17th floor is in progress.
Brickworks on the floors from 3, 7, 12 and 14.


RC “Teremky”

1st stage.
Completion of installation of windows up to the 24th floor.
Heat insulation of the building and works on the roof are in progress.
Internal mains and plumbing works are in progress.
Electric wiring inside the building on the 19th floor is in progress.
Plastering of walls on basement, inside turn-key apartments on the 19th floor and general use premises on floors 6, 7, 8, 12 is ongoing.
Stage 2, section 2 – pouring of slabs over the vertical elements on the 22th floor is in progress. Brickworks on the 10th and 16th floors are ongoing. Installation of windows – 2nd to 8th floors
Stage 2, section 3 - slab over the vertical elements on the 22th floor is in progress. Brickworks on the 10th to 16th floors are ongoing.
Stage 3, section 4. Pouring of vertical elements of the 8th floor is ongoing.
Stage 3- section 5 – Pouring of slabs over the vertical elements of the 8th floor has been commenced.
Stage 3- section 6 – Pouring of vertical elements of the 4th floor is in progress.